HomeMy WebLinkAbout2015-05-18 PACKET 06.2.STAFF REPORT CASE: SPI 5-018 & V15-019
ITEM: 6.2
PUBLIC MEETING DATE: 5/18/15 TENTATIVE COUNCIL REVIEW DATE: 6/3/15
APPLICATION
APPLICANT: Up North Plastics, Inc.
REQUEST: A site plan review of a proposed 240 -foot by 361 -foot (86,640 square foot)
warehouse addition on the west end of Up North Plastics' existing facility
and a variance to allow loading docks on the south elevation facing 95th
Street South.
SITE DATA
LOCATION:
ZONING:
GUIDED LAND USE:
9480 Jamaica Avenue South
1-2, General Industry
Industrial
LAND USE OF ADJACENT PROPERTIES: CURRENT
NORTH: Commercial/RR
EAST: Industrial
SOUTH: Industrial
WEST: Industrial
SIZE: Addition = 86,640 square feet
DENSITY: NIA
RECOMMENDATION
GUIDED
Commercial/RR
Industrial
Industrial
Industrial
Approval, based on the findings of fact and subject to the conditions
stipulated in this staff report.
Collage COTTAGE GROVE PLANNING DIVISION
J Grove
+ere Pride an04ozPeiltY Meet
Planning Staff Contact: John McCool, Senior Planner; 651-458-2874; 0mccool(�cottage-grove. orq
Application Accepted:, 4/21/15 60 -Day Review Deadline: 6/20/15
City of Cottage Grove Planning Division • 12800 Ravine Parkway South 9 Cottage Grove, MN 55016
Planning Staff Report
Up North Plastics Expansion Project
Site Plan Review and Variance Applications
Planning Case No. SP2015-018 and V2015-019
May 18, 2015
Proposal
Up North Plastics has applied for the following planning applications:
Site plan review approval for their proposed construction of a 240 -foot by 361 -foot (86,640
square feet) warehouse and light industrial use.
2. Variance to Title 11, Chapter 11, Section 5(B)(2), Performance Standards, regarding the ordi-
nance requirement that loading docks shall not be permitted along the side of a building which
faces a public street.
Up North Plastics is proposing to construct an 86,640 square foot building addition on the west
side of their existing principal building located at 9480 Jamaica Avenue South. The proposed
project includes concrete paving on the south, west, and north sides of the proposed warehouse
expansion. The paved expansion area on the south side of the new addition will include three
loading docks and two truck doorway openings on the west side of the new building addition. The
area north of the proposed building addition and on the west and north sides of the existing 80 -
foot by 150 -foot maintenance building will also be paved for the ongoing outdoor storage and
parking for semi -trailers.
A location map for the Up North Plastics site and proposed warehouse addition is shown below:
Location Map
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 2 of 10
Review Process
Application Received: April 21, 2015
Acceptance of Completed Application: April 21, 2015
Tentative City Council Date: June 3, 2015
60 -Day Review Deadline: June 20, 2015
Planning Considerations
Ordinance Criteria
Up North Plastic's 88 -acre site is zoned 1-2, General Industry District. This zoning classification is
consistent with the industrial land use designation shown on the Future Land Use Map of the
City's Future Vision 2030 Comprehensive Plan, adopted on March 2, 2011. The proposed ware-
house and light industrial uses operating within these structures and on the property are permitted
uses in the 1-2 District.
The City's Zoning Ordinance requires site plan approval for new structures and major additions
to existing structures. The purpose of the site plan review is to ensure that new development
conforms to the City's development standards and ordinance regulations. Plastics manufacturing
and fabrication is a conditional use in the 1-2 zone. The ordinance lists 12 performance standards
that must be met in order to grant the permit. All minimum building setbacks and maximum
building height regulations are met for this proposed expansion. Exterior building materials pro-
posed for this warehouse expansion will be consistent with the exterior materials, color, and
texture of the existing manufacturing facility. Staff believes that the proposed addition, consistent
with the previous approvals, meets all ordinance regulations.
