HomeMy WebLinkAbout2013-05-01 PACKET 07.A.REQUEST OF CITY COUNCIL ACTION COUNCIL
MEETING
DATE 5/1 /13
PREPARED BY: Community Development
ORIGINATING DEPARTMENT
AGENDA
ITEM #
.
Jennifer Levitt
STAFF AUTHOR
*****:�******************�********�**************
COUNCIL ACTION REQUEST:
Consider awarding the bid for the 2013 Pavement Management Project Utility and Street
Improvements to Hardrives, Inc. in the amount of $5,343,534.14, including Alternatives #1
and #2.
STAFF RECOMMENDATION
Award the bid for the 2013 Pavement Management Project Utility and Street Improvements to
Hardrives, Inc., who submitted the lowest of the four bids received, including Alternatives #1
and #2.
BUDGET IMPLICATION: $5,358,000 $5,343,534.14
BUDGETED AMOUNT ACTUAL AMOUNT
SUPPORTING DOCUMENTS
� MEMO/LETTER: Memo from Jennifer Levitt dated 4/25/13
Letter from Mike Boex, Bolton & Menk, Inc., dated 5/1/13
� RESOLUTION: Draft
❑ ORDINANCE:
❑ ENGINEERING RECOMMENDATION:
❑ LEGAL RECOMMENDATION:
� OTHER: Bid Tabulations
ADMINISTRATOR'S COMMENTS
Administrator Date
********************�************��*************
COUNCIL ACTION TAKEN: ❑ APPROVED ❑ DENIED ❑ OTHER
CITY OF COTTAGE GROVE
� MINNESOTA
To: Honorable Mayor and City Council
Ryan Schroeder, City Administrator
From: Jennifer M. Levitt, P.E., City Engineer
Date: April 25, 2013
Re: 2013 Pavement Management — Bid Award
Backqround/Discussion
The bids for the 2013 Pavement Management were found to be favorable in comparison to the
engineer's estimate. The low base bid was $5,343,526.27, compared to the engineer's estimate of
$5,358,000.
As part of the bid package, four alternatives were bid as part of the project. Alternative #1 was for
replacement of the concrete pads under the community mail boxes along Indian Boulevard. Alter-
native #2 was for community mailboxes in areas C1 and C2. The mailbox concrete pads are in poor
condition generally and have issues with proper slope for drainage, making for hazardous conditions
adjacent to the mailboxes. In some cases the concrete pad may be damaged or will not be aligned
at the proper elevation of the new concrete curb and gutter. Overall, the replacement of the pads will
provide a safer situation and improve the aesthetics of the neighborhood. The following are photos
of some of the community mailboxes:
It is staff's recommendation to accept Alternative #1 and Alternative #2 in the value of $32,816.84.
Alternative #3 was for six electrical pedestals (120 V receptacles and 1-120 Volt receptacles) at
Kingston Park for the Strawberry Festival for a cost of $24,845.86. Alternative #4 for was for six
pedestals (1-120 Volt, 1-50Amp, 1-30 Amp receptacles) for the cost of $34,906.69. After review of
the actual costs for different electrical pedestal options for the Strawberry Festival, it is above the
feasibility value of $20,000 that was estimated. Staff is not recommending proceeding with Alter-
natives #3 or #4 at this time. The Strawberry Festival is for a short duration each year, and onsite
generators provide the most cost effective option for supplying power to vendors and the stage
productions.
Recommendation
It is recommended the Council award the 2013 Pavement Management Project to Hardrives, Inc. for
the total base bid of $5,343,526.27, plus Alternative #1 and Alternative #2 totaling $5,376,343.11.
•� �G1!_TC�N � M� N K, I NC�
� Consulting Engineers �C Surveyors
" 2035 County Road D East • Suite B• Maplewood, MN 55109-5314
Phone (651) 704-9970 • Fax (651 } 704-9971
www.bolton-menk.com
May 1, 2013
Honorable Mayor and City Council
City of Cottage Grove
12800 Ravine Parkway South
Cottage Grove, MN 55016
Re: Bid Results
2013 Pavement Management Project
BMI No. N15.105420
Dear Honorable Mayor and City Council:
Bids for the 2013 Pavement Management Project were opened on Thursday, April 18, 2013. Four (4) bids
were received and ranged from $5,343,526.27 to $5,958,103.70. A Bid Tabulation has been included. Copies
will also be distributed to each Bidder after award by the City. The following is a summary of the Bids
received:
Low 2 3 4
Contractor: Hardrives, Inc. Northwest T.A. Schifsky & Bituminous
Asphalt, Inc. Sons, Inc. Roadways, Inc.
Total Base Bid: $5,343,526.27 $5,531,321.20 $5,814,416.53 $5,958,103.70
Bid Alternate #1:
Indian Blvd Community Maiiboxes
Bid Alternate #2:
C1/C2 Area Community Mailboxes
Bid Alternate #3:
Kingston Park Electrical
Bid Alternate #4:
Kingston Park Electrical
$3,806.18 $3,483.80
$29,010.66 $26,831.40
$24,845.86 $27,530.00
$34,906.69 $45,498.00
$2,672.42
$20,527.26
$24,390.90
$34,669.94
$6,290.00
$47,670.00
$25,110.35
$35,424.45
The low Bidder on the Project was Hardrives, Inc. with a Tota) Base Bid Amount of $5,343,526.27. This
compares to the Engineer's Estimate of $5,358,000. If the City Counci) decides to award the Project to the
low bidder, then Hardrives, Inc. should be awarded the Project on the Total Base Bid Amount of
$5,343,526.27. Any combination of Bid Alternates can be selected without affecting the low bidder.
If you have any questions, please feel free to contact me at 651-968-7674.
Sincerely,
BOLTON & MENK, INC.
Mi�Boe�
Senior Project Manager
DESIGNING FOR A BETfER TOMORROW
Bolton & Menk is an equal opportunity employer
ABSTRACT OF BIDS
2013 PAVEMENT MANAGEMENT PROJECT STREET AND UTILITY IMPROVEMENTS
CIiY Of COTTAGE GROVE, MINNESOTA
S.A.P. iS0-125-001 �
PROJECT NO. N15.105420
Oolo; 4I18201J
ITEM
APPROX.
