HomeMy WebLinkAbout2011-05-18 PACKET 08.A.REQUEST OF CITY COUNCIL ACTION COUNCIL AGENDA
MEETING ITEM #
DATE 5/18/11 e
PREPARED BY Community Development Jennifer Levitt
ORIGINATING DEPARTMENT STAFF AUTHOR
COUNCIL ACTION REQUEST
1. Consider accepting the Findings of Fact on the EAW for the 3M East Cove Sediment
Removal Project.
2. Consider declaring a negative declaration on the need for an EIS for the 3M East Cove
Sediment Removal Project.
3. Consider approving 3M's conditional use permit for a grading permit to remove
approximately 17,000 cubic yards of sediment containing PFCs from the East Cove at 3M
Cottage Grove.
STAFF RECOMMENDATION
1. Accept the Findings of Fact.
2. Adopt the resolution declaring a negative declaration on the need for an EIS.
3. Adopt the resolution approving a condtional use permit for a grading permit.
ADVISORY COMMISSION ACTION
DATE REVIEWED APPROVED
® PLANNING 4/25/11 ❑
® ENVIRONMENTAL 5/11/11 ❑ ❑
SUPPORTING DOCUMENTS
® MEMO /LETTER: Memo from John McCool dated 5/12/11
® RESOLUTION: Draft - Negative Declaration on the need for an EIS
Draft - Conditional use permit
❑ ORDINANCE:
❑ ENGINEERING RECOMMENDATION:
❑ LEGAL RECOMMENDATION:
® OTHER: Excerpt from 4/25/11 Planning Commission meeting minutes
ADMINISTRATORS COMMENTS
DENIED
Date
COUNCIL ACTION TAKEN: ❑ APPROVED ❑ DENIED ❑ OTHER
FROM: John McCool, Senior Planner
DATE: May 12, 2011
RE: Proposed 3M Cottage Grove East Cove Sediment Removal Project — EAW and
Conditional Use Permit Applications
.••
3M has submitted an application for an Environmental Assessment Worksheet (EAW) and a con-
ditional use permit (grading permit) for their East Cove Sediment Removal Project.
The East Cove Sediment Removal Project will remove approximately 17,000 cubic yards of se-
diment containing perfluorochemicals (PFCs) from the East Cove at the 3M Cottage Grove plant
and a portion of the sandbar at the cove outlet. The project removal area is approximately 1.5
acres in size and is located on 3M property at the base of a ravine adjacent to and east of the 3M
Cottage Grove Plant. The sediment in the cove is being removed by dredging to a depth of 6.5 to
7 feet below the top of the sediment and within the defined boundaries approved by the Minne-
sota Pollution Control Agency. A location map showing the location of the East Cove is below.
Location Map
A copy of the Environmental Assessment Worksheet and Work Plan is attached.
Honorable Mayor Bailey, City Council Members, and Ryan Schroeder
3M's East Cove Sediment Removal Project — EAW and Conditional Use Permit Applications
May 12, 2011
Page 2 of 6
Advisory Commission Recommendations
Planning Commission
The Planning Commission reviewed 3M's EAW and conditional use permit applications at a pub-
lic hearing on April 25, 2011. Mark Gaetz, a 3M representative attended the meeting and made a
short presentation on the various stages in completing this project. Dale Andrews, 8430 Keats
Avenue, asked questions concerning the three PFC clean -up sites in Washington County (3M
Cottage Grove Site, the 3M Oakdale Disposal Site, and the 3M Woodbury Disposal Site).
Andrews' questions pertained to the location of the three sites, the Settlement Agreement and
Consent Order between 3M Company and the Minnesota Pollution Control Agency, and the pub-
lic process for the EAW for each of these sites. It was explained that the cleanup and restoration
at the Oakdale and Woodbury Disposal sites were completed a couple years ago and the 3M
Cottage Grove East Cove site is scheduled to be completed this year. A copy of the planning staff
report, Minnesota Decision Document (2009), and Settlement Agreement/Consent Order (2007)
were given to Ms. Andrews. No other public testimony or written comments were received at that
meeting.
The Commission supported the applicant's proposal and unanimously (6 -0 vote) recommends
that the City Council accept the findings of fact listed in the planning staff report in conjunction
with a negative declaration on the need for an EIS for the 3M East Cove Sediment Removal
Project, The Planning Commission also unanimously (6 -0 vote) recommended the approval of
3M's conditional use permit application (grading permit) for this project. An excerpt from the
Planning Commission's unapproved minutes is attached.
Environmental Commission
The Environmental Commission reviewed 3M's EAW and conditional use permit applications at
their meeting on May 11, 2011. A copy of the planning staff report and all the documents cited in
the planning staff report were provided to the Environmental Commission members in advance of
their May 11 meeting. Mark Gaetz from 3M Company attended the meeting. There was no other
public testimony received at this meeting. The Environmental Commission also unanimously (6-
to -0 vote) recommends to the City Council the acceptance of the findings of fact in conjunction
with a negative declaration on the need for an EIS and approval of the conditional use permit for
the grading permit necessary to complete this project. An excerpt from the Environmental Com-
mission's unapproved minutes will be provided prior to the Council meeting.
The Environmental Review Process
The Minnesota Environmental Policy Act of 1973 established a formal process for reviewing the
environmental impacts of major development projects. The purpose of the review is to provide
information to units of government on the environmental impacts before approvals or necessary
permits are issued. Environmental review creates the opportunity to anticipate and correct these
problems before projects are built.