Along with the various site plan regulations associated with the building expansion, a variance is
required. The variance is to allow the docks to be located on the south side of the building. City
Code Title 11-11-5 specifically states loading docks "shall not be permitted on the side of a build-
ing facing a public street." Presently the dock facilities for the existing manufacturing facility are
on the south side of the building. Because of the angle of 95th Street compared to the south face
of the existing Up North Plastics' building, the three new docks on the south side of the proposed
building expansion project will be closer to the road. The southwest corner of the addition will be
approximately 293 feet from 95th Street, with the current condition being approximately 360 feet.
These building setbacks from 95th Street are some distance from the street and the existing berm
and landscaping along 95th Street helps mitigate on-site views.
The main reason the new docks are proposed on the south side of the proposed building addition
is because of the existing docks on the existing building. The internal operations of the plant have
been devised to work with the present building layout. The new addition is an extension of the
current processing and warehousing systems. For example, it would not be efficient for the exist-
ing docks to remain on the south and the new docks constructed on the west or north side of the
new addition. From a site design perspective, the site circulation has already been established
with the docks on the south side of the building. While typically it is not desirable to have the docks
on the public frontage, the existing conditions really dictate the functionality of the addition. The
existing landscaping and earth -berms aid in mitigating dock views.
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 3 of 10
Background
The original building was built by Whirlpool in 1965 and was used for the manufacturing and
assembly of home appliances. Whirlpool vacated the property in the early 1980's.
In 1985, Up North Plastics bought the property and the City granted a height variance to allow
construction of two 100 -foot towers, one 60 -foot tower, and six 60 -foot storage silos. A conditional
use permit was also approved. In 1990, Up North Plastics received approval to amend their con-
ditional use permit and a revised variance request to permit twelve 85 -foot storage silos. The two
existing 60 -foot silos were removed from the site.
In 1996, Up North Plastics received approval to amend their conditional use permit and another
variance to permit construction of 12 more storage silos and 8 blending tanks. In 1998, Up North
Plastics received administrative approval to relocate a portion of their existing parking lot. The
new parking lot construction and old lot removal was completed in the spring of 1999.
In September 1999, the City Council approved a conditional use permit and site plan review for
expansion of the operation by constructing a 320 -foot by 410 -foot concrete storage pad for the
long-term storage of semi -trailers. The approval for the additional storage area was predicated on
prohibiting any long-term storage in the south and southeast parking lots and within the dock area.
The applicant was also required to install earth berms and landscaping to aid in screening the
trailer storage areas.
Site Characteristics
The entire site is approximately 88 acres and is located at the northwest corner of 95th Street and
Jamaica Avenue. The total gross floor area of their existing manufacturing, warehouse and office
facility is approximately 381,540 sq. ft. Up North Plastics also has an existing accessory building
that is located northwest of their existing principal structure. This structure is 80 feet by 150 feet
and is used to store their maintenance and operating equipment.
Three access drives exist on 95th Street on one access drive exists on Ideal Avenue. Public
access onto the property is restricted. Employee and visitor parking are located southeast of the
main manufacturing facility. The rest of the paved areas are dedicated to truck maneuvering,
parking, and outside storage along the south, west, and north sides of the existing building. The
large green space areas along Jamaica Avenue and 95th Street are routinely managed.
Landscaping and earth -berms exist along 95th Street and were installed in the 1999-2000
timeframe. The existing landscaping is consistent with the requirements of the City's approval in
1999.
There is an existing seven -foot tall chain-link fence along the south and west property boundary
lines. Up North Plastics is proposing to relocate a segment of the existing chain-link fence that is
north of the access drive connecting to Ideal Avenue. The purpose of moving this segment of
fence toward Ideal Avenue is because it will be in the way of their proposed paved outdoor storage
area.