PART1 •IN�IAN BOULEVARD
1 MOBILIZATION
2 REMOVE CONCRETE CURB AND GUTTER
3 REMOVECONCRETEPAVEMENT
4 REMOVEBITUMINOUSSTREET
5 REMOVE MANHOLE OR CATCH BASIN
6 REMOVE SIGN
7 SAWING CONCRETE PAVEMENT (F�LL DEPTM)
e SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
9 REMOVE AND REPL4CE CONCRETE CURB AND GUTiER (HIGH EARLI�
1� REMOVEANDREPLACECONCRETESIDEWALKORPEDESTRIANRAMP
17 COMMONEXCAVATION(EV)-STREET
12 TOPSOIL BORROW (LV) MODIFIED
13 EXCAVATION SPECIAL
14 SUBGRADEPREPARATION
15 SKID LOADER
76 STREETSWEEPER(WITHPICKUPBROOM)
17 AGGREGATEBASECLASSS
78 MILL BITUMINOUS PAVEMENT (1.5)
79 MILL BITUMINOUS PAVEMENT FOR CRACK REPAIR, INCL PATCH
20 JOINTMHESIVE
21 FULL DEPTH RECLAMP,TION
72 HAU�BITUMINOUSPAVEMENTRECLAM4TION(L�
23 BITUMINOUSMATERIALFORTACKCOAT
24 NPE SP t2.5 WEARING COURSE MIXTURE (3,C) SPECIAL
25 TYPE SP 12,5 WEARING COURSE MIXTURE (3,C)
26 NPE SP 12.5 NON WEARING COURSE MUCTURE (3,B)
27 T'PE SP 72,5 NON WEARING COURSE MUCTURE (3,B) FOR PATCNING
28 PATCHBITUMINOUSDRIVEWAYORTRAIL
29 72" RCP STORM SEWER CLASS 5
30 CONNECTTO EXISTING STORM SEWER STRUCNRE
31 CONNECTTO EXISTING STORM SEWER PIPE
32 4' CIPP, te" RCP STORM SEWER
33 IRRIGATION SYSTEM REPNR
34 ADJUSTVALVEBOX
35 REPLACE VALVE BOXTOP SECTION
36 VALVEBOXEXTENSION
37 HYDRANTRISER
38 ADJUSTSTORMSEWERCATCHBASINCASTING
39 ADJUST STORM SEWER CATCH BASIN CASTING, INCL NEW R-3290.V8 CSTG AND NEW H�PEAD.1 RINGS
40 ADJUST STORM SEWER MANHOLE CASTING
47 ADJUSTSANITARYSEWERMANHOLECASTING
42 2k3' STORM SEWER C8, INCL R3290.V8 CSTG AND HDPE ADJ RINGS
43 4' DIA STORM SEWER CBMH, INCL RJ290�VB CSTG AND HDPE ADJ RINGS
44 PATCHDOGHOUSE-STORMSTRUCTURE
45 CONCRETEHYORANTACCESS'PAD
46 CONCRETE CURB AND GUTTER, DESIGN B4t8
47 G' CONCRETE DRNEWAY PAVEMENT (RESIDENTIAL) (HIGH EARLI�
4B 7" CONCRETE DRIVEWAY PAVEMENT (COMMERCIAy (HIGH EARLI�
49 T' CONCRETE VALLEY GUTTER (HIGH E4Rl,�
iLUMPSUM
5,820 LIN FT
2,100 S� YD
835 S� YD
2 EACH
21 EACH
265 LIN FT
1,030 LIN FT
1,510 UN Ff
5,565 SQ FT
35 CU YD
860 CU YD
1a EACH
'13,670 S� VD
30 HOUR
30 HOUR
50 TON
14,905 SQ YD
4,050 LIN FT
17,495 LIN FT
13,370 S� YD
750 CU YD
2,970 GALLON
2,840 TON
1,36� TON
1,810 TON
1,35� SQ YD
835 SO VD
45 LIN FT
2 EACH
1 EACH
1 EACH
2 EACH
17 EACH
4 EACH
6 UN FT
7 LIN FT
15 EACH
t EACH
6 EACH
27 EACH
2 EACH
1 E4CH
1 EACH
225 5� FT
5,820 LIN FT
80 S� V�
90 S� YD
90 SQ YD
i
Hardrives inc.
538,300.00
$2.03
$2.45
$2.03
saai.aa
$26.07
$4.67
51.90
519.19
$5.32
$3t28
$22.00
E312.80
$0.76
50.01
$122.76
517.82
50.98
$3.00
so.se
E�.88
$5.43
52.20
573.17
$fi3.29
$54.&5
510.00
874.98
540.14
5599.54
$437.92
$2,293.87
5156.40
$265.42
b203.32
$161.61
$609.96
8193.18
$719.56
$507.74
8505.65
$2,080.13
$2.476.34
$286.73
$4.69
5923
$46.92
$SOAS
560.47
St,721
SL95!
$28,976
$29.605
$1,094
878,920
$3,728
$70,389
80,
$3,fi64.
5891.
aia,sos.
$12,150.
87,816,
$11,765,
sa,o�z,
$6.534.
�,zo�,eoz.
$86,074.
599,278.
573,500.
$12,508.
$7,806.
St.199.
$437.
$2,293.
$372.
84,512.
z a a
Northwest Asphalt, lnc. I T.A. Schifsky & Sons, inc. I Bituminous Roadways, Inc.
$75,750.00
5275
35.35
$3.50
saoo.00
$25.00
$3.00
82.�0
szs.n
$725
535.00
szzoo
$350.00
E0.6�
$100.00
$725.0a
$25.00
5o.so
$3.75
S1.t0
$1.90
sie.es
$3.00
$68.75
362.35
$53.70
$13.75
820.65
$37.65
$650.00
$650.00
az,zoo.00
ssoo.00
$300.00
$375.00
5450.00
ssa3.00
$200.00
$620.00
5500.00
b500.00
$1,692.00
$2,'176.00
5200.00
$5,75
$9.95
$50,30
$55.95
$58,75
F3�
s�a,
$8,
t95,
884.
597.
$18,
$17.
57,
$1,
$
az.
s�.
$5,
S1.