The City is the Responsible Governmental Unit (RGU) for the EAW. The City is responsible for
verifying the completeness of the EAW if prepared by the applicant, and complying with the rule
timeframes for the EAW process. The EAW process to date has included the following steps:
Honorable Mayor Bailey, City Council Members, and Ryan Schroeder
3M's East Cove Sediment Removal Project— EAW and Conditional Use Permit Applications
May 12, 2011
Page 3 of 6
March 14, 2011
EAW and CUP applications submitted to the City
March 14, 2011
Notice of EAW availability for comment submitted to the Minnesota EQB for
publication in the EQB Monitor
March 15, 2011
Press release sent to the South Washington County Bulletin. A copy of this
press release is attached.
March 21, 2011
Notice published in the EQB Monitor that the EAW for 3M's East Cove Sedi-
ment Removal Project was available for review. The 30 -day review period
started on this date.
March 21, 2011
Notice of the availability to review the EAW for 3M's East Cove Sediment Re-
moval Project was posted on the City's web page and delivered to the Park
Grove Branch Library.
April 20, 2011
30 -day review period ended. Four comment letters received.
April 25, 2011
Public hearing held by the Cottage Grove Planning Commission.
May 11, 2011
Environmental Commission meeting.
The decision on the need for an Environmental Impact Statement (EIS) shall be made between
three and 30 days after the close of the review period. The City's decision must be provided
within five days to all persons on the EAW distribution list, to all persons that commented in
writing during the 30 -day review period, and to any person upon written request.
Conditional Use Permit
City Code Title 11 -6 -12, Grading, Filling or Excavation, requires all grading permits that result in
the moving of more than 1,000 cubic yards of material per acre of site area to be reviewed as a
conditional use permit. The City's review of this conditional use permit application will be concur-
rent with the EAW application.
• .
The Minnesota Pollution Control Agency (MPCA) and 3M signed a Settlement Agreement and
Consent Order in May 2007 to clean up three 3M PFC Disposal Sites in Washington County. One
of these sites is at the 3M Cottage Grove plant. As part of the agreement, 3M completed a Re-
medial Investigation and Feasibility Study for the Cottage Grove site, the focus of which was to
identify any remaining threats to public health or the environment from releases of PFCs at the
site. The Consent Order also required that in developing cleanup alternative, primary considera-
tion should go to those that excavate and destroy remaining PFC waste, or that excavate and
dispose of PFC wastes in a permitted, isolated, engineered containment facility.
The MPCA reviewed the alternatives identified in the Feasibility Study and issued a Minnesota
Decision Document in August 2009. A copy of the Minnesota Decision Document is attached.
This document summarized the facts and determinations made by the Minnesota Pollution Con-
trol agency in approving the recommended response action alternatives. A summary of the
recommended remedies at the 3M Cottage Grove site are:
® Institutional controls /deed restrictions, site access controls and long -term groundwater
monitoring.
6 Enhanced groundwater recovery with carbon treatment to remove PFCs prior to discharge.
Honorable Mayor Bailey, City Council Members, and Ryan Schroeder
3M's East Cove Sediment Removal Project — EAW and Conditional Use Permit Applications
May 12, 2011
Page 4 of 6
• Stabilize flow channel to East Cove and remove PFC- containing sediments throughout the
site.
• Remove portions of sandbar at cove outlet.
• Remove concrete basin previously used for sludge neutralization /disposal in Disposal Area
D1 and remove additional overlying soils in that area.
• Remove PFC contaminated soils in Disposal Areas D1, D2, and D9 which exceed Indus-
trial Soil Reference Values for PFOA and /or PFOS.
• Transport excavated soil, sediments and materials to an engineered long -term contain-
ment cell at SKB Industrial landfill, Rosemount, Minnesota or Environmental Quality Com-
pany's disposal waste treatment plant in Belleville, Michigan. All excavated materials ex-
ceeding the Industrial Soil Reference Values established by the Minnesota Pollution
Control Agency will be disposed off -site.
Remedy Timeline
October 21. 2009 — The City of Cottage Grove City Council approved 3M's conditional use permit
application to excavate approximately 19,000 cubic yards of soil from approximately two acres of
land located in the southeast corner of 3M Cottage Grove's site. This project removed approx-
imately 19,000 cubic yards of soil from approximately two acres of land located in the southeast
corner of 3M Cottage Grove's site identified as D1 and D2. The D1 Area is a former hydrofluoric
tar neutralization pit and the D2 Area is a former sludge disposal area that received sludge from
3M's wastewater treatment ponds. The work started in November 2009 and was completed in
2010. Cleanup projects for the D9 Area, access road, and East Cove areas were identified as
future projects.
April 21, 2010 — The City of Cottage Grove City Council held a public hearing and approved a
conditional use permit application to excavate approximately 10,000 cubic yards of soil from an
area described as Disposal Site Area 9. Area D9 is a former sludge disposal pit. The work started
in May 2010 and was completed in 2011.
July 7, 2010 — The City of Cottage Grove approved 3M's conditional use permit to excavate ap-
proximately 10,000 cubic yards of excess soil to re -grade an existing private access road
between their wastewater treatment facility and an area known as the East Cove. This work was
completed in November 2010.