Up North Plastics' stormwater basin exists in the southwest corner of their site. A photo of this
stormwater basin is shown below.
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 4 of 10
Below is an aerial photo showing Up North Plastic's current site:
Up North Plastics — 9480 Jamaica Avenue — 2013 Aerial Photo
Up North Plastics accepts industrial grade low density polyethylene (LDPE) and linear low density
polyethylene (LLDPE) plastics as well as plastic film. These materials are required to be dry and
free of contaminants. This is the primary reason why there are numerous semi -trailers on the site.
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 5 of 10
Landscaping
The overall lawn maintenance and existing landscaping on the property was found to be generally
in good condition. The construction of the proposed warehouse and outdoor storage will not
require any landscaping to be removed. The existing landscaping is consistent with the require-
ments of the City's approval in 1999.
Parking
The existing number of visitor and employee on-site parking spaces exceeds the City's minimum
ordinance regulations for this office and manufacturing use. Constructing the proposed ware-
house addition will not eliminate any off-street parking.
Minimum parking standards and parking setbacks are compliant with zoning regulations. The
parking space markings in the existing parking lot need a new coat of paint.
Architecture
The proposed 86,640 square foot addition will have the same uniform rib metal panel with a masonry
brick fagade on all three sides. The first eight feet of the building elevation will be brick with the
remaining portion of the fagade being the insulated metal panels. The building addition height (ap-
proximately 31 feet) is the same building height for the existing building. An illustration of the masonry
brick and insulated metal panels are shown below.
By ordinance, the City would typically not support use of metal panels over such an extensive wall
area. The ordinance permits the use of metal for accenting only. However, given the design and
materials of the existing structure, staff supports the current proposal to promote consistency
between the proposed building addition and existing building.
Three truck loading docks are proposed to be installed on the south side of the new addition and two
16 -foot by 16 -foot overhead doors will be installed on the west side of the new addition.
A photograph of the west side of their existing building is shown below:
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 6 of 10
Up North Plastics — West Elevation
The proposed building addition will be the same height as the existing building and the exterior build-
ing materials will be the same textures and colors. Building elevations for the proposed addition are
shown below and attached to this report.
�, xoanrtievenox
Building Elevations
Utilities
Up North Plastic's property is within the Metropolitan Urban Service Area (MUSA). City sanitary
sewer and water services exist from 95th Street. All city utilities in this vicinity provide the neces-
sary capacities to serve this existing and proposed industrial project.
The proposed building expansion will require a portion of Up North's stormwater and water sys-
tems to be relocated around the new addition. Additional fire hydrants will be installed. The prop-
erty owner is required to permit city access to the water system to flush water through the system.
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 7 of 10
The property owner is responsible for maintaining their private watermains, hydrants, and fire
suppression systems.
The applicant must submit their utility and grading plan to the City Engineer, Public Safety De-
partment, Public Works Department, and Building Official for review and approval. The fire hydrant
placement on the site shall comply with the Fire Marshal's requirements. Once these plans have
been approved by the City, a building permit will then be issued by the City.
La ��
r t +t 1
M+mrf i �
� I
-�tllnng anUBny "Pl'
Demolition Plan
Plan
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 8 of 10
Stormwater Management Plan
A stormwater basin exists in the southwest corner of the Up North Plastics site. Most of the surface
water runoff from the buildings and impervious surfaces drain to this basin. The northern slope of
this existing basin will be modified to create a flatter grade around the southwest corner of the
proposed addition for motor vehicles to access the proposed paved area west of the new building
addition. An illustration of the grade changes along the north side of the existing basin is shown
below.
Grading Plan
The City's engineering consultant is reviewing the property owner's Hydrology Report with a May
8, 2015 revision date. City approval of this report is required before a building permit can be issued
for the proposed building addition.
