HomeMy WebLinkAbout14 City FacilitiesPSCH Construction /Project Schedule October 26, 2011 1. Excavation, footings, foundation Oct 11 -Feb 2012 2. Utilities Oct -Nov 2011 3. Bond Sale Dec 2011 4. Slab Mrch 2012 5. Steel /Plank Feb- Aprl2012 6. Interior framing Mrch -July 2012 7. Masonry Aprl -Sept 2012 8. Electrical May -June 2012 9. HVAC May -June 2012 10. Drywall June 2012 11. Sdw /Ext lighting June 2012 12. Finishes Jul -Aug 2012 13. Landscape Jul -Aug 2012 14. Punchlist /Commissioning Aug -Oct 2012 15. FFE Sept -Oct 2012 16. Roofing Sept -Oct 2012 17. Final Oct -Nov 2012 PSCH Construction Schedule 102611 Community Pool / Community Room Project Schedule Based upon 2012 Referendum; 2013/14 Construction Years October 25, 2011 Historical 1. Current/Proiected 1. Staff review of Community Room Reuse 2. Design Charette on Community Room 3. Community Center Task Force 4. Council Review of Project Plan 5. All Commission Mtg 6. Concept Drawings (project budget deficit) 7. Task Force Mtgs 8. Council Referendum Question 9. Referendum (project budget deficit) 10. Council Budget Authorization for 2013/14 11. Architect Selection 12. Council CIP 2013 -17 Adoption 13. Design 14. Site Plan Review 15, Construction Drawings 16. Bid Award Process 17, Bid Award Community Room 18. Bid Award Community Pool 19. Site Prep / Pool 20. Substantial Completion Community Room 21. Substantial Completion Community Pool 22. Bond Sale 3 months Oct -Dec 2011 Community Pool Timellne 102511 Dec 2012 Dec 2012 Dec 2012 Jan. 14, 2012 Feb -Apr 2012 Feb -Aug 2012 May 2012 Aug 14, 2012 Sept. 2012 3 months Sept -Nov 2012 Dec. 2012 4 months Dec. /12 -Feb 2013 2 months Feb -March 2013 3 months Apr. -June 2013 2 months July -Aug 2013 August 2013 Sept. 2013 Sept -Nov 2013 March 2014 July 2014 Date? Community Pool Timellne 102511 Fire Station #2 Repair /Replacement Schedule Based upon 2016 CIP Construction Year October 24, 2011 Historical Council 2012 -16 CIP Workshop 1. Memo: Byerly re: Facility Locations 4/4/05 2. Memo: Redenjus re: New Bay Space Rec's 5/6/05 3. Council Receipt of Space Needs Report 3/15/06 4. City Facilities Project Scenarios 5/31/06 5. Council Receipt of Building Inventory 6/16/10 6. Fire Facilities Summary 10/2010 7. Memo: McMahan /LaBrosse re: Facil. Maint. 1/20/11 8. Memo: Schroeder: Planning Numbers 3/4/11 9. Memo: Byerly: Station 2 Needs Summary 9/16/11 10. Memo: Byerly: Station 2 Needs 5/10/11 11. Memo: Byerly: FD Action Items 10/16/11 12. Memo: Byerly: Equipment Housing 10/19/11 Current/Prolected 1. Council 2012 -16 CIP Workshop 10/19/11 2. Council 2012 -16 CIP Adoption 12/7/11 3. Station Consolidation Report Jan -Sept 2012 4. Phase One and Two Environmental Report Jan -Sept 2012 5. Create Space Needs Budget Sept. 2012 4. Council 2013 -17 CIP Adoption Dec. 2012 5. Create Budget Authorization for 2014 -17 Sept. 2013 6. Council 2014 -18 CIP Adoption Dec 1013 7. Architect Selection 3 months June -Aug 2014 8. Programming 2 months Sept -Oct 2014 9. Schematic Design 3 months Nov 2014 -Feb 2015 10. Design Development 4 months Feb -May 2015 11. Site Plan Review 2 months June -July 2015 12 Drawinas 3 months Aua - Nov 2015 13. Best Value Bid Process 3 months Nov 2015 to Feb 2016 14. Station #2 Bid Award 2 weeks February 2016 15. Station #2 Notice To Proceed 2 weeks February 2016 16. Station #2 Substantial Completion 14 months April 2017 17. Station #2 Final Completion 2 months June 2017 FD2Timeline102011 PSCH, Rec Project and FD2 Schedule Alignment Oct -11 PSCH Rec FD2 Excav /foot /found Utilities Bond Sale Staff Review Staff Review Charette /Task Force /Council CIP Adoption Slab Steel /Plank Interior Framing Masonry/Elec /HVAC Drywall /Ext Light Finishes /Landscape Punchlist /FFE Roofing Final All Commission Concepts /Proj Estimating Task Force Comunication Proj. Approach Approval Referendum Question Referendum Election Budget Authorization Architect Selection Architect Selection CIP /Design- Design Site Plan Site Plan Construction Drawings Construction Drawings Construction Drawings Bid Process Bid Process Bid Award Site Prep Begins Bond Sale Subst. complete /Room Subst. complete /Pool Phase One and Two Phase One and Two Phase One and Two Phase One and Two Phase One and Two Phase One and Two Phase One and Two Phase One and Two Space Needs Budget CIP Adoption Space Needs Space Needs Space Needs Space Needs Project Estimating Proj. Approach Approval Design Budget Architect Selection Architect Selection Architect Selection