au,000.00
$3.00
E4.12
$3.09
ssie.ao
818.54
$208
$206
818,75
56.08
$30.90
3at2o
E2o6.o0
$1.00
580.00
sioo.00
520.00
stia
$258
$1.00
51.W
ss.ao
$2.50
569.00
$64.W
$57,00
$24,00
823.00
$40.t7
82,781.00
$1,500.00
52,266.00
5515.oa
8262.65
$92.70
572.10
5530.45
$775.85
$7,030.00
$48825
$48925
51,781.90
sz,oie.so
$154.50
$5A5
89.D
54223
547.74
857.01
$17
82,580.1
St236.0
F�
F7
�
�
.`�
a2s,000.00
55,00
510.00
57.00
5405.�0
$26.35
$2.fi0
$2A5
$3020
$6.40
s2z.ao
szs.zs
aias.00
5D.50
$135.00
$135,00
aisso
ai.ss
$2.75
51.15
57.45
aii.as
$3.00
573.00
$fi5.00
$50.50
531.35
529.65
$40.50
$605.00
$445.00
52,315.00
5765.00
s2so.00
$335.00
aiss.00
$6t5A0
$205.00
8740.00
$Q95.00
8500.00
$2,100.00
52,500.00
auo.ao
84.75
59.30
847.%
$50,W
$61.00
azs,000.00
$29,100.00
$21,000.00
55,845.00
$810.00
5553.35
5689.00
52.523.50
$45,602.00
$35,676.00
ano.00
sz�7�s.00
steso.00
as,ess.00
54,050.00
$4,050.00
ss�s.00
s�e,ssi.as
511,137.50
$13,21925
$19,386.50
58,587.50
se,sio.ao
SZ(17,320.00
888,400.00
$91,405.00
E42,322.50
$24.757.75
51,822.50
$1.210.00
saas.ao
$2,315.00
5330.00
sa,zso.00
81.3A0.00
ssso.00
$615.00
$3,075.00
s�ao.00
$2,970.00
sia,soo.00
54,2()0,00
s2,soo.aa
azeo.00
$1,068.75
$54,12fi.00
$3,788.00
$4,545.00
$5,490.00
PROIECT N0. N35.105420
omo: aiarzwo
ITEM
NO. ITEM
50 TRUNCATEDDOMES
51 PEDESTRIAN CURB RAMP
52 SALVAGEANDREINSTALLMNLBOXCLUSTER
53 TEMPORARYMFJLBOX
54 4" PVC CONDUIT CROSSING FOR STREET LIGHTS
55 HANDHOLE
56 FEED POINT
57 TNO NO 6 AN� NO 10 GROUND IN PLACE IN CONDUIT
58 PNO NO 4 AND NO 10 GROUND IN PLACE IN CONDUIT
59 TRAFFIC CONTROL
60 SIGN PANELS, NPE C
67 SILT FENCE, NPE MACHINE SLICED
62 STORM DRAIN INLET PROTECTION PER STANDARD DETAIL ERO-0B
63 STORM DRPJN INIET PROTECTION PER STANDARD DETAIL ERO-0C
64 WATER FOR TURF ESTABLISHMENT
65 HYORAULICSOILSTABILIZERNPES
66 SEEDING, INCL SEED MIX, PERTILIZER, AND HYDRAULIC SOIL STABIUZER
67 PAVEMENTMESSAGE(RIGHTARROW)POLYPREFORM
68 4"SOLIDUNEWHITE-EPDXV
69 4"DOUBLESOLIDLINEYELLOW-EPDXY
70 12" SOI.ID LINE WHITE-POLY PREFORM
71 24" SOLID LW E W HITE - POLY PREFORM
PART 2- PROJECT AREAS Ci AND C2
72 MOBILIZATION
73 FIELD OFFICE
74 TRAFFIC CONTROL
75 PORTABLE MESSAGEBOARD
76 CLEAR AND GRUB 1REE
77 REMOVE CONCRETE CURB AND GUTfER
78 REMOVE RCP STORM SEWER
79 REMOVE HDPE STORM SEWER
BO REMOVE FES
8� REMOVE RIP RAP
82 BULKHEAD 36" RCP STORM SEWER
83 REMOVEPL4YGROUNDTIMBERS
84 REMOVECONCRETEPAVEMENT
85 REMOVE BITUMINOUS STREET
86 REMOVEBITUMINOUSDRIVEWAYORTRAIL
87 REMOVE MANHOLE OR CATCH BASIN
88 REMOVE SIGN
89 SPIVAGEFENCE
9� SALVAGEANDREWSTALLSIGN
91 SALVAGEANDREINSTALLPENCE
92 MODIFY FENCE FOR 3fi" WIDE PED RAMP
93 CLOSEFENCEOPENING
94 MODIFY LANDSCAPING FOR NEW TRAlLS
95 SAWINGCONCRETEPAVEMENT(FULLDEPTH)
96 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
97 REMOVE AND REPLACE CONCRETE CURe AND GUTfER (HIGH EARLI�
98 REMOVE AND REPL4CE CONCRETE SI�EWALK OR PEDESTRIAN RAMP
99 COMMONEXCAVATION(EV)-STREET
700 COMMON EXCAVATION (EV)-TRAIL
707 SUBGRADE EXCAVATION (EVj
TOTAL PART 1 -INDIAN BOULEVARD
APPROX
�UANT. UNIT
380 S� FT
1,995 Sq FT
4 EACH
70 EACH
340 LW FT
31 EACH
3 EACH
3,745 LIN Ff
1,t7� LIN FT
1LUMPSUM
393 SO Ff
100 LIN FT
15 EACH
ZO EACH
270 M GALLON
300 POUND
3,990 SQ YD
7 EACH
t0,�10 LIN Ff
4,710 LIN FT
900 LIN FT
95 LIN FT
7LUMPSUM
1LUMPSUM
7LUMPSUM
2 VJEEK
9 TREE
36,470 LIN Ff
1,120 LIN FT
75 LIN FT
1 EACH
1 LUMP SUM
2 EACH
330 LIN FT
t,090 S� YD
57,5�0 SQ YD
5,870 5� YD
10 EACH
25 EACH
25 UN FT
2 EACH
40 LIN FT
6 EACH
t EACH
1LUMPSUM
1,OB0 UN FT
8,1&5 LIN FT
6,a90 UN FT
t,660 SQ FT
5,120 CUYD
7,370 CU YD
7.it0 CUY�
1 3 J 4
Hardrives Inc. I Northwest Asphalt, inc. I 7.A. Schifsky & Sons, Inc. I Bituminous Roadways, Inc.
Ropers, MN Shakooee. MN N. SL Paul. MN
$36.49
54,07
$47.96
$15.64
$0.07
8527.33
$3,910.01
$S.fiO
8725
572,130.00
E3128
$4.53
$69.86
$69.86
$20.85
51.01
5122
$333.65
$0.3t
$0.65
$71.47
$72.94
5165,000.00
$7,583.49
576,256.a2
5938.41
szso.s�
$2.03
$70.95
$626
$49526
51,965,43
8307.59
$4.08
$2.45
$1.53
ss.00
$364.93
azs.o�
$10.43
$130.34
$10.43
8208.53
$t56.40
5260.67
$4.62
$1.89
$20.61
$5.11
87,00
$11.47
$9.38
512,277
3
$t,965.<
$615.1
$1,346,5
$1,251
$15,02:
510,411
$40.00
55,15
smo.00
St1.00
sii.aa
$320A�
$3,850A�
$1020
571.00
$5,000.00
530.00
sa.00
$15�.00
aisa.00
aia.00
$1.50
51.00
5336.00
50.32
50.65
$17.55
$23.10
$63,000.00
ais,000.00
E5,OOOA�
asoo,oa
$400,00
82.75
$5.00
$5.00
$200.00
b500.00
$700.00
$5.00
55,35
51.45
$3.50
$350A�
azs.ao
ffi70.00
5150.00
$40.00
szaa.00
$250.00
51,000.00
$3.00
$2.00
$26.77
$7.25
817.00
$19.00
$17.00
€$7[Z31
;i
�'
$39.74
$5.05
an.m
$1�.30
so.eo
$515.00
$3,862.50
$5.53
$7.16
$30,000.00
523.95
$2.06
5154.5�
aisaso
sie.sa
$1.55
$0.95
$978.50
8�.31
so.sa
515.04
$27.30
saso,000.00
aio,soo.00
E59,000.00
ssi z.es
$360.50
82.27
St1.33
$73.39
$t,236A�
5515.00
$727.00
$7As
E3.fi1
$129
$t.03
$484.10
aie.sa
$97.85
$97.&5
$25.75
5257.50
$575,�0
$5,150.00
$200
$2.00
$78.75
$6.08
810.30
510.30
$1430
F3I']LFL!