City Department Review and EDA Comments
Representatives from various City Departments reviewed the applicant's site plan review applica-
tion. The Building Division has reviewed the conceptual development plans and is unable to
provide comments regarding building code regulations until such time that all detailed construction
plans are submitted to their office.
The Cottage Grove Economic Development Authority (EDA) reviewed this project at their meeting
on May 12. They provided no comments or recommendation.
No comments or recommendations were received from other advisory commissions.
Recommendations
That the Planning Commission recommends that the City Council approve Up North Plastic's
development plan (site plan review application) as prepared by Krech, O'Brien, Mueller & Asso-
1 UY
f
1
-
nuvuoauuxn
' u
&
-
.
u
t
t
\a+uxcolx+c.»oee
d7
i \
I l
•.�: ..:�
�F�}_'
G^31 �i✓1 v' I,ly�,t}.
�' i
-y
I
3/ ,-
51
�
.�
lumno
nntmnv
Seam
Grading Plan
The City's engineering consultant is reviewing the property owner's Hydrology Report with a May
8, 2015 revision date. City approval of this report is required before a building permit can be issued
for the proposed building addition.
City Department Review and EDA Comments
Representatives from various City Departments reviewed the applicant's site plan review applica-
tion. The Building Division has reviewed the conceptual development plans and is unable to
provide comments regarding building code regulations until such time that all detailed construction
plans are submitted to their office.
The Cottage Grove Economic Development Authority (EDA) reviewed this project at their meeting
on May 12. They provided no comments or recommendation.
No comments or recommendations were received from other advisory commissions.
Recommendations
That the Planning Commission recommends that the City Council approve Up North Plastic's
development plan (site plan review application) as prepared by Krech, O'Brien, Mueller & Asso-
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 9 of 10
ciates dated March 20, 2015 for the construction of Up North Plastic's 86,641 square foot ware-
house addition and granting a variance to City Code Title 11-11-513(2), Performance Standards,
regarding the ordinance requirement that loading docks shall not be permitted along the side of a
building which faces a public street. The Planning Commission can modify any of the draft rec-
ommendations and conditions of approval. Approval of this site plan and variance to the loading
docks facing 95th Street is based on the following findings of fact:
A. The southwest corner of the proposed building addition is approximately 306 feet from 95th
Street. The minimum front yard setback is 40 feet.
B. The variance is generally consistent with the City Vision 2030 Comprehensive Plan's goals
and policies for commercial and industrial standards.
C. The future "Industrial" land use designation delineated in the Future Vision 2030 Compre-
hensive Plan is consistent with the existing 1-2, General Industry, zoning classification.
D. The new docks are proposed on the south side because of the existing dock locations on
the existing manufacturing and warehouse facility. The internal operations within the plant
have been devised to work with the present building layout and floor plan. The new addition
is an extension of the current processing system.
E. The site circulation has already been established with loading docks in the south side of the
facility. While typically it is not desirable to have the docks on the public frontage, the existing
conditions really dictate the functionality of the proposed addition.
Approval of Up North Plastics' site plan for the construction of their warehouse addition with three
loading docks along the south exterior wall for the new addition is subject to the following con-
ditions:
1. All applicable permits (i.e., building, electrical, mechanical) and a commercial plan review
packet must be completed, submitted, and approved by the Building Official, Fire Marshal,
and Public Works Director prior to the commencement of any construction activities.
2. An outdoor lighting plan must be submitted to the City for review and approval. All lighting must
meet City Code requirements. All outdoor light fixtures must be downward directed with cut-
offs. The specifications of all light fixtures must be provided with the application for a building
permit.
3. The final architectural plans and exterior construction materials and colors must be reviewed
and approved by the Planning Department prior to the issuance of a building permit.
4. The grading and erosion control plan for the site must comply with NPDES II Permit require-
ments. Erosion control devices must be installed prior to commencement of any grading activ-
ity. Erosion control must be performed in accordance with the recommended practices of the
"Minnesota Construction Site Erosion and Sediment Control Planning Handbook" and the con-
ditions stipulated in Title 10-5-8, Erosion Control During Construction, of the City's Subdivision
Ordinance.