Date Yr 2011 Oct Nov Dec Yr 2012 Jan Feb March April May June July Aug Sept Oct Nov Dec Yr 2013 Jan Feb March April May June July Aug Sept Oct Nov Dec Yr 2014 Jan Feb March April May June July Aug Const. Budget/Program. Sept Programming Oct Schematic Design Nov Schematic Design Dec Yr 2015 Schematic Design Jan Design Development Feb Design Development March Design Development April Design Development May Site Plan Review June Site Plan Review July Construction Drawings Aug Construction Drawings Sept Construction Drawings Oct Construction Drawings Nov Best Value Dec Yr 2016 Best Value Jan Bid Award Feb Construction Start March Bond Sale April May June July Aug Sept Oct Nov Dec 1' WITan Jan Feb March Substantial completion April Final Completion May June July Community Center Task Force's Process Summary MEETING DATE QO T I ON DISCUSSION TOPICS November 13, 2000 The Parks Recreation and Natural Resources Commission discussed topics they wanted to discuss with the City Council for a future joint meeting. The Commission asked about scheduling a community center workshop. December 2000 Community center survey of 12 facilities within the metropolitan area was presented to the Parks Recreation and Natural Resources Commission. January 8 2001 Community Center revenues from other communities was presented to the Parks, Recreation and Natural Resources Commission. February 12, 2001 I Community center survey results were updated and presented to the Parks, Recreation and Natural Resources Commission, May 14 2001 The Parks Recreation and Natural Resources Commission discussed the timeline fora community center and requested that this matter be discussed at a future joint meeting with the City Council. i June 11, 2001 t Parks Recreation and Natural Resources Commission was presented with additional survey information. The Commission suggested that the information should be distributed to other interested parties A list of proposed uses within a community center was developed. August 13, 2001 I Parks Recreation and Natural Resources Commission expressed an interested in obtaining more information about a private /public partnership for a proposed community center. September 10, 2001 Parks Recreation and Natural Resources Commission reviewed the draft community center scopinq sheet and suggested that comments from the Senior Center Washington County YMCA other city advisory commissions City Council and Cottage Grove Athletic Association be solicited. The Commission discussed banquet facilities and public meeting rooms. i November 12, 2001 Community center scopinq survey draft was reviewed by the Parks Recreation and Natural Resource Commission. The Commission suggested the scopinq survey be distributed to city advisory commissions City Council other civic groups and local religious institutions. Febn,ary 11. 2002 March 11, 2002 Parks Recreation and Natural Resources Commission reviewed the results of the Communitv Center Scooina Survey #1. Pool /Indoor water park ranked high. Parks, Recreation and Natural Resources Commission discussed how to assist City Council in researching and investigating the development of a community center. April 8, 2002 Parks, Recreation and Natural Resources Commission adopted 2002 Goals and Objectives, Short Term Goal #3 assisting the City Council in researching and investigating into development of a community center. Future joint meeting with City Council for direction and layout guidelines for 2002. Page 1 of 5 Community Center Task Force's Process Summary May 13, 2001 Parks, Recreation and Natural Resources Commission discussed the idea of a community center in Cottage Grove. Commission members were encouraged to visit other community centers. September 18, 2002 I Joint meeting with City Council and Parks, Recreation and Natural Resources Commission. Community Center was discussed. October 16, 2002 Parks, Recreation and Natural Resources Commission discussed the City Council's direction that the Commission continue to pursue a needs assessment for a community center. Commission members discussed the survey that was sent out in the winter of 2001 and identified sites within the community center where a community center could be located. November 11, 2002 Parks, Recreation and Natural Resources Commission held community center workshop and developed a planning outline. December 11, 2002 Parks, Recreation and Natural Resources Commission developed a Planning Process Outline. Developed