$11,587
820,709
$8,377
�
�
$36.85 $13,266.00
anno ae,nsso
ass.00 azzo.00
572.65 St26.50
50.07 $3.40
$525.00 $16,275.00
$3,950.0� 511,&50.00
$5.65 521,75925
57.30 $8,547.00
stori.�s si,on.�s
531,60 $12,403.00
aa.zo sazo.00
s�so.00 s2,zso.00
s�BO.00 ss,oaa.00
azs.00 as,�so.00
ai.so as�o.00
a�.�o Sfi,783.00
$845.00 $5,975.00
$0.32 $3,20320
5a.s5 $3,061.50
515.35 $13,815.00
528.00 $2,fi60.00
5993,200.45
saa,soo.ao 5aa,soo.00
s�i,soo.ao aii,soo.00
az,�ssso az.tssso
asas.00 s�,eso.00
$400A� 53,600A�
$2.50 891,175.00
$71A5 $t2,376,00
$6,30 $472,50
ssoa.aa asoo.00
$1,985.00 81,985.00
$310.00 8620.00
S10S� $3,465.00
59.50 810,355.00
52.30 $118,450.00
$7.00 $40,670,00
$370.00 $3,70�.00
$26.35 $658.75
$t0,50 §262.50
$130A� $260.00
526.00 S'1,040.00
aeoo.00 aa,soo.00
$685.00 5685.00
$3,300.00 $3,300.00
$2.60 $2,808.00
$2.45 $20,05325
531.35 $790,921,50
ss.00 as,sso.00
$17.45 $89,344A�
$19.50 $25,545.00
577.45 St9,%9.50
PROJECT NO. N15.105420
Dulo: 4I18/101J
ITEM
NO. ITEM
702 TOPSOIL BORROW (L� MODIFIED
t03 EXCAVATIONSPECIAL
104 SUBGRADE PREPARATION
105 SKID LOADER
106 STREETSWEEPER(WITHPICKUPBROOM)
107 AGGREGATE BASE CLASS 5
108 AGGREGATEBASECLA555,'100%CRUSHED
109 MILLBITUMINOUSPAVEMENT(1.5")
110 MILL BITUMINOUS PAVEMENT FOR CRACK REPAIR, INCL PATCH
111 JOINTADHESIVE
112 FULL DEPTH RECLAMATION
113 SALVAGE AND RESPREAD RECLAIM MATERIAL
t14 BITUMINOUSMATERIALFORTACKCOAT
115 NPE SP 12.5 WEARING COURSE MIXTURE (2.C) SPECIAL
116 TYPE SP 12.5 WEARING COURSE MIXTURE (3,Cj SPECIAL
t17 TVPE SP 12.5 WEARING COURSE MIMURE (3,C)
718 TYPE SP 9.5 WEARING COURSE MU(TURE (2,B)
119 NPE SP'12.5 NON WEARING COURSE MIXTURE(2,C)
t20 iYPE SP'125 NON WEARING COURSE MIXTURE (3,8j
t21 iYPE SP 125 NON WEARING COURSE MIXTURE (3,B) FOR PATCHING
722 PATCHBITUMINOUSDRIVEWAYORTRAiI
123 12" CMP STORM SEWER
724 t2"RCPSTORMSEWERCL4555
125 15" RCP STORM SEWER CLAS55
126 30" RCP STORM SEWER CLA553
127 36" RCP STORM SEWER CL4S53
128 42" RCP STORM SEWER CLAS53
129 42" ARCH RCP STORM SEWER CLASS 3
130 12" CMP FLARED END SECTION
131 15" RCP FLARED END SECTION INCL TRASH GUARD
132 2'Y!' STORM SEWER CB. INCL R-3290.VB CSTG AND HDPE AD.1 RINGS
133 4' DIA STORM SEWER CBMH, INCL R-0342 CSTG AND CONCRETE STOOL GRATE FRAME
'134 4' DL4 STORM SEWER CBMH, INCL R-2501-G CSTG AND HDPE ADJ RINGS
135 4'DIASTORMSEWERCBMHWITH3'SUMP,INCLR-2501GCSTGANDHDPEADJRINGS
'136 4' DW STORM SEWER MH, INCL R-1642-B CSTG AND HDPE MJ RINGS
137 4.5' DIA STORM SEWER MH, INCL R-1642-8 CSTG AND HDPE ADJ RINGS
138 5' DIA STORM SEWER CBMH, INCL R-3?90.V8 CSTG AND HDPE ADJ RINGS
'139 7' �IA STORM SEWER MH, INCL R-1642-B CSTG AND HDPE ADJ RINGS
740 8' OW STORM SEWER MH, INCL R-1642-8 CSTG AND HDPE ADJ RINGS
141 MOOIFYOVERFLOWSTRUC7URE
142 CONNECTTO E%ISTING STORM SEWER PIPE
143 CONNECTTO E%ISTING STORM SEWER MANHOLE
141 ADJUST STORM SEWER GATCH BASIN CASTING
145 ADJUSTSTORM SEWER CATCH BASIN CASTING, INCL NEW 4' DIATOP SLAB, R-3290.V0 CSTG. AND HDPE ADJ RINGS
146 ADJUST STORM SEWER CATCH BASIN CASTING, INCL NEW 6' DIATOP SLAB, R-3290.VB CSTG. AND HDPE ADJ RINGS
147 ADJUSTSTORMSEWERMANHOLECASTING
148 ADJUSTSANITARYSEWERMANHOLECASTING
149 RIP RAP CLASS 3
150 PATCHDOGHOUSE-STORMSTRUCNRE
151 PATCH TOP SLAB TO BARREL SECTION JOINT-STORM STRUCTURE
152 PATCHINVERT-STORMSTRUCTt/RE
153 CONSTRUCTINVERT-STORMS7RUCTURE
154 ADDSTEP-STORMSTRUCTURE
155 REPAIRSTEP-STORMSTRUCTURE
156 ADD 1' SECTION, 6' DIASTORM STRUCTURE
APPROX.