March 14, 2011 — The City Council was informed that a notice of availability to review 3M's EAW
was submitted to the Environmental Quality Board on March 14, 2011. The EQB publish the
notice in the EQB's Monitor on March 21, 2011. The 30 -day public comment period for the EAW
was from March 21, 2011, to April 20, 2011. A press release briefly describing the project, where
the EAW can be reviewed, the comment period deadline, and to whom comments should be
submitted was sent to the South Washington County Bulletin. The EAW process was briefly
described and a copy of the EAW and Work Plan were distributed to the City Council.
Honorable Mayor Bailey, City Council Members, and Ryan Schroeder
3M's East Cove Sediment Removal Project — EAW and Conditional Use Permit Applications
May 12, 2011
Page 5 of 6
March 25, 2011 — The Planning Commission was informed of 3M's EAW and conditional use
permit applications for the East Cove Sediment Removal Project. The EAW process was briefly
described and a copy of the EAW and Work Plan were distributed to the Planning Commission.
April 13 2011 —The Environmental Commission and Planning Commission held a joint workshop
meeting to listen to 3M's presentation on the East Cove Sediment Removal Project. The EAW
process was briefly described and a copy of the EAW and Work Plan were distributed to the Envi-
ronmental Commission.
April 25, 2011 — The Planning Commission held a public hearing. A planning staff report, EAW,
Work Plan, Press Release, EQB Monitor Publication, EQB's agency distribution list, four agency
comment letters, Minnesota Decision Document (2009) and Settlement Agreement/Consent
Order (2007) were provided to the Commission.
May 11 2011 — The Environmental Commission met. A copy of all the materials given to the
Planning Commission for their meeting on April 25, 2011 was also distributed to the Environ-
mental Commission.
Planning Considerations
Agency Comment Letters Received
The City received four comment letters on the East Cove Sediment Removal EAW. The comment
letters from the South Washington Watershed District, Minnesota Pollution Control Agency, and
Minnesota Department of Natural Resources generally acknowledged that they reviewed the
EAW and generally found the documents to be complete and accurate and do not require the
preparation of an Environmental Impact Statement.
The comment letter from the Metropolitan Council addressed a wide range of issues that can be
summarized in the following categories:
• The East Cove Sediment Removal Project does not address the effects of the project rela-
tive to Pool 2 PFOS impairment.
• The ability of the proposed project to reduce PFOS transport to Pool 2 has not been fully
demonstrated.
• The project does not include post - project monitoring to evaluate the reduction in the trans-
port of PFOS to Pool 2.
The Minnesota Pollution Control Agency reviewed the comments submitted by Metropolitan
Council Environmental Services to the City of Cottage Grove dated April 19, 2011. It is MPCA's
opinion that many of the comments provided by the Met Council are not within the scope of the
proposed sediment excavation project that is the subject of the EAW. Many of the issues they
raised either are currently being discussed or will be discussed as part of two other processes in
which the MPCA is involved with Met Council. These other processes pertain to the Met Council's
wastewater treatment plant National Pollutant Discharge Elimination System (NPDES) permit and
the Total Maximum Daily Load (TMDL) study of Pool 2 to address the impairment caused by
PFOS.
Honorable Mayor Bailey, City Council Members, and Ryan Schroeder
3M's East Cove Sediment Removal Project — EAW and Conditional Use Permit Applications
May 12, 2011
Page 6 of 6
A copy of the four comment letters received for this project and the City's responses are attached.
A copy of Minnesota Pollution Control Agency's letter (April 25, 2011) responding to comments
submitted by Metropolitan Council Environmental Services to the City of Cottage Grove dated
April 19, 2011 is also attached.
Next Steps in the EAW Process and Criteria for Decision - Making
The next steps in the EAW process will include the following:
The City must respond in writing to all substantive comments received during the comment
period. The City may choose to respond to late comments received after the comment
period.
® The City will determine the need for an Environmental Impact Statement and adopt
findings of fact document.
Minnesota rules require that the City must make a decision on the need for an EIS be-
tween three and 30 days after the comment period ends. The City may postpone the deci-
sion for an additional 30 days, or a longer period of time, as agreed with the proposer, if
there is a need to gather additional information to respond to the comments.
Public Hearing Notices
A public hearing has been scheduled for the Planning Commission meeting on April 25, 2011. A
notice announcing this public hearing was published in the South Washington County Bulletin on
April 13, 2011. Public hearing notices were mailed to 79 neighboring property owners on April 14,
2011.
Recommendation
That the City Council takes the following actions:
1. Accept the Findings of Facts on the EAW for the East Cove Sediment Removal Project pro-
posed by 3M Company.
2. Adopt a resolution declaring a negative declaration on the need for an EIS for the East Cove
Sediment Removal Project proposed by 3M Company
3. Adopt a resolution approving 3M's conditional use permit application for a grading permit that
will remove approximately 17,000 cubic yards of sediment containing PFC's from the East
Cove at the 3M Cottage Grove plant and a portion of sandbar at the cove outlet; subject to
conditions.