six goals. Concerns expressed for replicating facilities and I serviced, competition with existing businesses, supported an idea that a coffee shop be with a community center and discussed the idea of leasing space in the community center for other businesses. January 13, 2003 C private Parks Recreation and Natural Resources Commission discussed future sites for community center. A map showing the general location of future parks was presented to the Commission The City's Finance Director provided the Commission with a memorandum the generally described tax implications if a community center was approved The Commission discussed the possibility of a public/private partnership, health clubs ISD 833 and operating costs. February 10 2003 Parks Recreation and Natural Resources Commission reviewed the revised community i center location map The process of preparing an areawide planning study for the East Ravine area was discussed The Commission discussed an idea of athletic fields, open space trails and other future public buildings. March 10, 2002 Parks Recreation and Natural Resources Commission discussed the potential sites for a community center. September 8 2003 It was reported to the Parks Recreation and Natural Resources Commission that a Task Force was being formed for the preparation of a planning document for the future growth in the East Ravine The Commission expressed an interest that athletic fields and cmmnlex he considered with the community center. November 8, 2003 I The Parks Recreation and Natural Resources Commission was informed that a Citizen Advisory Team will be formed to begin work on master planning the area of the community known as East Ravine The community center topic might be part of that process. December 8, 2003 It was reported to the Parks Recreation and Natural Resources Commission that the Citizen Advisory Team for the East Ravine will meet on December 9 2003. The Citizen Advisory Team has tentatively scheduled their first public open house for January 8 Page 2 of 5 Community Center Task Force's Process Summary Page 3 of 5 2008 at River Oaks Municipal Golf Course, The Parks Recreation and Natural Resources Commission was updated on the East Ravine Open House. The Commission recommended their support of the Concept C January 12, 2004 land use map. February 4, 2009 GitY-Hall City Council discussed the idea to create a community center task force. • A community center work plan (tentative) presented to the City Council. • Work Plan proposed the following tasks: o Task Force to review project scope and fiscal ability. February 18, 2009 G6g4a4 o Collect information on community center. o Identify options. o Select Preferred Option. o Prepare final report for City Council's review and action. March 9, 2009 Gity Hall • A volunteer from the Parks, Recreation and Natural Resources Commission was asked to serve on the Com nun it Center as Force. March 10, 2009 Gity Hall • A volunteer from the Advisory Committee on Historic Preservation was asked to serve on the Community Center Task Force. March 18, 2009 G*Ha8 • City Council appointed 25 residents to serve on the Community Center Task Force. April 15, 2009 '} City • City Council appointed five additional residents to serve on the Community Center Task Force. • Community Center Task Force's first meeting. • Discussed future meeting dates and times. • Work program. April 28, 2009 • Logistics for touring community centers in other communities. lea Arer; a . Recreational Facility Needs Study, 2005 was distributed to members. • Discussed preferred sites, conceptual site, facility designs, and financing options. Parks, Recreation and Natural Resources Commission was informed that the City May 11, 2009 City Hall Council had formulated a Community Center Task Force. • Overview of community centers in Chaska, Inver Grove Heights, Maple Grove, South Shoreview and Eagan. June 2, 2009 Washington • Cottage Grove's Public and Private Facilities Inventory was presented. Cottage Grove's Pubic Parks and Athletic Facilities Inventory was presented. • Potential community center facilities were identified and ranked facility priorities. i Parks, Recreation and Natural Resources Commission was updated on the Community June 8, 2009 66Lt4au I Center Task Forces progress. i i Parks, Recreation and Natural Resources Commission was updated on the Community July 13, 2009 city Hall Center Task Force's progress. September 14, 2009 City Hall Parks, Recreation