�UANT. UNIT
5,46� CU YD
15 EACH
71,430 SO VO
135 HOUR
735 HOUR
13,fi00 TON
2,23(1 TON
56,020 SQ YD
17,760 LIN FT
8.12q LIN FT
19,930 S� YD
19,830 5a VD
it,240 GALLON
t 1,00� TON
2,950 TON
2,480 TON
920 TON
7,370 TON
3,370 TON
5,400 SQ YD
5,790 5a YD
18 LIN'rT
130 LIN Ff
730 LIN FT
t.125 LIN FT
2(1 LIN FT
18a LIN Ff
50 LIN FT
2 EACH
1 EACH
4 EACH
1 EP,CH
2 EACH
1 EACH
1 EACH
6 EACH
1 EACH
I EACH
1 EACH
1 LUMPSUM
6 EACH
2 EACH
73 EACH
2 EACH
1 EACH
45 EACH
187 EACH
10 CU YD
49 EACH
6 EACH
1 EACH
t EACH
it EACH
3 EACH
7 EACH
� � � a
Hardrives Inc. I Northwest Asphalt, Inc. I T.A. Schifsky 8 Sons, inc. I Bituminous Roadways, lnc.
$22,00
$3t2.80
$0.84
$0.01
5722.16
811.34
$76.56
$0.98
$3.00
$0.68
$0.87
$2.03
E2.2o
873.57
873.35
E63.38
863.43
861.81
$55.41
$10.00
514.92
322.84
$25,02
$26.95
541.65
567.77
$80.81
ss2.eo
$218.96
$819.49
$2,OBD.13
$2.007.13
$1,965.43
52,173.96
51,928.94
$2.91426
$3,154.07
$4.582.53
$8,810.56
$2,372.07
$474.42
$620.39
$193.18
81.329.41
81.485.80
8493.&?
$49277
$83.41
$730.33
5145.97
$130.33
$307.58
E156.40
$156.40
$406.64
�
�
$14.102.
F�
$27.00 $147
$350.00 $5
$0.55 $39
5100.00 $'13
$725.00 $ifi
811.30 $153
$13.40 529
so.ee sas
E3.75 566
si.�a ae
sa.�s sia
81.86 $37
$3.00 S33
$68.90 5735
$69.05 $203
E62.60 5155
sss.�a asa
$61.35 5452
$53.90 $'178
$13.75 $74
$20.65 5119
$3�A� 9
$28.19 $3
$2729 $19
$43.45 $48
$59.18 $1
$79.04 $74
aes.ea sa
$750.00 9
$fi90.00 9
81,350,00 $5
St�s�.00 gi
$2,539.00 $5
sz,7as.00 5z
at�sa.00 5i
az,�szoo sis
$3,186.00 $3
86,348,00 $6
58,079.00 $8
87,600.00 $t
$650.00 $3
$850.00 St
$200,00 $14
$7,432.00 $2
$1,670.00 $1
awo.00 szz
$500,00 $93
575.00 9
azao.00 ss
$200,00 $1
5400.00 9
5750.00 5
siio.00 E�
si�o.ao 1
ai,azo.00 si,
$70,05
$206.00
$1.03
$92.70
SsL85
812.36
$12.36
ai.aa
$2.58
$1.03
ai.00
51.00
a2.so
sszoo
$69.00
E84.00
s�i.00
asa.00
as�.00
$24.00
$19.80
$26.78
$27.87
$28.84
546.35
567.98
584,46
aioais
8278.10
si,oso.so
$1,369.90
81,sa8.aa
51.946.70
$1,767.30
ai,rjo.ao
az,eszso
83,13120
$6,567.10
$B,BOfi.50
$3,007.60
5824.00
51,493.50
$300.00
$2,763.00
$2,894.30
$48925
$489.25
5703.00
as2.�a
5216.30
$216.30
St,081,50
$97.85
$82,40
$2,008.50
Fi
$3,
821
871,01
S91 AE
$1,2<
821
$1.OE
87.07
525.45
$ I85.00
so.as
$135,00
8735.00
516.30
$18.35
si.zs
b3.45
87.10
s�.ao
$5,45
$3.00
s».sa
an.�a
$6520
ssa.ia
56520
sso.io
$31.35
525.50
523.15
$2525
$2720
542.00
$68.45
aeiso
$93.70
$T20.00
sezs.00
$2,t00.00
82,a25.0o
s�,ses.00
aznss.00
57,945.00
sz,sas.00
83,185,��
$4,625.00
$8,895A�
82,395A�
S480A�
$625.00
azos.00
$t,345.00
s�,soo.00
saso.00
$St�A�
585,00
aiao.00
5745.00
$130.00
$310.00
5760.00
5160,00
5410.00
$32,
$18.
$18,
5711.
$40.
s�a.
567,
$8,
sz�.
ame,
b33;
$786,
szia;
$i67,
sss;
$480,
Si65,
$169,
$147,
Fi!
PROIECT NO. N15.305420
omo: ana2oia
ITEM
NO. ITEM
'I57 A�01' SECTION, 4' DIASANITARY STRUCNRE
158 REPL4CE R3290 CURB BOX
159 REMOVE LOOSE GASKET IN 36" RCP STORM SEWER
160 8" PVC SANITARY SEWER, SDR 35
161 8" DIP SANITARYSEWER, CL.52
162 4' DIA SANITARY SEWER MH, INCL R-t642-B CSTG AND HDPEADJ RINGS
163 CONNECTTOEXISTINGSANITARYSEWERMANHOLE
t64 ADDS7EP-SANITARYMANHOLE
765 4' CIPP, 1T' RCP STORM SEVJER
766 4' CIPP, 75' RCP STORM SEVJER
767 4' CIPP, 18" RCP STORM SEWER
768 4' CIPP, 8" VCP SANITARY SEWER
169 LINE4'DIASTORMSTRUCTURE
170 LINEfi'DIASTORMS7RUCTURE
171 LINEB"VCPSANITARYSEVJER
172 SEAL 8" VCP JOINT
173 IRRIGATION SYSTEM REPAIR
174 ADJUSTVALVEBOX
175 REPLACE VALVE BOXTOP SECTION
176 VA�VEBOXEXTENSION
177 HYDRANTRISER
178 REMOVE AND REPLACE 6" GATE VALVE AND BOX
179 REMOVE AND REPtACE 17' BUTTERFLY VALVE AND BOX
t80 6" WATER MFUN OFFSET
781 8" WATER MAIN OFFSET
te2 EXCAVATION FOR INSULqTING EXISTING WATEft SERViCE (JEFFERY Cn
te3 4" INSULATION
784 8" X 4" PVC WYE, SDR 35
185 4" PVC SANITARY SEWER SERVICE, SCH 40, INCL REMOVAL OF EXISTING SERVICE
186 7" COPPER WATER SERVICE. TPE K INCL REMOVAL OF E%ISTING SERVICE
187 REMOVE AND REPLACE CURB STOP AND BOX
188 CONCRETEHVDRANTACCESSPAD
189 CONCRETE CURB AND GUTTER, DESI6N B4te
190 CONCRETE CURB AND GUTTER, DESIGN 0418 (HIGH EARLI�
191 5' CONCRETE DRAINAGE SLAB
192 6" CONCRETE DRIVEWAY PAVEMENT (RESIDENTIAL) (HIGH EARL1�
'193 T CONCRETE DRIVEWAYPAVEMENT (COMMERCIAL) (MIGH EARLY)
194 T' CONCRETE VALLEV GUTfER (HIGH EARLI�
195 TRUNCATEDDOMES
t96 PEDESTRL4N CURB RAMP
197 SALVAGEANDREINSTALLMAILBOXCLUSTER
198 TEMPORARY MAILBOX
199 HANDHOLE
200 FEED POINT
201 TNO NO 6AND NO 10 GROUND IN PLACE IN CONDUIT
202 TNO NO 4AND NO 10 GROUND IN PLACE IN CONDUIT
203 4" PVC CONDUIT FOR STREET LIGHT CROSSING
204 SIGN PANELS, TVPE C
205 TRASH RECEPTACLE AND CONCRETE PAD
206 BENCH AND CONCRETE PAD
207 SHELTERFOUNDATION
208 20k20'SHELTER
209 PICNIC TABLE
210 CONCRETE PLAYGROUND 80RDER
217 SILT FENCE, TYPE MACHINE SLICED
APPRO%.