RESOLUTION NO. 2011 -XXX
NEGATIVE DECLARATION ON THE NEED FOR AN ENVIRONMENTAL IMPACT
STATEMENT (EIS) FOR 3M'S EAST COVE SEDIMENT REMOVAL PROJECT
WHEREAS, the City of Cottage Grove is the Responsible Governmental Unit (RGU) in
the processing of the Environmental Assessment Worksheet (EAW) for the proposed 3M East
Cove Sediment Removal Project; and
WHEREAS, the EAW is based on 3M Company's proposal to remove approximately
17,000 cubic yards of sediment containing perfluorochemicals (PFCs) from the East Cove at the
3M Cottage Grove plant and a portion of the sandbar at the Cove's outlet; and
WHEREAS, the City of Cottage Grove has submitted a copy of the EAW to all public agen-
cies on the EQB's distribution list, provided a press release to the South Washington County
Bulletin local newspaper, and published a notice of the availability of the EAW in the EQB Monitor
on March 21, 2011, all of which were done in accordance with applicable State laws, rules, and
regulations; and
WHEREAS, the 30 -day comment period ended on April 20, 2011, with four regulatory
agencies commenting; and
WHEREAS, the City of Cottage Grove acknowledges the comments from the Minnesota
Pollution Control Agency, Minnesota Department of Natural Resources and South Washington
Watershed District; and
WHEREAS, the City of Cottage Grove has considered the comments that were received
and will complete the Findings of Fact, including responses to the commenting regulatory agen-
cies and individuals.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Cottage
Grove, Washington County, Minnesota, that a Findings of Fact for the negative declaration on
the need for an Environmental Impact Statement for 3M's East Cove Sediment Removal
Project has been prepared on behalf of the City to address the specific comments and con-
cerns of the responding agencies, and the Findings are attached to this resolution.
Passed this 18th day of May, 2011.
Myron Bailey, Mayor
Attest:
Caron M. Stransky, City Clerk
RECORD OF DECISION
FINDINGS OF FACT, CONCLUSIONS, AND CITY COUNCIL RESOLUTION
DATE: May 12, 2011
RE: Record of Decision — Negative Declaration on the Need for a EIS
PROJECT: 3M East Cove Sediment Removal Project
ADMINISTRATIVE BACKGROUND
The City of Cottage Grove is the Responsible Governmental Unit (RGU) for this project and 3M
Company is the project proposer. An Environmental Assessment Worksheet (EAW) has been
prepared for this project in accordance with Minnesota Rules Chapter 4410. The EAW was de-
veloped to assess whether or not there are impacts from the project to determine if an Environ-
mental Impact Statement (EIS) is required.
The EAW was filed with the Minnesota EQB and circulated for review and comments to the
required EAW distribution list. A notice of availability to review 3M's EAW was submitted to the
Environmental Quality Board on March 14, 2011. The EQB published the notice in the EQB's
Monitor on March 21, 2011. The 30 -day public comment period for the EAW was from March
21, 2011, to April 20, 2011. A press release briefly describing the project, where the EAW can
be reviewed, the comment period deadline, and to whom comments should be submitted was
sent to the South Washington County Bulletin.
The Minnesota Pollution Control Agency (MPCA) and 3M signed a Settlement Agreement/ Con-
sent Order in May 2007 to clean up three 3M PFC Disposal Sites in Washington County. One of
these sites is at the 3M Cottage Grove plant. As part of the agreement, 3M completed a Re-
medial Investigation and Feasibility Study for the Cottage Grove site, the focus of which was to
identify any remaining threats to public health or the environment from releases of PFCs at the
site. The Consent Order also required that in developing cleanup alternatives, primary consider-
ation should go to those that excavate and destroy remaining PFC wastes or that excavate and
dispose of PFC wastes in a permitted, isolated, engineered containment facility.
The MPCA reviewed the alternatives identified in the Feasibility Study and issued a Minnesota
Decision Document in August 2009. This document summarized the facts and determinations
made by the Minnesota Pollution Control agency in approving the recommended response
action alternatives.
It is the finding of the City of Cottage Grove (RGU) that the Environmental Assessment Work-
sheet (EAW) for 3M's proposed East Cove Sediment Removal Project was completed and is
adequate to determine whether the project has the potential for significant environmental ef-
fects. The EAW described the type and extent of impacts anticipated to result from the proposed
project. This document provides clarifications and additional information since the EAW was
published.
Record of Decision — Negative Declaration on the Need for a EIS
3M East Cove Sediment Removal Project
May 12, 2011
Page 2 of 6
The City of Cottage Grove further recognizes the following findings of fact in conjunction with a
negative declaration on the need for an EIS for the proposed East Cove Sediment Removal
Project:
PROJECT DESCRIPTION
The East Cove Sediment Removal Project will remove approximately 17,000 cubic yards of
sediment containing perfluorochemicals (PFCs) from the East Cove at the 3M Cottage Grove
plant and a portion of the sandbar at the cove outlet. The project removal area is approximately
1.5 acres in size and is located on 3M property at the base of a ravine adjacent to and east of
the 3M Cottage Grove Plant. The sediment in the cove and sandbar are being removed by
dredging to a depth of 6.5 to 7 feet below the top of the sediment and within the defined bounda-
ries approved by the Minnesota Pollution Control Agency. There will not be any permanent loss
to existing wetland in the East Cove. The project will have a temporary impact on the East Cove
during sediment removal and construction. As removal is completed, the excavated cove will be
backfilled with soil to elevations consistent with pre- construction conditions.
This work is in accordance with MPCA's Decision Document with 3M to remove sediments
containing perfluorochemicals (PFCs) from the East Cove and a portion of the sandbar at the
cove outlet. The removed sediments will be placed in a containment cell at the SKB Industrial
Landfill in Rosemount, Minnesota.
FINDINGS OF FACT
1. Comparing environmental impacts that may be reasonably expected to occur from the
proposed project with the criteria contained in Minnesota Rules 4410.1700, subpart 7, the
City of Cottage Grove, Washington County, Minnesota finds that the proposed project
does not have the potential for significant environmental effects.