and Natural Resources Commission was updated on the Community Center Task Force's progress. • Reviewed community center amenities in Inver Grove Heights, Shoreview, October 6, 2009 Ise Arena Minnetonka, Chaska, Maple Grove and Eagan. • Task Force members supported the preparation of a market analysis to bett T Page 3 of 5 Community Center Task Force's Process Summary understand the market area and types of facilities that the market area could support. • Reviewed the results of the facility priorities ranking from the June 2, 2009 meeting. • Idea of a civic campus center concept was discussed. • Future Vision 2030 Comprehensive Plan was presented. • Staging Plan, Future Parks and Open Space map, Future Trailway Plan, and January 5, 2010 City Wall Proposed Roadway Functional Classification map were displayed. • Eleven potential community center sites were identified, discussed and ranked. January 12, 2010 City Hall Economic Development Authority was updated on the Community Center Task Force's proqress, • Candidate sites for a community center were discussed. March 2, 2010 City Hall • Ballard -King & Associates' Market Analysis was presented. • Program facilities were discussed. • Conceptual drawing of a civic campus site north of the Washington County South Service Center site was presented. • Conceptual development plan fitting a public safety /city hall, community center, county library and parking ramp on the Norris Square site was discussed. April 6, 2010 City Hall • Second part of Ballard -King & Associates' Market Study was discussed. • Partnership models with private (for profit) and non - profit was discussed. • City owned and operated facility was discussed. • Community Center and private fitness membership fees were presented, Parks, Recreation and Natural Resources Commission was updated on the Community April 12, 2010 City Wall Center Task Force's progress. • Ballard -King & Associates preliminary market analysis and facility space allocation was discussed. • YMCA project in White Bear Lake, Andover, Elk River, and Lino Lakes was presented. May 4, 2010 Gity -Wa4 • Financing alternatives and options were discussed. • Facility characteristics were compared for the community centers in Inver Grove Heights, Shoreview, Maple Gove, Maplewood, and Chaska; including the Lifetime Fitness and Gold's Gym in Woodbury; and the Southeast YMCA in Woodbury. • Ballard -King & Associates' revised program and preliminary market analysis ionrlo }inn nra nromn}orl • Banquet facilities at River Oaks Municipal Golf Course and Mississippi Dunes June 1, 2010 mill Golf Links were described. • Community center architectural design, event size flexibility, financing options, property tax impacts, voter referendum and community survey topics were discussed. • Public Safety /City Hall project and preliminary site renderings was displayed. August 16, 2010 City Hall • Potential partnering with St. Paul Area YMCA discussion. • Construction cost scenarios if the City did nor did not partner with t he YMCA were Community Center Task Force's Process Summary Page 5 of 5 discussed. • Presentation from the YMCA regarding facilities, programs and partnerships. September 7, 20101 City • Model design, financial considerations, operation costs, ownership responsibilities and partnership scenarios were discussed. City Council was informed that the City Economic Development Authority and September 15, 2010 YMCA may sponsor a community survey to determine the need for a community center in Cottage Grove. . Public Safety /City Hall project and Ravine Parkway bridge design presented to November 15, 2010 City Hall the Task Force. •Six site development concepts for the Ravine Parkway site were discussed. November - December YMCA initiates community survey. 2010 Parks, Recreation and Natural Resources Commission was updated on the January 13, 2010 Gity -Mall Community Center Task Force's progress, January 25, 2011 City Hall YMCA market study and results from their phone survey were presented. • A copy of YMCA's Market Study survey was presented to the Task Force members. • Partnership options discussed. February 8, 2011 Cit • School District 833 future bond referendums discussed. • Task Force unanimously approved a motion for the City to partner with the YMCA. • Task Force's facility preferences were summarized. • Task Force supported idea of combining a county library and community center. • Draft Community Center Task Force