QUANT. UNIT
1 E4CH
2 EACH
7 EACH
585 LIN FT
20 LIN FT
6 EACH
1 EACH
8 EACH
2 EACH
1 EACH
1 EACH
3 EACH
�6 LIN FT
34NFf
550 LIN FT
t EACH
6 EACH
78 EACH
5 EACH
12 LIN Ff
6 UN FT
t EACH
1 EACN
I EACH
1 EACH
2 EACH
730 SQ YD
5 EACH
75 LIN FT
200 LIN FT
5 EACH
1,950 S� FT
33,80� LIN FT
2,670 LIN FT
140 5a FT
800 SQ YD
175 S� YD
150 5� YD
328 SQ Ff
1,370 54 FT
7� EACH
121 EACH
703 EACH
8 EACH
16,570 LIN Ff
2,3'10 UN FT
820 LIN FT
456 SQ Ff
3 EACH
1 EACH
1 LUMPSUM
1 LUMPSUM
2 EACH
330 LIN Fl
200 LIN Ff
i
Hardrives Inc.
5380.57 $380.Si
8224.18 $4483E
588.62 $88.6:
822.68 $13.267.BC
$114.69 52,293.8C
$2,763.08 E16,578.4E
51,027.02 51,027A:
$67,77 $542.1E
$1,981.07 $3,962,t4
$2,293.87 $2,293,87
$2,293.87 $2.293.87
51.981.07 $5.94321
$364.93 $5,838.88
5745,St $2,236.5°
$38.06 520,933AC
81,t2�.86 $7,120.86
$156.40 $938.4C
8265.42 $20,702.7E
E203.32 $1,0'I6.6C
$761.61 51,939.32
$609.00 53,654AC
$2,068.69 82,069.69
$2,893.40 52,893.44
$2,658.81 $2,658.81
$3,075.88 $3,WS.BB
$7�3,80 $1,407.60
b46.92 86,099.60
5140,76 $703.80
ste.se ai,azssa
$22.42 b4,484.00
$2G5.88 $1,329.40
$4.69 $9,145.50
$9,23 $311,974.00
810.17 $27,153.90
$6.78 $94920
$46.92 $37,536,00
550.05 $5,755.75
aso.ae ss.on.aa
$3fi.49 811,968.72
54.07 55,575.90
$47.96 $3,35I.20
$15,64 $1,892.44
$521.34 553,698A2
$3,294.85 826,358.80
$7.03 $1t6,487.10
$7.25 516,747.W
$0.01 5820
531.28 St4263.68
$1.048.93 $3,146.79
57.445.15 $1.445.15
$10,391.14 510,391.14
520,8535� 520,853.50
$878.03 51,956.06
$76.88 $5,504.40
$4.53 5906.00
z � y
Northwest Asphalt, Inc. I TA. Schifsky & Sons, Inc. I Bituminous Roadways, lnc.
Shakooee. MN N. St. Paul. MN
51,250.00 S'1,2
$230A� 841
$250.00 82:
527.07 $15,8:
$78.76 $1,5
$2,310.00 $13,8!
aiaso.00 s�,r
5110.00 $8!
$1,900.00 83,8f
$2,200.00 $2,2f
82.200.00 $2.2(
St.900.00 $5.7(
8350A� $S,6f
$715.00 $2,1.
$36.50 $20,Oi
$'I,W5.00 $t,0i
$500.00 $3,0(
saoo.00 szs,ac
5375,�0 $1,8i
5450,�0 $5,4(
$575,�0 $3,OS
$2,390.00 � $2,3:
54,675.00 $4,6i
$7,800.00 $1,8(
sz,zoo,00 5z,zc
5aso.ao asc
$43.00 $S,SS
$327.00 51,G
azssz sz,zi
$29.19 $5,8£
8563.00 $2,81
55.75 $7121
59.95 $336,31
510.70 328,SE
ss.os s&
$50.30 540,2�
855,95 $6,4:
$58.75 $8,7.
$40,00 513,ii
$5.75 $7,0:
siao.ao s�,oc
$11.55 $1,3:
$310.00 531,9E
$3,850.00 $37,6C
$1�.60 $175,64
$11.6� 526,7E
$17.00 59,�
$30.00 $13,6E
$1,�00.00 83,3C
$7,510.00 $1,51
$6,882.00 $6,82
szz,aaa.00 azz.oc
$1.155.00 52.31
$28.35 $9.3°
$4.00 $BC
$1,390.50
$139A5
$566.50
$29.87
87725
E2.142.40
E2,5/5,00
an.zs
si,sn.ao
52266.00
$2,266.00
$1.957.00
$360.50
$736.45
$37.6�
81.107.25
5515.00
8262.65
$92.70
872.10
8530.45
$3,273.6�
anase.so
$3,6t5.3�
sa,azs.00
s�,asosa
536A5
5133.90
azs.�a
$28.84
$79825
55.05
5927
siosi
ss.is
$4223
547.74
$57.07
839.14
$5.05
s�z.ia
$10.7A
asis.00
$3,254.80
56.95
8721
so.ai
323.95
$82.40
$78025
$10,300.00
$30,900.00
$1,500.00
$22.66
$2.06
$1,390
$278
$566
517,473
$1.545
aiz,esa
$2.575
ssia
$3,914
$2,268
E2.266
85,871
$5,768
82,209
$20,680
51.707
$3,090
$20,486
$463
$865
$3,182
$3,213
sa.�se
$3,6t5
sa,azs
$2,781
�
S7
5385.00
azso.00
$90.00
$23.00
ai�s.ao
sz,�so.00
51,640.00
sse.as
$2,000.00
$2,315.00
$2,315.00
$2,000.00
$370.00
$750.00
$38A5
$7,130A�
$165.00
$230.00
5350.00
$765.00
$615.00
$2,090.00
sz.sza.00
$2,685.�0
$3,100.00
s�io.00
547.35
$140.00
siszo
522.65
$270.00
$4.75
$9.30
aio.zs
b6.85
547.35
$50.50
561.00
$36.85
54.t0
sss.00
512.fi5
ssas.ao
53,325.00
$7.70
57.30
so.oi
$37.6�
5900.0�
$1,085.00
ss,na.00
$24,300.00
ai,aso.00
$16.85
$5.50
�
521.