2. The EAW is incorporated by reference in this Record of Decision.
3. City staff submitted the EAW to the Minnesota Environmental Quality Board (MEQB) on
March 14, 2011.
4. A press release announcing the availability of the EAW for public review and comment,
including a brief description of the project, was sent to South Washington County Bulletin
on March 14, 2011.
5. The EAW was filed with the MEQB and notice for its availability for public review and
comment was published in the EQB Monitor on March 21, 2011. A copy of the EAW was
sent to all persons on the MEQB Distribution List and to persons who requested a copy.
The EAW was also made available on the City of Cottage Grove's website, Cottage
Grove City Hall, and at the Washington County Library — Park Grove Branch.
6. The 30 -day public review and comment period, the City of Cottage Grove received four
written comments on the EAW from:
Record of Decision — Negative Declaration on the Need for a EIS
3M East Cove Sediment Removal Project
May 12, 2011
Page 3 of 6
a. Minnesota Department of Natural Resources
b. Minnesota Pollution Control Agency
c. Metropolitan Council Environmental Services
d. South Washington Watershed District
7. The written comments received are summarized below with a City of Cottage Grove
response following each comment.
Minnesota Department of Natural Resources (DNR) Central Region
The DNR reviewed the EAW and commented that the document appeared to be com-
plete and accurate and does not require the preparation of an EIS. The DNR reported
that they are currently reviewing the Public Waters Work Permit application.
Comment: The DNR commented that they are reviewing the Public Waters
Work Permit application for this project.
Response: The RGU acknowledges that additional project requirements beyond
what is currently outlined in the EAW may be included as conditions
of the permit and understand that the decision of whether or not the
permit will be granted will not occur until the environmental review
process is complete.
Minnesota Pollution Control Agency (MPCA)
The MPCA reported that the EAW contains detailed descriptions of the excavation and
remediation of the PFC contaminated sediments in the East Cove as contained in the
MPCA approved Remedial Design /Response Action Plan for the 3M Cottage Grove Site.
The East Cove cleanup project was approved by the MPCA Commissioner as outlined in
the Minnesota Decision Document dated August 28, 2009 and as outlined in the Settle-
ment Agreement /Consent Order dated May 11, 2007.
Comment: The MPCA commented that a Clean Water Act (CWA) Section 404
Permit from the U.S. Army Corps of Engineers (USAGE) for project
related wetland impacts may be necessary. If a USACE Section 404
Individual Permit is required, then a MPCA CWA Section 401 Water
Quality Certification or waiver must also be obtained as part of the
permitting process.
Response: The USACE has decided that a permit will not be done under a 404
Individual Permit but will be done under the current general permit
that exists for the 3M Cottage Grove plant.
Metropolitan Council (Met Council)
The Metropolitan Council generally agrees that removal of contaminated sediment from
both the East Cove and the Mississippi River in this area will improve the water quality,
particularly fish tissue concentrations of PFOS in Pool 2. Metropolitan Council expressed
the following concerns:
Record of Decision — Negative Declaration on the Need for a EIS
3M East Cove Sediment Removal Project
May 12, 2011
Page 4 of 6
1. The East Cove Sediment Removal Project does not address the effects of the project
relative to Pool 2 PFOS impairment.
2. The ability of the proposed project to reduce PFOS transport to Pool 2 has not been
fully demonstrated.
3. The project does not include post - project monitoring to evaluate the reduction in the
transport of PFOS to Pool 2.
Comment: The proposed remediation project is not sufficient to properly ad-
dress the impairment of water quality and fish in Pool 2.
Response: The East Cove Sediment Removal Project is an environmental re-
mediation project designed to remove PFC impacted sediment from
the East Cove and sandbar for the protection of human health and
the environment. The project is to prevent PFCs from potentially
desorbing from the sediment into surface water and groundwater. A
groundwater extraction system is being installed in accordance with
the Minnesota Decision Document dated August 28, 2009 and
MPCA approved Remedial Design /Response Action Plan for the 3M
Cottage Grove site.
The sediment removal project in the East Cove is an important com-
ponent of the cleanup plan to reduce migration of PFCs to the Mis-
sissippi River. The MPCA will continue to evaluate PFC impacts to
the Mississippi River from all sources.
Comment: The EAW does not quantify the degree of reduction expected from
the East Cove to Pool 2.
Response: It would be quantified in the TMLD for Pool 2.
South Washington Watershed District
Comment: The South Washington Watershed District reported that they do not
have any substantial comments regarding the EAW.
Response: Comment noted.
8. The following permit and approvals will be required for the project:
Unit of Government Type of Application Status
City of Cottage Grove Conditional Use Permit (grading permit) To be obtained
MDNR /USAGE /LGU MN Local /State /Federal Application Forms For Being submitted
Water/Wetland Projects — Part I (Basic Applica-
tion): Wetland Conservation Act (WCA)
Record of Decision — Negative Declaration on the Need for a EIS
3M East Cove Sediment Removal Project
May 12, 2011
Page 5 of 6
USACE Regional General Permit GP- 001 -MN; Section 404- Being submitted
Clean Water Act and Section 10 -River and Harbors
Act
MN Pollution Control Agency Stormwater General Permit for Construction To be prepared
Activities
South Washington SWWD review — May not require a separate permit
Watershed District
CONCLUSIONS
The City of Cottage Grove has fulfilled all applicable procedural requirements of law
and rule regarding the preparation of the Environmental Assessment Worksheet
(EAW) for the proposed 3M East Cove Sediment Removal Project.
