HomeMy WebLinkAbout2007-08-14 EDA MinutesCITY OF COTTAGE GROVE
ECONOMIC
DEVELOPMENT
AUTHORITY
MINUTES
August 14, 2007
Pursuant to due call and notice thereof, a regular meeting of the Economic Development
Authority was held at City Hall, 7516 80th Street South, Cottage Grove, Minnesota on the 14th
day of August 2007.
CALL TO ORDER
The meeting was called to order at 7:32 a.m. by EDA President Bailey.
ROLL CALL
Members Present: Myron Bailey, EDA President
Tony Jurgens, EDA Member
Paul Poncin, EDA Member
Pat Rice, EDA Vice President
Gerry Weingartner, EDA Secretary /Treasurer
Jim Wolcott, EDA Member
Members Absent: Sara Westall, EDA Member
Others Present: Howard Blin, Community Development Director
Joe Fischbach, Management Analyst
Ron Hedberg, Director of Finance & Administrative Services
Ryan Schroeder, EDA Executive Director
Sandy Shiely, Mayor
Ken Smith, Management Analyst
Jesse Swenson, Management Analyst
Jon Avise, South Washington County Bulletin
Jack Grotkin, RJRyan Commercial Design and Construction
Al Ploeger, Mainstreet Bank
Bryan Van Hoof, CB Richard Ellis
Ben Granley, Werner Electric Supply, Minnesota
Economic Development Authority - Minutes
August 14, 2007
Page 2
APPROVAL OF MINUTES
EDA Member Jurgens clarified his comments relating to the CottageView site discussion item
from the July meeting. A motion was made by EDA Member Wolcott to approve the July 10,
2007 Economic Development Authority minutes as amended. Seconded by EDA
Secretary /Treasurer Weingartner, All Present in Favor.
DEVELOPMENT UPDATE
EDA Executive Director Schroeder gave the EDA a development update. The second contractor
for the second phase of the East Ravine utilities is on site this week. The Roundabout project
may get a slip lane on to northbound Highway 61 by Labor Day weekend. The Colonial
Commons project has been slowed because pipe conflicts the contractor was unaware of. Staff
is unaware of any prospective purchasers of the HealthEast building. The Atkinson Cemetery
project continues to progress. The sidewalk and apron were put in over the past several weeks
and the fence is being constructed this week. EDA members were also provided with an
updated building permits analysis by EDA Executive Director Schroeder.
DEVELOPMENT AGREEMENT: WERNER ELECTRIC SUPPLY OF MINNESOTA
EDA Executive Director Schroeder presented this item to the EDA. This development aligns
with the goals identified in the 2007 -2012 Strategic Plan adopted by the EDA and ratified by the
City Council in that it brings a corporate headquarters to the Industrial Park. The development
would include approximately 36,188 square feet of office space and 86,400 square feet of
warehouse space. Plans also include the option of expanding both the office and warehouse
spaces. The intent is to purchase 49.98 acres and immediately deed back 1.45 acres for a
future residential cul -de -sac. Of the remaining 48.53 acres it is proposed that Werner purchase
approximately 20 acres for $2,273,832. The remaining 28.5 acres would be added to Hamlet
Park for use as park land and storm water holding ponds. This land would be purchased using
ED Trust Fund monies, storm water area (including MNDOT monies) and park dedication funds.
Additionally, this development would generate $500,000 in present value tax increments.
Members of the Werner team presented a site plan and architectural renderings and stood for
questions from the EDA. EDA Member Poncin made a motion to authorize a purchase
agreement with WAG Farms and development agreement with Werner Electric Supply of MN
(and assigns) and request allocation of $500,000 from the ED Trust Fund toward project
expenses, subject to City Attorney review and approval. Seconded by EDA Vice President Rice,
All Present in Favor.
STEERING COMMITTEE MEETING- COMPREHENSIVE PLAN UPDATE
Community Development Director Howard Blin presented what the Comprehensive Plan Update
Steering Committee has been working on. At their June meeting they discussed the land use
plan and designating urban reserve in areas of the City. At the August meeting they discussed
transportation. They will be meeting with the City Council in September. In October there will be
a representative from Washington County at their meeting to discuss the Red Rock Corridor.
2
Economic Development Authority - Minutes
August 14, 2007
Page 3
2007 EDA GOLF TOURNAMENT UPDATE
Jesse Swenson gave the EDA an updated budget and registration numbers thus far for the
2007 event.
CAI FNnAR
The EDA members were reminded of upcoming meetings and events.
MISCELANEOUS BUSINESS ITEMS
None
ADJOURN
EDA Vice President Rice moved to adjourn the meeting. Seconded by EDA Secretary /Treasurer
Weingartner, All Present in Favor, the meeting adjourned at 8:05 AM.
Respectfully Submitted,
Joe Fischbach
Management Analyst
3