HomeMy WebLinkAbout2007-07-11 PACKET 04.C.REQUEST OF CITY COUNCIL ACTION COUNCIL AGENDA MEETING ITEM # DATE 07/11/07 PREPARED BY Engineering Jennifer Levitt ORIGINATING DEPARTMENT STAFF AUTHOR COUNCIL ACTION REQUEST Consider approval of Change Order #3 for the Silverwood 1 and 2 nd Additions. STAFF RECOMMENDATION Approve the change order which provides for additional work needed to repair major washouts at three storm pond inlets caused by concentrated flow of stormwater runoff behind the inlets. It also provides for the installation of riprap to the bottom of the pond below the 12" trail culvert. ADVISORY COMMISSION ACTION ❑ PLANNING ❑ PUBLIC SAFETY ❑ PUBLIC WORKS ❑ PARKS AND RECREATION ❑ HUMAN SERVICES /RIGHTS ❑ ECONOMIC DEV. AUTHORITY El DATE REVIEWED APPROVED DENIED ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ SUPPORTING DOCUMENTS ® MEMO /LETTER: Brian Kelley, June 21, 2007 ❑ RESOLUTION: ❑ ORDINANCE: ❑ ENGINEERING RECOMMENDATION: ❑ LEGAL RECOMMENDATION: ® OTHER: Change Order #3 ADMINISTRATORS COMMENTS Date COUNCIL ACTION TAKEN APPROVED Fn E� . 2335 Highway 36 W St, Paul, MN 55113 Tel 651- 636 -4600 Fax 651 -636 -1311 www.hone5troo.col➢ June 21, 2007 Bonestroo Jennifer Levitt City of Cottage Grove 8635 West Point Douglas Road South Cottage Grove, MN 55016 -3318 Re: City of Cottage Grove, Minnesota Silverwood 1" and 2" Additions City Project No.05222 File No, 000048 - 05222 -0 Change Order #3 Dear Jennifer: Transmitted with this letter are four (4) copies of Change Order No. 3 for the Silverwood 1" and 2 ° Additions Project. Also enclosed are copies of the contractor's invoices and supporting information. This Change Order provides for additional work needed to repair major washouts at three storm pond inlets caused by concentrated flow of stormwater runoff behind the inlets. It also provides for the installation of riprap to the bottom of the pond below the 12" trail culvert. As always, please feel free to contact me if you have any questions or concerns about this project. I can be reached on my mobile phone at: (651) 324 -5586 or by email at: brian.kelley @bonestroo.com Yours Very Truly, Bonestroo Brian M. Kelley Construction Supervisor Enclosure Date ECA St. Paul St. Cloud Rochester Milwaukee Chicago 7 i a ®� Bonestroo Owner City of Cottage Grove, 7516 80th Street South, Cottage Grove, MN Date June 20, 2007 Contractor', Three Rivers Construction, Inc, 15001 Hudson Road, P O Box 206, Lakeland, MN 55043 Bond Company. Federal Insurance Co., 15 Mountain View Rd., Warren, NJ 07061 Bond No 8204 -57 -5) CHANGE ORDER NO. 3 SILVERWOOD 1ST AND END ADDITIONS UTILITY, STREET, AND STREET LIGHTING IMPROVEMENTS CLIENT PROTECT NO 05222 BONESTR00 FILE NO 000048- 05222 -0 Description of Work This Change Order compensates the Contra-'or for non - warranty emergency erosion repaRs. No. 1 2 3 4 Item Contract Unit Quantity Unit Price Total Amount CHANGE ORDER NO. 3 EMERGENCY EROSION REPAIRS ON 5/8/2007 LS 1 $2,791 17 $2,791,17 EMERGENCY EROSION REPAIRS ON 5/9/2007 LS 1 $2,745,45 $2,745,45 EMERGENCY EROSION REPAIRS ON 5/10/2007 LS 1 $3,711,90 $3,711.90 EMERGENCY EROSION REPAIRS ON 6/14/2007 ES i $6,817.09 $6,817,09 TOTAL CHANGE ORDER NO. 3: $16,065.61 4806222 -00O3 xhs Amount Orders Contract Amount (including this change order) CHANGE IN CONTRACT TIMES Original Contract Times: Substantial Completion (days or date): Ready for final Payment (days or date): Increase of this Change Order: Substantial Completion (days or date): Ready for final Payment (days or date): Contract Time with all approved Change Orders: Substantial Completion (days or date): Ready for final Payment (days or date): Recommended for Approval by: BONESTR00 Approved by Contractor: THREE RIVERS CONSTRUCTION, INC. f Date cc: Owner Contractor Bonding Company Bonestroo & Assoc. $1,249,413.42 $13,701.62 $16,065.61 $1,279,180.65 Date: Approved by Owner: CITY OF COTTAGE GROVE Date Recommended for Approval CITY OF COTTAGE GROVE City ngineer Date: � ZZ-IC 480522MCO3 -x1,