Pursuant to Minnesota Rules Part 4410 the proposed project has been evaluated by
the public and the City of Cottage Grove (RGU). This evaluation included preparation
and public review of the EAW under the environmental review rules established by the
Minnesota Environmental Quality Board (EQB).
3. Pursuant to Minnesota Rules Part 4410.1700, Subpart 5, a copy of this RGU Findings
of Fact and the City resolution making a negative declaration on the need of an EIS is
being provided within five days, to all persons on the MEQB Distribution List, to per-
sons commenting, and to persons who requested a copy. This Findings of Fact will
also be made available on the City of Cottage Grove's website.
4. The EAW described the type and extent of impacts anticipated to result from the project.
This document provides clarifications and information that the proposed project will re-
sult in no permanent loss to existing wetland in the East Cove and has generated infor-
mation which is adequate to determine whether the project has the potential for
significant environmental effects.
Areas where potential environmental effects have been identified are addressed in the
work plan of the project. Mitigation will be provided where impacts are expected to re-
sult from the project construction and are incorporated into the project design and
have been or will be coordinated with state and federal agencies during the permit
process.
6. Based on the criteria in Minnesota Rules Part 4410.1700, the project does not have
the potential for significant environmental effects.
An Environmental Impact Statement is not required for the proposed 3M East Cove
Sediment Removal Project.
Record of Decision — Negative Declaration on the Need for a EIS
3M East Cove Sediment Removal Project
May 12, 2011
Page 6 of 6
8. 3M is providing the financial assurance that this project will be performed and restoration
completed in accordance with plans approved by the Minnesota Pollution Control
Agency.
9. The East Cove Sediment Removal Project is merely one component of the overall
clean -up plan at the 3M Cottage Grove site. This sediment removal component will
prevent one source from contributing PFC's to the Mississippi River and is an impor-
tant component of the cleanup plan to reduce migration of PFCs to the Mississippi
River.
10. This remedial activity will prevent this mass of PFCs from potentially desorbing from the
sediment into surface water and groundwater. A groundwater extraction system is being
installed in accordance with the Minnesota Decision Document to intercept groundwater
containing PFCs moving toward the Mississippi River.
11. The proposed project is an environmental remediation project designed to remove PFC -
impacted sediment from the East Cove and sandbar for the protection of human health
and the environment in accordance with the MPCA Minnesota Decision Document and
MPCA approved Remedial Design /Response Action Plan for the 3M Cottage Grove site.
12. The Minnesota Pollution Control Agency has provided oversight of 3M investigations
at the 3M Cottage Grove facility concerning PFCs contamination issues and will mon-
itor the effectiveness of the PFC cleanup actions conducted by 3M.
13. The Minnesota Pollution Control Agency has reviewed and approved 3M's proposed
cleanup plans concerning PFC remediation activities at the 3M Cottage Grove facility.
The Commissioner of the MPCA approved the final PFC cleanup plan for the 3M
Cottage Grove site, which is documented in the Minnesota Decision Document dated
August 28, 2009.
14. The Minnesota Pollution Control Agency will continue to evaluate PFC impacts to the
Mississippi River from all sources as part of the Total Maximum Daily Load Study.
15. This remedial activity will prevent this mass of PFCs from potentially desorbing from the
sediment into surface water and groundwater. A groundwater extraction system is being
installed in accordance with the Minnesota Decision Document to intercept groundwater
containing PFCs moving toward the Mississippi River.
16. The approximately 17,000 cubic yards of sediment will be excavated from the East Cove
and sandbar areas. The sediment has been classified as a nonhazardous solid waste. It
will be dewatered by addition of a super absorbent polymer, which will allow the sedi-
ment to pass the paint filter test both at the loading point and at the disposal point. The
dewatered sediment will be transported to the SKB Industrial Landfill and placed in a
specially engineered cell for the 3M PFC remediation wastes as approved by the MPCA.
RESOLUTION NO. 2011 -XXX
RESOLUTION APPROVING THE CONDITIONAL USE PERMIT TO EXCAVATE
APPROXIMATELY 17,000 CUBIC YARDS OF EXCESS SOIL FROM LAND
LOCATED IN THE SOUTHEAST CORNER OF THE 3M COTTAGE GROVE SITE
WHEREAS, 3M has applied for a conditional use permit to remove approximately 17,000
cubic yards of sediment containing perfluorochemicals (PFCs) from the East Cove at the 3M
Cottage Grove plant and a portion of the sandbar at the Cove's outlet in the southeast corner of
the 3M Cottage Grove site, located on property legally described below:
That part of Section 35, Township 027 North, Range 21; Cottage Grove, Washington
County, MN being in the West Half of Section 35, Township 027 North, Range 21 West
and lying south of the right -of -way of the Chicago, Milwaukee, & St. Paul Railway
Company.