Report was presented to the Task Force. • Criteria used in ranking the preferred sites were discussed. March 1, 2011 Sty MaA . Task Force unanimously approved a motion that the proposed Public Safety /City Hall site along Ravine Parkway be the preferred site for a community center. i • Joint City Council and ISD 833 School Board meeting. March 2, 2011} m Future referendums by the School District and a community center referendum i were discussed. Parks, Recreation and Natural Resources Commission was presented the results of 6Anrrh IA 9n11 Q.itvHAI, tha YKACA'a mnrkat aturiv March 26, 2011 Bourse The Draft Community Center Task Force Report was presented to the All Commission Workshop meeting. Parks, Recreation and Natural Resources Commission was updated on the Community April 11, 2011 i Gity -Half Center Task Force's progress and a copy of the draft report was presented. April 20, 2011 City Hall Final Report presented to the City Council Report received and placed on file. Page 5 of 5 Community Center Task Force's Process Summary Page 6 of 5 City Council discussed the proposed Highland Park splash pad project. Council also June 1, 2011 City Hall acknowledged Community Center Task Force's work relative to a community center and aquatic facilities. • The Community Center Task Force was informed that the City Council received and placed on file their Final Report. June g, 2011 • The Community Center Task Force was presented an update on the Public Safety /City Hall Project and YMCA Partnership discussions. • Referendum process was discussed. Parks, Recreation and Natural Resources Commission was updated on the Community June 13, 2011 City Hall Center Task Force's progress. A draft "Letter of Intent" agreement with the YMCA was presented to the Economic j June 14, 2011 City Hall Development Authority. i • Community Center Task Force discussed referendum strategies and development of public information materials for residents to make an informed decision on the bond June 21, 2011 City Hall referendum ballot question. • Community Center Task Force Chairperson or Co- Chairs was discussed. Community Center Task Force discussed the YMCA Community Center Space July 26, 2011 City Hal Planning Concept Study, City Council decided not to have a bond referendum question for a community center August 10, 2011 City Hall or any other public capital improvement project on this year's election ballot. Page 6 of 5 Cottage Grove Park Buildings; July 2011 Park Square Date Building Footage Constructed Hamlet 990 1960 Armstrong 486 1965 Hamlet 1200 1970 PTV 1296 1974 rehab 2010 Woodridge 1444 1980 Highlands 952 1985 expanded 2011 Lamar 888 1985 Hearthside 952 1985 Station 3 666 1994 Kingston 1410 1997 P. Thompson 2400 2003 City of Cottage Grove Facility Inventory (by year of construction and major remodeling) Old Town Hall 1881 Public Works Mower Garage 1962 Public Works Storage Building 1962 City Hall 1968 Public Works Garage 1968 City Hall Expansion 1973 Public Works large storage 1985 Fire Station #2 1985 City Hall PD garage expansion 1985 Public Works small storage 1986 Fire Station #1 Remodel 1994 Fire Station # 3 and Rec Room 1994 Fire Station # 4 1994 City Hall Remodel 1995 Public Works Expansion 1997 Public Works Salt Storage 2000 Park and Rec Facilities Hamlet #2 1960 Pool and Rec Center 1962 Armstrong Warming House 1965 pop: 4,851 (1960) pop: 12,200 pop: 15,300 .•. =I. pop: 22,935 (1990) pop: 30,582 34,463 (2010 est) 34,657 (2011 est) 34,927 (2012 est) Hamlet #1 1970 Ice Arena 1974 Nina Shelter 1974 Pine Tree Park 1974 Oakwood Shelter 1976 Woodridge Park 1980 Hearthside Park 1985 Highlands Park 1985 Lamar Park 1985 Lamar Shelter 1985 Lamar Shelter #2 1985 Woodridge Shelter 1990 River Oaks Club House 1990 River Oaks Maintenance Bldg 1990 Pool Shelter 1995 Kingston Park 1997 River Oaks Banquet Facility 1999 Hamlet Shelter 2000 P. Thompson Park 2003 West Draw Shelter 2007 Ice Arena Expansion 2008 Well Houses and Towers #1 (8193 Grange Blvd) #2 (8780 Grenadier Ave) 1958 Tower @ 8193 Grange (150K) 1959 #3 (8313 Hyde Court) 1960 #4 (no building; 8350 81 St. Lane) #5 (no building; 8407 83rd) #6 (no building; 8550 81 St ) 1972 Water Booster (8540 81 St ) 1972 Tower @ 6700 Inwood (1.5m) 1972 #7 (8440 Foothill) 1977 #8 (8320 Foothill) 1977 #9 (no building; 8664 81 St ) 1981 Tower @ 8520 81 (3.0m) 1981 Tower @ 8149 Innsdale (1.5m) 1981 #10 (59 and Heath) 1984 Tower @ 6950 Meadowgrass (_ m) 199_ #11 (70 and Idsen) 2004