HomeMy WebLinkAbout2008-11-05 PACKET 04.C.REQUEST OF CITY COUNCIL ACTION COUNCIL AGENDA
MEETING ITEM #
DATE 11/05/08
PREPARED BY Engineering Jennifer Levitt
ORIGINATING DEPARTMENT STAFF AUTHOR
COUNCIL ACTION REQUEST
Consider adoption of a resolution approving final payment in the amount of $10,604.25 to Keys
Well Drilling Company for the Deep Well No. 10 Maintenance.
STAFF RECOMMENDATION
Adopt resolution and final payment. The contractor, Keys Well Drilling Company in
accordance with the contract plans and specifications, has satisfactorily completed the work.
ADVISORY COMMISSION ACTION
❑ PLANNING
❑ PUBLIC SAFETY
❑ PUBLIC WORKS
❑ PARKS AND RECREATION
❑ HUMAN SERVICES /RIGHTS
❑ ECONOMIC DEV. AUTHORITY
DATE REVIEWED APPROVED
DENIED
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
❑
SUPPORTING DOCUMENTS
® MEMO /LETTER: Richard Foster, October 23, 2008
® RESOLUTION:
❑ ORDINANCE:
❑ ENGINEERING RECOMMENDATION:
❑ LEGAL RECOMMENDATION:
® OTHER: Request for payment
ADMINISTRATORS COMMENTS
3
7 jt >/c '1C1
City Administrato Date
COUNCIL ACTION TAKEN:
C� ` AP PROVED
-1
RESOLUTION APPROVING FINAL PAYMENT IN THE AMOUNT OF
$10,604.25 TO KEYS WELL DRILLING COMPANY FOR DEEP WELL #10
MAINTENANCE
WHEREAS, the City Engineer has certified that work has been
satisfactorily completed, and
WHEREAS, the total contract amount is $44,885.00 compared to the
original contract amount of $26,740.00.
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of
Cottage Grove, County of Washington, State of Minnesota, that $10,604.25 be
paid to Keys Well Drilling Company for the Deep Well #10 Maintenance.
Passed this 5th day of November, 2008.
Sandra Shiely, Mayor
Attest:
Caron M. Stransky, City Clerk
2335 Highway 36 w
St. Paul, MN 55113
Tel 657- 636 -4600
Fax 651- 636 -1311
www.bonestroo -corn
October 23, 2008
Ms. Jennifer Levitt
City of Cottage Grove
8635 Point Douglas Drive
Cottage Grove, MN 55016
Re: Deep Well No. 10 Maintenance
City Project No. 08273
Bonestroo File No. 000048 - 08273 -0
Dear Jennifer,
Enclosed please find four (4) copies of the 2nd and Final Request for Payment for the
Deep Well No. 10 Maintenance. The Contractor for this project is Keys Well Drilling
Company.
PROJECT REVIEW
The well pump was removed in March 2008, repaired, and reinstalled in June 2008. As
part of the project a water level monitor was installed in the well and modifications of
the master control were required. This work was completed in August 2008.
CONSTRUCTION COST OVERVIEW
The following is a summary of the Original Contract Amount and the Final Construction
costs:
Deep Well No. 10 Maintenance
Total Part 1 — Pump Repair
Total Part 2 — Level i oolvtor
Change Order No. 1
TOTAL COSTS
Original Quotation
Amount
$17,690.00
$9,050.00
$17,700.00
$44,400.00
Final Quotation
Amount
$18,135.00
$9,050.00
$17,700.00
$44,885.00
The Part 1 - Pump Repair was a little higher as two line shafts more than anticipated
needed replacement.
St. Paul
St. Cloud
Rochester
Milwaukee
Chicago
City of Cottage Grove
Deep Well No, .10 Maintenance
Page 2
October 23, 2008
Change Order No. 1 covered removal of loosened sandstone from the well cavity. When
the well pump was removed the bottom of the well was measured. The well had filled
from 283 feet to 260 feet, 23 feet of loose sandstone. It was not anticipated the well
would need to be bailed as there was no evidence of sandstone in the well discharge.
