1. Consider approving Change Order No. 1, which provides for temporary lighting on 80th
Street during the project duration for safety purposes.
2. Consider approving final payment in the amount of $95,976.20 to Eureka Construction, Inc.
for the Pond ED-P5 Water Quality Improvements/80th Street Box Culvert project.
� � :_ •►I►I_ ►�� •►
1. Approve Change Order No. 1.
2. Adopt the resolution approving the final payment of $95,976.20 to Eureka Construction, Inc.
for the Pond ED-P5 Water Quality Improvements/80th Street Box Culvert project.
BUDGET IMPLICATION $1,147,518.70 $1,155,292.97
BUDGETED AMOUNT ACTUAL AMOUNT
SUPPORTING DOCUMENTS:
S1NWD/Storm
Water Area Fund
FUNDING SOURCE
� MEMO/LETTER: Letter from Dave Sanocki, Stantec., dated 4/30/14
� RESOLUTION: Draft
❑ ORDINANCE:
❑ ENGINEERING RECOMMENDATION:
❑ LEGAL RECOMMENDATION:
� OTHER: Change Order No. 1
ADMINISTRATOR'S COMMENTS
S�
� I�
City Administrator Date
*�*******�*******************��*�*��*******�***�
COUNCIL ACTION TAKEN: ❑ APPROVED ❑ DENIED ❑ OTHER
RESOLUTION NO. 2014-XXX
RESOLUTION APPROVING FINAL PAYMENT IN THE AMOUNT OF
$95,976.20 TO EUREKA CONSTRUCTION, INC. FOR THE POND ED-P5
WATER QUALITY IMPROVEMENTS/80TH STREET BOX CULVERT PROJECT
WHEREAS, the City Engineer has certified that work has been satisfactorily
completed; and
WHEREAS, the original total contract amountwas $1,147,518.70. There was
one change order for this project in the amount of $7,774.27, which revised the
contract amount to $1,155,292.97. The actual contract amount completed was
$1,184,307.98; and
WHEREAS, the project has been satisfactorily completed in accordance with
the contract plans and specifications.
NOW THEREFORE BE IT RESOLVED, the City Council of the City of
Cottage Grove, County of Washington, State of Minnesota, that $95,976.20 is paid
to Eureka Construction, Inc. for the final payment of the Pond ED-P5 Water Quality
Improvements/80th Street Box Culvert Project.
Passed this 7th day of May 2014.
Myron Bailey, Mayor
Attest:
Caron M. Stransky, City Clerk
Stantec Consulting Services Inc.
2335 Highway 36 West
St. Paul MN 55113
Tel: (651) 636-4600
Fax: (651) 636-1311
April 30, 2014
Jennifer Levitt, PE
City Engineer/Community Development Director
12800 Ravine Parkway South
Cottage Grove, Minnesota 55016
Re: Pond ED-P5 Water Quality Improvements
City of Cottage Grove
Stantec Project No. 193802264
Dear Jennifer,
Enclosed please find four (4) copies of change order No. 1 and the 7 and Final Request
for Payment for the Pond ED-P5 Water Quality Improvements Project. The Contractor for
this project is Eureka Construction, Inc. In addition to the Request for Payment, the
Contractor has submitted their IC-134 forms.
PROJECT REVIEW
This project began in September, 2012 and was substantially completed in September,
2013. Final punch list items were completed in November, 2013.
CONSTRUCTION COST OVERVIEW
The Original Contract amount for this project was $1,147,518.70. There was one change
order for this project in the amount of $7,774.27 which revised the contract amount for
this project to $1,155,292.97. The change order was to provide temporary lighting to 80tn
Street for the project duration.
The Final Construction amount is $1,184,307.98. The Final Construction amount for this
project was $29,015.01 over the Revised Contract amount. The total over run was due
primarily to the increased bituminous trail section, street patch area, length of 2" electrical
conduit placed and restoration around the ponding area.
RECOMMENDATION
The Contractor, Eureka Construction, Inc. has satisfactorily completed the Work in
accordance with the contract plans and specifications. Therefore, it is recommended that
final payment of $95.976.20 be made to the Contractor and the project be accepted by
the City of Cottage Grove.
�eslq� �r�lh ca?�r�uni}y �ra rr�inc3
April 30, 2014
Page 2 of 2
After acceptance, please distribute all copies of the Request for Payment as appropriate.
If you have any questions about this project or require further information please contact
me 651-604-4905.
Regards,
STANTEC CONSULTING SERVICES INC.
�
tr
Dave Sanocki
Senior Project Manager
Enclosures
copy: Craig Larson
File
€�es[�n with vorr�rrtuni�y ir? rr�er�c3
" �.;• '� 4f ..,.u� .. g�
Owner: City of Cottage Grove, 12800 Ravine Pkwy. S., Cottage Grove, M Date arch 14
� stantec Contractor:Eureka Construction, Inc., 8500 210th St. W„ # 130, Lakeville, MN 55044
Bond Co: Travelers Cas. & Surety Co, of America, One Tower Square, Harfford, CT 06183 Bond No: 105798605
CHANGE ORDER NO. 1
80TH STREET BOX CULVERT
CLIEN7 PROJECT NO. 12-2010-Q1
STANTEC FILE NO. 193802264
Description af Work
This Change Order provides for temporary lighting on 80th Street during the praject duration.
Contract Unit 7otal
No. Item Unit Quantity Price Amount
CHANGE ORDER NO. 1
1 TEMPORARY LIGHTING ON 80TH STREET LS 1 $7,742.27 $7,774.27
TOTAL CHANGE ORDER NO. 1: $7,774.27
193802264CHOI.xism
Original Contract Amount
Previous Change Orders
This Change Order .
Revised Contract Amount (including this change order)
CHANGE IN CONTRAC7' i'IMES
Original Contract Times:
Substantial Completion (days or date):
Ready for final Payment (days or date):
increase of this Change Order:
Substantial Completion (days or date):
Ready far final Payment (days or date):
Contract Time with all approved Change Orders:
Substantial Completion (days or date):
Ready for final Payment (days or date):
Recommended for Approval by:
STAtdTEC
�
/
f��
Cru;� W La�'so�.
Appr ed by Contractor:
EUREKA CONSTRUGTION, INC.
,
����- t�
Date
cc: Owner
Contractor
Bonding Company
Stantec
$1,147, 518.70
$0.00
$7,774.27
$1,155,292.97
Date:
Zg /
Approved by Owner:
CITY OF CO'RAGE GROVE
Date:
t 93802264CH0I.xlsm