HomeMy WebLinkAbout2014-07-16 PACKET 04.B. REQUEST OF CITY COUNCIL ACTION COUNCIL AGENDA
MEETING ITEM # �
DATE 7/16/14 •
.
PREPARED BY: Community Development Jennifer Levitt
ORIGINATING DEPARTMENT STAFF AUTHOR
:�*�***�*�*************:�:�:�*******�*****�****��***
COUNCIL ACTION REQUEST
Consider approving final payment in the amount of $11,581.73 to Minnesota Dirtworks, Inc. for
the Woodridge Park Pond Improvements project.
STAFF RECOMMENDATION
Adopt the resolution approving the final payment of $11,581.73 to Minnesota Dirtworks, Inc. for
the Woodridge Park Pond Improvements project.
BUDGET IMPLICATION: $111,578.95 $120,483.89 Stormwater Utility
BUDGETED AMOUNT ACTUAL AMOUNT FUNDING SOURCE
SUPPORTING DOCUMENTS
� MEMO/LETTER: Letter from Dave Sanocki, Stantec., dated 6/17/14
� RESOLUTION: Draft
❑ ORDINANCE:
❑ ENGINEERING RECOMMENDATION:
❑ LEGAL RECOMMENDATION:
❑ OTHER:
ADMINISTRATOR'S COMMENTS
c� 1
City Administrator Date
****:�***�**�**�*�******��***************�**�:****
COUNCIL ACTION TAKEN: ❑ APPROVED ❑ DENIED ❑ OTHER
RESOLUTION NO. 2014-XXX
RESOLUTION APPROVING FINAL PAYMENT IN THE AMOUNT
OF $11,581.73 TO MINNESOTA DIRTWORKS, INC. FOR THE
WOODRIDGE PARK POND IMPROVEMENTS PROJECT
WHEREAS, the City Engineer has certified that work has been satisfactorily
completed; and
WHEREAS, the original total contracfi amount was $111,578.95. The final
construction amount is $120,489.89, which is $8,904.94 over the original contract
amount. The total overrun was due to the sidewalk improvements that occurred at
the intersection of the park entrance and 90th Street. The actual amount of the
. completed project was $120,483.89; and
WHEREAS, the project has been satisfactorily completed in accordance with
the contract plans and specifications.
NOW THEREFORE BE IT RESOLVED, the City Council of the City of .
Cottage Grove, County of Washington, State of Minnesota, that $11,581.73 is paid
to Minnesota Dirtworks, Inc. for the final payment of the Woodridge Park Pond
Improvements Project.
Passed this 16th day of July 2014.
Myron Bailey, Mayor
Attest:
Caron M. Stransky, City Clerk
Stantec Consulting Services Inc.
' 2335 Highway 36 West
St. Paul MN 55113
Tel:(651) 636-4600
Fax:(651)636-1311
June i�, 2014
Jennifer Levitt, PE
City Engineer/Community Development Director
i2800 Ravine Parkway South
Cottage Grove, Minnesota 55oi6
Re: Woodridge Park Pond Improvements
City of Cottage Grove
Stantec Project No. i938o1476
Dear Jennifer,
Enclosed please find three (3) copies of the 2nd and Final Request for Payment for the Woodridge Park
Pond Improvements Project. The Contractor for this project is Minnesota Dirt Works, Inc. In addition to
the Request for Payment, the Contractor has submitted their IC-134 forms.
PROJECT REVIEW
This project began in August, 2012 and was substantially completed in September, 2oi2. Final punch list
items were completed in October, 2oi3.
CONSTRUCTION COST OVERVIEW
The Original Contract amount for this project was $1i1,578.95. The Final Construction Amount is
$i The Final Construction amount for this project was $8,904•94 over the Original Contract
Amount. The total over run was due to the sidewallc improvements that occurred at the intersection of the
park entrance and 90� Street. The original plan was to improve one concrete pedestrian ramp at the
northwest corner of the park entrance and 90� Street. A second concrete pedestrian ramp, located at the
northeast corner of the parlc entrance and 90� Street, was deteriorating and in need of repair and was
reconstructed as part of this project.
RECOMMENDATION
The Contractor, Minnesota Dirt Works, Inc. has satisfactorily completed the Work in accordance with the
contract plans and specifications. Therefore, it is recommended that final payment of $i1,58�.73 be made to
the Contractor and the project be accepted by the City of Cottage Grove.
After acceptance please distribute all copies of the Request for Payment as appropriate. If you have any
questions about this project or require further information please contact me 6 51 - 604 - 4905•
Regards,
STANTEC ONSULTING SERVICES INC.
�
��
Dave Sanocki
Senior Project Manager
Enclosures
Design with community in mind
�
A
d.