WHEREAS, 3M has also applied for an Environmental Assessment Worksheet (EAW) for
the proposed 3M East Cove Sediment Removal Project; and
WHEREAS, a public hearing notice was published in the South Washington County
Bulletin on April 13, 2011; and
WHEREAS, public hearing notices were mailed to 79 neighboring property owners on
April 14, 2011; and
WHEREAS, the Planning Commission held the public hearing for the EAW and
conditional use permit at their meeting on April 25, 2011. The public hearing was open for public
testimony, and testimony from the applicant and the public was received and entered into the
public record; and
WHEREAS, the Planning Commission reviewed the EAW and unanimously (6 -to -0 vote)
recommended a negative declaration on the need for an Environmental Impact Statement (EIS) for
3M's East Cove Sediment Removal Project; and
WHEREAS, the Environmental Commission reviewed the EAW at their meeting on May 11,
2011, and unanimously (6 -to -0 vote) recommended a negative declaration on the need for an
Environmental Impact Statement (EIS) for 3M's East Cove Sediment Removal Project.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Cottage
Grove, Washington County, Minnesota, hereby approves the conditional use permit to remove
approximately 17,000 cubic yards of sediment containing perfluorochemicals (PFCs) from the East
Cove at the 3M Cottage Grove plant and a portion of the sandbar at the Cove's outlet in the
southeast corner of the 3M Cottage Grove site, subject to the following conditions:
1. 3M must comply with the remedial actions documented in the Minnesota Decision
Document made by the Minnesota Pollution Control Agency staff in approving the
recommended response action alternatives.
Resolution No. 2011 -XXX
Page 2 of 2
2. 3M will obtain all required State permits before excavation begins.
3. A copy of the National Pollution Discharge Elimination System (NPDES) general
storm water permit from the MPCA must be given to the City.
4. 3M will provide a copy of the Stormwater Pollution Prevention Plan (SWPPP) and
a copy of all the erosion control inspections to the City Engineer.
Passed this 18th day of May 2011.
Myron Bailey, Mayor
Attest:
Caron M. Stransky, City Clerk
EXCERPT FROM UAPPROVED MINUTES OF THE
PLANNING COMMISSION MEETING ON APRIL 25, 2011
6.3 3M East Cove Environmental Assessment Worksheet — Case EAW11 -007
3M Company has applied for a conditional use permit for removal of approximately
17,000 cubic yards of sediment containing PFCs from the East Cove at the 3M Cottage
Grove plant and a portion of the sandbar at the cove outlet. The project removal area is
approximately 1.5 acres in size and is located on 3M property, 10746 Innovation Road, at
the base of a ravine adjacent to and east of the 3M Cottage Grove Plant. 3M has also ap-
plied for an Environmental Assessment Worksheet (EAW) for their East Cove Sediment
Removal Project.
McCool summarized the staff report and recommended approval of both the conditional use
permit and the environmental assessment worksheet subject to the conditions stipulated in
the staff report.
Mark Gaetz, 3M Company, stated that this is the final stage of the physical removal at the
site; there were three other distinct locations within the 3M Cottage Grove property that they
took care of earlier. Under this consent order, there are other activities that will happen re-
lated to treatment of waters and installation of a barrier well system for ground water extrac-
tion, which is the primary protection of the river. He presented schematics of the different
phases of this project. He explained that the East Cove is a seasonal wetlands area and is
the continued discharge area for the 3M wastewater treatment facility. He stated that they
need to maintain their discharge so they can continue to operate the facility. He provided a
description of the staged approach to the excavation and disposal of the excavated sedi-
ment. Sheet pilings will be installed by the railroad right -of -way and the west and north sides
of the cove around the sandbar area along the bank of the Mississippi River. The water will
be diverted to the east side of the Cove and a temporary loading dock will be constructed.
They will then reverse the flow to the west side of the Cove and install a turbility curtain on
the north and east sides of the Cove. They will dredge the east section of the Cove by using
a piece of equipment on a floating platform and depositing the dredged material onto a barge
where they will apply a super absorbent material. This material will be loaded onto trucks for
transport to the approved disposal site. After the east side is dredged and partially backfilled,
they will move to the west section and divert the water flow to the east. They will be exca-
vating approximately 17,000 cubic yards of sediment in wet form, which will be dewatered on
site and hauled to the disposal site in Rosemount, Minnesota. Contaminated sediment at the
sandbar will be removed and backfilled with clean sand. The last stage is to remove the
dams and barges, stabilize, and demobilize. The schedule, pending PCA approval, is to start
the process in June and demobilize in November 2011. The Army Corps of Engineers and
Department of Natural Resources will provide a recommendation on the planting plan, to be
completed in spring 2012 and then monitor the plantings over time to ensure active growth.
Poncin asked what the jurisdiction is for the Planning Commission in regard to this applica-
tion. McCool responded that the City is the responsible government unit and is responsible
to evaluate that the EAW includes all the environmental issues and findings of the environ-
mental review process, advertise the availability of the EAW, and conduct the public hear-
Excerpt from Planning Commission Minutes
3M East Cove Environmental Assessment Worksheet
April 25, 2011
Page 2 of 4
ings. Planning staff is recommending that the Planning Commission consider a recommen-
dation of a negative declaration that an Environmental Impact Statement is needed, because
the City finds this project is warranted for the removal of the PFCs found in the sediment
material in the East Cove, based on the findings that are identified in the planning staff re-
port. Staff is also recommending approval of the conditional use permit for the grading oper-
ation to take place, subject to the conditions listed in the staff report. McCool reported that
today, the City received a response from the Minnesota Pollution Control Agency responding
to the comments made by the Metropolitan Council. The MPCA identified that the comments
made by the Met Council were not within the scope of this particular project, but there are
other projects taking place in Pool 2 of the Mississippi River, and it also deals with the total
daily load limits of the Mississippi River. Those projects and their evaluations are ongoing.
Linse asked if the negative declaration on the EIS is primarily because the benefit for getting
PFCs out is greater than the impact on the environment. McCool responded that was
correct.
Treber opened the public hearing.