However unless the loose sandstone was removed, it is likely the well would pump
sandstone in the near future.
RECOMMENDATION
The contractor, Keys Well Drilling Company, has satisfactorily completed the work in
accordance with the contract plans and specifications. Therefore, it is recommended that
final payment of $10,604.25 be made to the Contractor and the project be accepted by
the City of Cottage Grove.
After acceptance, please distribute all copies of the Request for Payment as appropriate.
If you have any questions or require further information please contact me.
Respectfully,
BONESTROO
Richard W. Foster, P.E.
Enclosures
cc: Mike Boex
File
1 1 ►
Bone
Owner: City of Cottage Grove, 7516 80th Street S, Cottage Grove, MN 55016 -3161 Date: October 1, 2008
For Period: 6/17/2008 to 10/1/2008 Request No: 2 AND FINAL
Contractor: Keys Well Drilling Company, 1156 Homer Street, St Paul, MN 55116 -3232
CONTRACTOR'S REQUEST FOR PAYMENT
DEEP WELL NO. 10 MAINTENANCE
BONESTR00 FILE NO. 000048-08273-0
CITY PROJECT NO. 08273
SUMMARY
1 Original Contract Amount
2 Change Order - Addition
3 Change Order - Deduction
4 Revised Contract Amount
5 Value Completed to Date
6 Material on Hand
7 Amount Earned
8 Less Retainage 0%
9 Subtotal
10 Less Amount Paid Previously
11 Liquidated damages -
12 AMOUNT DUE THIS REQUEST FOR PAYMENT NO
Recommended for Approval by:
BONESTR00
Approved by Contractor:
KEYS WELL DRILLING COMPANY
Je£ y & Y Keys;; ident
Specified Contract Completion Date:
$ 26,740.00
$ 17,700.00
$ 0.00
$ 44,440.00
$ 44,885.00
$ 0.00
$ 44,885.00
$ 0.00
$ 44,885.00
$ 34,280.75
$ 0.00
2 AND FINAL $ 10,604.25
Approved by Owner:
CITY OF COTTAGE GROVE
Off' `�'6P GIB
Date:
/O —02 7— 0 z3
Recommended for Approval
CITY OF COTTAGE GROVE
City 0gineer
Date:
RFP WorCattageGmvaxls
CHANGE ORDER NO.1
1 TRANSPORT TO AND ERECT ON THE JOB SITE, A WELL RIG WITH LS 1 6000.00 1 $6,000.00
ALL NECESSARY EQUIPMENT, TOOLS, AND MATERIALS FOR
2 BAILING ACCUMULATED SAND FROM BOTTOM OF DEEP WELL CY 52 225.00 52 $11,700.00
TOTAL CHANGE ORDER NO. 1 $17,700.00
WORK COMPLETED TO DATE:
TOTAL PART I -PUMP REPAIR
Contract
Unit
Quantity
Amount
No.