$1.
5
$17,
$1,
$t.
S3,
s�,
$S,6t7
�
52,
51,
$6,
PROJECT NO. N15.105420
omo; anerzma
ITEM
NO. ITEM
212 STORM DRAIN INLET PR07ECTION PER STANDARD DETAIL ER0�4B
213 STORM� DRAIN INLET PROTECTION PER STANDARD DEfAIL ER0�4C
214 STORM DRAIN INLET PROTECTION PER STANDARD DETAIL ER0�4D
215 WATERFORTURFESTABUSHMENT
216 HYDRAULIC SOIL STABILIZER NPE 5
277 SEEDING, INCL SEED MIX FERTIL2ER, AND HYDRAULIC SOIL STABILIZER
218 SEEDING, INCL NATIVE SEED MIX FERTIUZER, AND HYDRAULIC SOIL STABI�IZEf
2t9 SOD,MINERALNPE
220 PAVEMENT MESSAGE (RIGHTARR0IA� POLY PREFORM
221 PAVEMENTMESSAGE(LEFfARftOW)POLYPREFORM
722 PAVEMENT MESSAGE (THRU ARROW) POLY PREFORM
223 PAVEMENT MESSAGE (HANDICAPPED SVMBOL) POLY PREFORM
224 4"SOLIDLINEWHITE-EPDXY
225 4" DOUBLE SOLID LINE YELLOW -EPDXY
226 12" SOLID LINE WHITE - POLY PREFORM
227 12" SOLID UNE YELIOW - EPDXY (SPEED BUMP)
228 24"SOLIDLINEVJHITE-POLYPREFORM
729 DECIDUOUS SHRUB NO 1 CONT
230 3" CAL DECIDUOUS TREE B88
BASE BID:
TOTAL PART 1- INDIAN BOULEVARD
TOTAL PART 2- PROJECT AREAS Ct AND C2
TOTAL BASE BID
BID ALTERNATE #i - INDIAN BLVD COMMUNITY MAIIBOXES
APPROX.
�UANT. UNIT
42 EACH
42 EACH
4 EACH
1,060 M GALLON
2,00� POUND
26,600 S� VD
2,300 SQ YD
6,900 SO YO
2 EACH
4 EACH
t EACH
8 EACH
16,510 I.IN FT
5,800 LIN FT
22� LIN Ff
48 LIN FI
25 LIN FT
2 SHRUB
14 EACH
TOTAL PART 2- PROJECT AREAS C1 AND C2
1 6 CONCRETE MAILBOX PAD 378 S� FT
2 SALVAGEANDREINSTALLCOMMUNINANllL80X BEACH
TOTAL eID ALTERNATE #'I • INDUIN eLVD COMMUNITY MAILBOXES
BIO ALTERNATE #2 -C1/C2 AREAS COMMUNIN MAILBO%ES
7 5' CONCRETE MAILBOX PAD 2,934 SQ FT
2 SALVAGE AND REINSTALL COMMUNITY MAILBOX fi0 EACH
TOTAL BID ALTERNATE #2 -INDIAN BLVD COMMUNITY MAILBO%ES
BID ALTERNATE #3 - KINGSTON PAftK ELECTRICAL
1 ELECTR�CAL RUN t
2 ELECTRICAL RUN 2
3 ELECTRICAL RUN 3
4 ELECTRICAL RUN 4
5 ELECTRICAL RUN 5
6 ELECTRICAL RUN 6
7 ELECTRICAL RUN 7
e ELECTRICAL RUN e
9 ELECTRICAL RUN 9
10 HANDHOLES
it POWERPEDESTALS
12 SERVICECABINET
13 BOLLARDS
eID ALTERNATE iM • KWGSTON PARK ELECTRICAL
1 ELECTRICAL RUN t
2 ELECTRICAL RUN 2
25 LIN FT
70 LIN FT
76 LIN FT
7� LIN FT
80 LIN FT
20 LIN FT
62 LIN FT
7a LIN ( I
90 LIN F f
9 EACH
6 EACH
7 EACH
12 EACH
810 ALTERNATE #7 • KINGSTON PARK ELECTRICAL
25 LIN FT
70 LIN FT
i z a a
Hardrives Inc. Northwest Asphalt, Inc. T.A. Schitsky & Sons, Inc. Bituminous Roadways, Inc.