Dale Andrews, 8430 Keats Avenue South, asked about the 2007 agreement and if this is a
subset of whatever actions were to be taken by that agreement. She also asked for clarifica-
tion on the number clean -up sites. McCool responded there are three sites. Andrews asked
outside of the 3M plant, what the other two Washington County are. Gaetz responded in
Woodbury on the east side of County Road 19 just north of the Woodbury/Cottage Grove
boundary and in Oakdale on Highway 5 between Granada and Hadley. Andrews asked if the
May 2007 agreement is public record. Gaetz responded yes. Andrews asked if they went
through the same process for other two locations. Gaetz responded that this process was
very similar to what was done in Oakdale and Woodbury; the only difference is that there is a
wetland involved with the Cottage Grove site. Andrews asked if this process was also done
because it involved the Mississippi River. Gaetz responded that it is in a sandbar in the
River.
No one else spoke. Treber closed the public hearing.
Poncin stated that in the Met Council letter, one of their points of concern is that the East
Cove Sediment Project does not include post project monitoring, which was not addressed in
the MPCA letter. She asked if there is a monitoring plan. Gaetz responded that the whole
project, including the East Cove and the former disposal areas, will be under a post site
monitoring program once all the remedies are put in place. In regard to the Met Council let-
ter, he explained that the EAW form does not allow for a good description of the project.
They supplied as part of their package detailed information related to the remediation
project. It was designed to give an understanding of what was going on. He believes the Met
Council misunderstood what was to be evaluated, and the remedy plan approved by the
MPCA had already been given public notice, which would have been the proper time to ad-
dress the comments related to the work plan. Poncin asked at the conclusion of the East
Cove project would they test to see if the PFCs are removed. Gaetz responded that a testing
protocol is not a part of this particular remediation project. He explained that as part of de-
veloping the design for this project, hundreds of samples from more than 60 years of dispo-
Excerpt from Planning Commission Minutes
3M East Cove Environmental Assessment Worksheet
April 25, 2011
Page 3 of 4
sition were collected within the cove area. There is approximately two feet of clean granular
material on the surface, and below that is the sediment layer, which is 4.5 to 5 feet deep.
That layer is the material they will be removing. Below the sediment area is virgin soil and
clay that is not impacted. Based on the data collected during the investigations, they have
established the elevations to which they need to excavate. They will be utilizing a floating
barge to excavate under the water using GIPS-controlled equipment based on very good sur-
vey data. They will remove material down to the targeted depth and use visual acuity to con-
firm that the sediment has been removed.
Rambacher asked for clarification on if there will or will not be tests after the fact. Gaetz re-
sponded that there will be no physical material testing for confirmation of removal because it
is not a practical method in this type of environment. However, there will be an ongoing
groundwater monitoring program supporting the overall remedy. He stated that one of the
most important of the other aspects of this project is the installation of new barrier wells
along the east side of the site and coupled with the existing production wells that are on the
site, this will provide hydraulic control over the site. Basically, the wells intercept water before
going into the river. It is not possible to get all the material out, as some has gone down into
the water table, but that material will be recovered through these extraction wells. Once it is
recovered through the extraction wells, that water will be redirected back into the plant and
before it is discharged, it will be treated with activated carbon. They will basically remove the
PFCs that remain in the groundwater before the water goes back into the river. The objective
of the sediment removal project is to remove the source material, and the objective of the
barrier well system is to assure that any PFCs that possibly remain does not get to the river.
Rambacher asked for a quick overview of a barrier well. Gaetz responded that as part of the
project, 3M established two hydraulic barrier wells on the western portion of the property.
Those wells extract water on a continuous basis. This water is used in the facility and then
goes through their wastewater treatment system before it is discharged. They discovered
that hydraulic control only goes a certain distance to the east of those wells, so they installed
two additional high capacity wells on the eastern portion of the property and are waiting for
the opportunity to do some extended pump testing to make sure they have complete cover-
age along the bluff. In concert with the wells that currently exist, these wells keep anything
that might be in the groundwater from getting to the river. These additional wells will extend
that control all the way to the eastern boundary of Ws property. Rambacher asked if the
barrier wells are pumping water out of the ground and bringing it back to the plant. Gaetz re-
sponded that it is brought back to the plant and re -used within the facility. They are estab-
lishing carbon treatment systems sufficient to treat all the extracted groundwater at the site
before it is discharged through their normal wastewater process.
Pearson made a motion to recommend acceptance of the Findings of Facts on the EAW
for the East Cove Sediment Removal Project proposed by 3M Company and declare a
negative declaration on the need for an EIS for the East Cove Sediment Removal Project
proposed by 3M Company. Rostad seconded. Motion passed unanimously (6 -to -0
vote).
Excerpt from Planning Commission Minutes
3M East Cove Environmental Assessment Worksheet
April 25, 2011
Page 4 of 4
Rambacher made a motion to recommend approval of the conditional use permit to
allow removal of sediment from the East Cove at 3M Cottage Grove, subject to the
conditions listed below. Poncin seconded.
1. 3M must comply with the remedial actions documented in the Minnesota Deci-
sion Document made by the Minnesota Pollution Control Agency staff in
approving the recommended response action alternatives.
2. 3M will obtain all required State permits before excavation begins.
3. A copy of the National Pollution Discharge Elimination System (NPDES) general
storm water permit from the MPCA must be given to the City.
4. 3M will provide a copy of the Stormwater Pollution Prevention Plan (SWPPP)
and a copy of all the erosion control inspections to the City Engineer.
Motion passed unanimously (6 -to -0 vote).