Item
Unit
Quantity
Price
to Date
to Date
PART 1 - PUMP REPAIR
1
REMOVE AND REINSTALL LINE SHAFT TURBINE PUMP AND
LS
1
3600.00
1
$3,600.00
MOTOR
2
F & I NEW DISCHARGE HEAD BEARING
LS
1
150.00
1
$150.00
3
FURNISH STAINLESS STEEL PUMP HEAD SHAFT
LS
1
400.00
1
$400.00
4
10" X 10', SCH, 40, LINE SHAFT COLUMN PIPE WITH COUPLING
EA
15
530.00
16
$8,480.00
5
10" X 5', SCH, 40, LINE SHAFT COLUMN PIPE WITH COUPLING
EA
1
400.00
2
$800.00
6
10" X 10', SCH, 40 SUCTION PIPE
EA
1
360.00
1
$360.00
7
1- 11/16" X 10' STAINLESS STEEL LINE SHAFT
EA
1
320.00
1
$320.00
8
1- 11/16" X 5' STAINLESS STEEL LINE SHAFT
EA
1
230.00
$0.00
9
1- 11/16" STAINLESS STEEL LINE SHAFT COUPLING
EA
1
65.00
1
$65.00
10
BEARING RETAINER W /RUBBER BEARING
EA
1
90.00
2
$180.00
11
REMOVE EXISTING BEARING AND INSTALL NEW RUBBER
EA
17
25.00
15
$375.00
BEARING
12
INSTALL NEW STAINLESS STEEL SHAFT SLEEVE
EA
1
60.00
17
$1,020.00
13
FURNISH STAINLESS STEEL BOWL SHAFT
LS
1
325.00
1
$325.00
14
F & I COMPLETE SET OF BOWL BEARINGS
LS
1
240.00
1
$240.00
15
MACHINE BOWL AND IMPELLER AND INSTALL BRONZE WEAR
EA
4
180.00
3
$540.00
RING PER STAGE
16
REASSEMBLE BOWL ASSEMBLY
LS
1
200.00
1
$200.00
17
PAINT DISCHARGE HEAD, MOTOR, COLUMN, BOWL AND
LS
1
500.00
0.25
$125.00
SUCTION PIPE
18
SHOP TIME FOR WELL PUMP REPAIRS
HR
20
70.00
10
$700.00
19
FURNISH AND INSTALL TUBING FOR LEVEL MONITOR
LF
170
1.50
170
$255.00
TOTAL PART 1 - PUMP REPAIR
$18,135.00
PART 2 - WATER LEVEL MONITOR:
20
MODIFY DISCHARGE HEAD FOR WATER LEVEL MONITOR
LS
1
250.00
1
$250.00
CONNECTION
21
FURNISH AND INSTALL WATER LEVEL MONITOR, LEVEL
LS
1
8800.00
1
$8,800.00
INDICATOR IN PANEL, AND ALL ELECTRICAL WORK
TOTAL PART 2 - WATER LEVEL MONITOR
$9,050.00
CHANGE ORDER NO.1
1 TRANSPORT TO AND ERECT ON THE JOB SITE, A WELL RIG WITH LS 1 6000.00 1 $6,000.00
ALL NECESSARY EQUIPMENT, TOOLS, AND MATERIALS FOR
2 BAILING ACCUMULATED SAND FROM BOTTOM OF DEEP WELL CY 52 225.00 52 $11,700.00
TOTAL CHANGE ORDER NO. 1 $17,700.00
WORK COMPLETED TO DATE:
TOTAL PART I -PUMP REPAIR
$18,135.00
TOTAL PART 2 -WATER LEVEL MONITOR
$9,050.00
TOTAL CHANGE ORDER NO. 1
$17,700.00
TOTAL WORK COMPLETED TO DATE
$44,885.00
00004MB273 -0 RFP2
PROJECT PAYMENT STATUS
OWNER CITY OF COTTAGE GROVE
CITY PROJECT NO. 08273
80NESTROO FILE NO. 000048- 08273 -0
CONTRACTOR KEYS WELL DRILLING COMPANY
CHANGE ORDERS
No. Date Description Amount
1 6/11/2008 maintenance work. See Change Order. ' $17,700.00
Total Change Orders $17,700.00
PAYMENT SUMMARY
No. From To Payment Retainaae [mmnleted
1
04108/2008
06/16/08
34,280.75
1,804.25
36,085.00
2 AND FINAL
06/17/2008
10/01/08
10,604.25
lRevised Contract
44,885.00
Material on Hand
Total Payment to Date
$44,885.00
Original Contract
$26,740.00
Retainage Pay No. 2 AND FINAL
I Change Orders
$17,700.00
Total Amount Earned
$44,885.00
lRevised Contract
$44,440.00
00004M8273 -0 RFP2