� Owner: Ci of Cotta e Grove 7516 80th St. S. Cotta e Grove MN 55016 Date: A ril 21 2014
For Period: 9/8/2012 to 4/21/2014 Re uest No 2/FINAL
Stantec Contractor: Minnesota Dirt Works Inc. 2500 W. Coun Rd 42, Suite 105, Burnsville, Mn 55337
CONTRACTOR'S REQUEST FOR PAYMENT
WOODRIDGE PARK POND IMPROVEMENTS PROJECT
STANTEC PROJECT N0.193801476
SUMMARY
1 Original Contract Amount $ 111,578.95
2 Change Order - Addition $ 0.00
3 Change Order - Deduction $ 0.00
4 Revised Contract Amount $ 111,578.95
5 Value Completed to Date $ 120,483.89
6 Material on Hand $ 0,00
7 Amount Earned $ 120,483.89
8 Less Retainage 0% $ 0.00
9 Subtotal $ 120,483.89
10 Less Amount Paid Previously $ 108,902.16
li Liquidated damages - $ 0.00
12 AMOUNT DUE THIS REQUEST FOR PAYMENT N0. 2/FINAL $ 11,581.73
Recommended for Approval by: Approved by Owner:
STANTEC CITY OF COTTAGE GROVE
�
G vt,. ;� uJ (�.v's eh.
ov by Contractor:
MINNESOTA DIRT WORKS, INC. Date:
�� �����
�� �
Recommended for Approval
CITY OF COTTAGE GROVE
�°YV�l..Y��.a�^
Ci Engineer
Specified Contract Completion Date:
Date:
� �f�'1'�
193801476REQ2FINAL.xism
Contract Unit Current Quantity Amount
No. Item Unit Quantity Price Quantity to Date to Date
BASE BID:
1 MOBILIZATION LUMP SUM 1 $8,000.00 1 $8,000.00
2 CLEARING AND GRUBBING LUMP SUM 1 $3,000.00 1 $3,000.00
3 REMOVE PIPE CULVERT LIN Ff 14 $12.30 14 $172.20
4 REMOVE PIPE APRON EACH 1 $86.20 1 $86.20
5 COMMON EXCAVATION CU YD 6423 $3.55 6423 $22,801.65
6 CLAY LINER (LV) CU YD 1339 $22.60 1339 $30,261.40
7 24" RC PIPE SEWER DESIGN 3006 CLASS III LIN FT 66 $42.15 63 $2,655.45
8 24" RC PIPE APRON EACH 1 $690,00 1 $690.00
9 CONNECT INTO EXISTING CATCH BASIN EACH 1 $725.00 1 $725,00
10 RANDOM RIPRAP CLASS III CU YD 30 $46.80 30 $1,404.00
li SEEDING, MnDOT MIX 310 SQ YD 1982 $1.50 449.34 1949.34 $2,924.01
12 SEEDING, MnDOT MIX 350 SQ YD 2719 $1.45 777.22 2777.22 $4,026.97
13 MOWING AC 6 $100.00 1.6 1.6 $160.00
14 EROSION CONTROL BLANKETS CATEGORY 3 SQ YD 4671 $1.00 726.56 4726.56 $4,726.56
15 SILT FENCE, TYPE MACHINE SLICED LIN FT 345 $2,50 344 $860.00
16 TEMPORARY ROCK CONSTRUCTION ENTRANCE EACH 1 $700.00 1 $700.00
17 STREET SWEEPER (WITH PICKUP BROOM) HOUR 3 $130.00 $0.00
18 BUR OAK EACH 7 $450.00 7 $3,150.00
19 SWAMP WHITE OAK EACH 7 $450,00 7 $3,150.00
20 RIVER BIRCH EACH 5 $430.00 5 $2,150.00
21 WINTERBERRY EACH 11 $65.00 11 $715.00
22 RED TWIG DOGWOOD EACH 11 $65.00 11 $715.00
TOTAL BASE BID: $93,073.44
ALTERNATE NO. 1
23 IYPE SP 12.5 WEARING COURSE MIXTURE (2,B) TON 85 $85.85 91.24 $7,832.95
24 AGGREGATE BASE (LV) CLASS 5 TON 260 $25.00 262 $6,550.00
25 GEOTEXTILE FABRIC 7YPE V SQ YD 673 $1.10 650 $715.00
26 6" CONCRETE WALK SQ Ff 100 $15.00 115 618.5 $9,277.50
27 TRUNCATED DOMES SQ FT 20 $50.00 24 48 $2,400.00
28 SILT FENCE, 7YPE MACHINE SLICED LIN FI" 240 $2.50 95 254 $635.00
TOTAL ALTERNATE N0. 1 $27,410.45
TOTAL BASE BID: $93,073.44
TOTAL ALTERNATE N0. 1 $27,410.45
TOTAL WORK COMPLETED TO DATE $120,483.89
793801476RE42FI NAL.xism
PROJECT PAYMENT STATUS
OWNER CITY OF COlTAGE GROVE
STANTEC PROJECT N0. 193801476
CONTRACTOR MINNESOTA DIRT WORKS, INC.
CHANGE ORDERS
No. Date Descri tion Amount
Total Chan e Orders
PAYMENT SUMMARY
No. From To Pa ment Retaina e Com leted
1 08/24/2012 09/07/12 108,902.16 5,731.69 114,633.85
2/FINAL 09/08/2012 04/21/14 11,581.73 120,483.89
Material on Hand
Total Pa ment to Date $120,483.89 Ori inal Contract $111,578.95
Retaina e Pa No. 2/FINAL Chan e Orders
Total Amount Earned $120,483.89 Revised Contract $111,578.95
193801476REQ2FINAL.xlsm