HomeMy WebLinkAbout2010-04-07 PACKET 04.E.REQUEST OF CITY COUNCIL ACTION COUNCIL AGENDA MEETING ITEM # DATE 04/07/201 PREPARED BY Engineering Jennifer Levitt ORIGINATING DEPARTMENT STAFF AUTHOR COUNCIL ACTION REQUEST County Road 74 (65 Street) Road Improvement Update. STAFF RECOMMENDATION County Road 74 (65th Street) Road Improvement Update. ADVISORY COMMISSION ACTION ❑ PLANNING ❑ PUBLIC SAFETY ❑ PUBLIC WORKS ❑ PARKS AND RECREATION ❑ HUMAN SERVICES /RIGHTS ❑ ECONOMIC DEV. AUTHORITY El SUPPORTING DOCUMENTS DATE REVIEWED APPROVED DENIED ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ ❑ MEMO /LETTER: Jennifer Levitt, March 22, 2010 and Wayne Sandberg, March 18, 2010. ❑ RESOLUTION: ❑ ORDINANCE: ❑ ENGINEERING RECOMMENDATION: ❑ LEGAL RECOMMENDATION: ❑ OTHER: ADMINISTRATORS COMMENTS ity Administrator Date COUNCIL ACTION TAKEN: ❑ APPROVED ❑ DENIED OTHER From: Jennifer M. Levitt, P.E., City Engineer Date: March 22, 2010 Re: County Road 74 (65 Street) Road Improvement Update The City was notified by Washington County on March 18, 2010 in a letter from Wayne Sandberg, PE that the County was not able to financially meet the obligations of the proposed turnback at this time due to the challenging economic conditions. The County is committed to improving the road surface of 65 Street and will be performing a mill and overlay rehabilitation to the pavement. The rehabilitation will extend from CSAH 13 to CSAH 22 in Newport. This is an advantage over the turnback. In the turnback agreement the Newport section of roadway would not have seen improvements in 2010, leaving drivers with a rough road surface in that section. Under the current proposal the Newport section will see an improved driving surface as well as Cottage Grove. The County recognizes that the mill and overlay is a temporary fix to the ride quality of the road and is committed to plans for a future turnback which addresses drainage repairs, a trail extension and improved sight lines along the roadway. The County is committed to making the improvements to the pavement on 65 Street during the 2010 construction season. P, M �* March 18, 2010 Jennifer Levitt, P.E. City Engineer City of Cottage Grove 8635 West Point Douglas Road South Cottage Grove, MN 55016 -3318 RE: CR 74 Turnback and Pavement Rehabilitation Project Dear Ms. Levitt: Public Works Department Donald J. Theisen, P.E. Director /County Engineer Wayne H. Sandberg, P.E. Deputy Director /Assistant County Engineer Per our phone conversation of Monday, March 15, 2010 — this letter is notification that Washington County will perform a pavement rehabilitation project on County Road 74 (65 Street South) in 2010. The project limits will are identified as the portions of road, not recently reconstructed, between County State Aid Highway (CSAH) 13 (Hinton Avenue) and CSAH 22 (Hastings Avenue). This includes segments of road in Cottage Grove and Newport. The scope of this pavement rehabilitation project will be significantly smaller than the negotiated turnback project. The cost of the negotiated turnback, coupled with the potential need for ROW acquisition and the need to modify city utilities, pushed the project cost and schedule beyond that which can be allotted for this project at this time. We recognize the community need to address the pavement conditions, and this revised project will do so. We look forward to continuing to work with both communities, as well as the watershed district, residents and other stakeholders to develop a plan to transfer the jurisdiction of this road to the city. In the interim, we believe that a fast, low cost pavement rehabilitation project is the best and appropriate strategy to ensure the safety and economic viability of this roadway. If you have any questions, do not hesitate to contact me at 651- 430 -4339 or at wayne.sandberq�a co.washington.mn.us Sincerely, Wayne H. Sandberg, P.E. Assistant County Engineer Deputy Public Works Director C: Myra Peterson — County Commissioner Jim Schug — County Administrator Don Theisen — County Engineer / Director Ryan Schroeder — City Administrator Les Burshten — City Public Works Director 11660 Myeron Road North, Stillwater, Minnesota 55082 -9573 Phone: 651 - 430 -4300 • Fax: 651 -430 -4350 • TTY: 651 - 430 -6246 www.co.washington.mn.us Equal Employment Opportunity / Affirmative Action