Ro ere, MN Shako ee, MN N. St. Paul, MN
'�E AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT UNIT PRICE AMOUNT
$69.86 $2,834.12 8150.00 $6,300,00 §703.00 $4,326.00 $130A� $5,460
569.86 $2,934.12 5150,00 $6,300.�0 $703.00 $4,326,00 $13�.00 $5,460
$99,05 $39620 $150.00 $600.00 5703.00 $412.00 $13�A� $520
$20.&5 522,1�1.00 $18,00 $19,080.00 $18.54 $79,652.40 $2525 $26,765
$1.�1 $2,020.00 $1.50 83,000,00 $1.55 83,100.00 $0.95 $7,900
$1.72 $32,45200 $7.00 $26,600.00 $0.95 $25,270.00 $1.45 $38,570
$1.71 $2,806,00 $125 $2,875.00 $129 $2,967.00 $2.20 $S,OfiO
$3.44 $23,736.00 $3.25 $22,425.00 $3.35 S23,it5,00 $5.00 $34,500
$333.66 $667.32 $336.00 $fi72.00 $824A� $t,648.00 5845.00 $t,690
$333.66 81,334,64 $336.00 57,344A0 $824.0� $3,296.00 5845.00 $3,380
$265.88 $265.88 $267,75 $267.75 $824.00 $824A� $845.00 $845
$406.64 $3,253.'12 $4t0.00 $3,280.00 $309.00 $2,472.00 $315.00 52,520
$0.31 $5,118.10 $0.32 $5,28320 $0.31 $5,118.10 $0.32 $5,283
$0.65 $3,T7�.00 $0.65 $3,770.00 $0.64 $3,772.00 $0.65 53,770
b11.47 52,523.40 817.55 $2,541.00 575,04 $3,308.80 $15.35 53,377
810.43 $500.64 St0.50 $504.00 $10,30 $494.40 $10.50 $504
$22.94 $573.50 523,70 $577.50 $27.30 $682.50 $28.00 s�ao
St5,64 $3t28 550,00 $100.00 51�3,�0 $206.00 $100.00 $200
SSt0.97 $7,752.74 $450.00 $6.300.00 $360.50 55,047.00 $665.00 $9,3'ID
54,465,565.60 E6,586,390.05 §4,829,692.16 � $4,964.903
$254.17 $2, 33.36I $700.00 $ $800.00I $'103.00 $1 $824.00I E550.00
$4.69 $'13,760.46 $7.10 $20,831.40 $4.89 $14,347.26 55.00 $14,f
$254.17 $15,2502(1 $10�.00 $6,000.00 $703.00 $6,180.�0 5550.00 $33,(
529,010.66 526,8J7.40 520�527.26 $47,E
53126 $781.50 $35.80 $895A� $30.90 $77250 $31.45 $i
823.44 $1,640.80 52620 $1,834A� $23.18 $7,622.60 $23,65 51,E
$824 $70224 520.00 $7,520A� 59.17 $696.92 $9.30 $i
$9.30 $651.00 $20.50 $7,435.00 $9.19 $643.30 $9.40 SE
$923 $738.40 $18,60 57,488.00 S9.t7 $733.60 $9.30 $i
$10.56 $27120 $27.80 $55fi.0� $10.43 $208.60 $70.65 $:
$7.83 $485.46 $20.00 57,240.00 87.74 $479.88 $7.90 $t
$7.83 $548,7a $18.90 5�,323.00 $7.74 $547.80 $7.90 5:
$7.02 $637.80 $i6B� $1,494.00 $6.95 $625.50 $7.10 $E
$458.78 $4,129,02 5245.00 $2,205.00 $4532� $4,W8.80 $465.00 $4,1
8479.63 $2,877.78 $530.00 53,180,00 $473.8� 52,842.80 $485.00 82,:
$4,566.92 $4,556.92 $3,94�.00 $3,940.00 $4,532A� 84,532,00 $4,6'10.00 84,E
SS73.47 ... $6,881.64 $535.00 56,420.00 $551,05 ffi6,612.60 5580,00 $6,£
576.72 81,903.00 $9320
$33.37 $2,335.90 547.7�
S?A,S90.90 $25,770
875.19 $7,879.75 $76.85 b7,921
b32,96 $2,30720 $33.70 $2,355
PROJECT N0. N15.105420
Oalo: 4I18201�
ITEM
NO.
3 ELECTRICAL RUN 3
4 ELECTRICAL RUN 4
5 ELECTRICAL RUN 5
6 ELECTRICAL RUN 6
7 ELECTRICAL RUN 7
8 ELECTRICAL RUN 8
9 ELECTRICAL RUN 9
70 HANDHOLES
71 POWER PEDESTALS
72 SERVICE CABINET
73 BOLLAROS
SUMMARY:
ITEM
BID ALTERNATE 714 - KINGSTON PARK ELECTRICAL
TOTAL BASE BID
TOTAL BID ALTERNATE #1 -INDIAN BLVO COMMUNIN MAILBO%ES
TOTAL BID ALTERNATE #2 -INDIAN BLVD COMMUNITY MAILBOXES
BIO ALTERNATE W-KINGSTON PARK ELECTRICAI
BID ALTERNATE #4 - KINGSTON PARK ELECTRICAL
APPRO%.
QUANT. UNIT
7fi LIN Ff
70 LIN FT
80 LIN FT
20 LIN FT
62 LIN FT
70 LIN FT
90 �IN FT
9 FACH
6 EACH
1 EACH
t2 EACH
i
Hardrives Inc.
Rogers, MN
IGE AMOUNT
$20.03 $t,SL
517.31 81,211
$14.37 E1.14:
537.11 $74:
$18.42 87,14'<
$13.68 §957
813.34 $1,20C
$6t5.t8 55,53E
$620.38 $3,7Y.
$6,788.85 $6,78E
z
Northwest Asphalt, Inc.
$34.00
529.30
$20.40
$53.65
$33.00
azs.so
$18.40
5375.00
ai,eos.00
$6,300,00
a
TA. Schifsky & Sons, Inc.
N. St. Paul, MN
'PRICE AMOUNT
$20.60 $1,5E
517.70 $1,1f
574.19 81,tF
$36.67 $7:
81823 $1.1E
573.52 $94
$13.18 $1,tE
$618.00 $S,5E
8618.00 $3,7C
$6,706.33 $6,7C
4
Bi[uminous Roadways, Inc.
'PRICE AMOUNT
szo.zs
817.45
aia.so
$37.45
siaso
$13.80
$13.45
$620.00
$625.00
$6,855.00
$580.00
RESOLUTION NO. 2013-XXX
RESOLUTION AWARDING THE BID FOR THE 2013 PAVEMENT MANAGEMENT
UTILITY AND STREET IMPROVEMENTS TO HARDRIVES, INC.
IN THE AMOUNT OF $5,343,526.27
WHEREAS, plans and specifications for the 2013 Pavement Management Project Utility
and Street Improvements were completed according to City standards; and
WHEREAS, bids were requested to provide the necessary work; and
WHEREAS, there were four alternatives as part of the bid package for the project.
Alternative #1 was for replacement of the concrete pads under the community mail boxes along
Indian Boulevard. Alternative #2 was for replacement of the concrete pads for the community
mail boxes in areas C1 and C2. Alternative #3 was for six electrical pedestals (120 V
receptacles and 2-120 Volt receptacles) at Kingston Park for the Strawberry Festival. Alternative
#4 was for six electrical pedestals (1-120 Volt, 1-50 Amp, 1-30 Amp receptacles) at Kingston
Park for the Strawberry Festival; and
WHEREAS, it was determined that the replacement of the concrete pads for mail
boxes would provide a safer situation and improve the aesthetics of the neighborhood and
should be included as part of the project. The cost of Alternative #1 and #2 is $32,816.84; and
WHEREAS, after review of the actual costs for different electrical pedestal options for the
Strawberry Festival it was determined that the costs for Alternatives #3 and #4 are above the
estimated feasibility value; and
WHEREAS, four firms submitted bids; and
WHEREAS, it appears that Hardrives, Inc. is the lowest responsible bid; and
WHEREAS, it is the recommendation of the City Engineer that the bid be awarded to
Hardrives, Inc. in the amount of $5,343,526.27, which includes Alternatives #1 and #2.
NOW THEREFORE BE IT RESOLVED, the City Council of the City of Cottage Grove,
County of Washington, State of Minnesota, the bid for the 2013 Pavement Management Project
Utility and Street Improvements Project is awarded to Hardrives, Inc. in the amount of
$5,343,526.27.
Passed this 1 st day of May 2013.
Myron Bailey, Mayor
Attest:
Caron M. Stransky, City Clerk