Planning Staff Report
Up North Plastic's Expansion Project— Planning Case Nos. SP2015-018 and V2015-019
May 18, 2015
Page 10 of 10
The applicant must provide the City with an as -built survey of all private utilities prior to issuance
of the certificate of occupancy.
6. All mechanical equipment screening and trash enclosures must be constructed of materials
that are consistent with the principal building's exterior materials.
7. Storm sewer pipe must be reinforced concrete pipe (RCP).
8. The property owner is responsible for maintaining the stormwater basin. A stormwater man-
agement plan and the stormwater design shall be compliant with the City's Surface Water
Management Plan and South Washington Watershed District's (SWWD) regulations. Final
drainage plans must be submitted to the City and South Washington Watershed District for
review. A separate maintenance agreement for the stormwater basins must be executed
prior to the City issuing a certificate of occupancy for the new addition.
The exterior color of the overhead doors shall be a color and material that is similar and com-
plementary to the color scheme for the existing doorways along the south side of the building.
10. Up North Plastics must allow the City access to the private fire hydrants for inspection and
periodic flushing. A Storz Fire Department connection fitting must be installed on all fire hydrants
on the property.
11. Roof -top mechanical units shall be screened as required in City Code Title 11-6-4.
12. The fire hydrant placement on the site shall comply with the Fire Marshal's requirements.
Once these plans have been approved by the City, a building permit will then be issued.
13. Solid waste storage and/or storage in closed containers must be screened in compliance with
City Code Title 11-6-3, Solid Waste Storage, regulations.
14. The minimum setback for the fencing along Ideal Avenue is 30 feet.
Prepared by:
John McCool, AICP
Senior Planner
Attachments:
Site Plan
Demolition Plan
Grading and Drainage Plan
Building and Wall Sections Details
Ii ; gii•i€j� j!'"I 65T0-9TO89 V1O53NNIW '3AOL030vnoD
3p { L+ 1 N1fW53ON3AV ValvwvC 08VG g
goer 0 I "�gF tyeji. ;,¢`F�gkc,t I NOIlI0Otl 3SnONaUVM
Fi.ga p: s3USnd H1HONdN
gdg� �i� fii ptilf it F E a a
133HS 311I1 ''�
I1
a �I"
._................�........:.
LU w ii
r
� a
z
o Q-
NJ='a9po
QW Egg
Kp
� ."arsrsaas naaan `pr
s
W .0
�6� =§E ��� �5� � � tooa5fg,
e $ g�
r Fy 4.`q
fl
. e
fit° ��`sy-�� &` �.�4
3 ay@ g%§1 �H 111 In 3i 6 =dm 1"ee
■ .. _@ `' Yp Na§ € ev. $ :;e a=° __________ ___ _______________________ _
0fflE
F. BEp [@
dg bio ^wt8 5 eH. � � yy �idNQ 371/ 35 -
Z T a"ZS32 �6 Ei[ fii{g d$bd8o 4:3 �dai �9 �
pp $$ p
F 9{ 6 y NB Kp @S9 ¢¢p'p 7 g "efa i$gi' 679{E pa {e kygylt 9 EkE 1His^i� -p1j[ s�By. ! aid9 3 ?k ` e 3$
Q Ei ei a 3! 9H 4 it l.73 3}33�P44dt86�@Bfl 99$f 99 :S$$SB9 6i� s iia.g�$555fg g 46gflg i �;ffi if4FP( $, k6 hfif FI$f iiif7$$ff li
f
'j Lu 3;
,
g �zI4 * $H§4Sa$i!#f� ���� k3$3P$c faif➢ss4�d46i@v r��fi;�1 i$ee k�i� 331�Sk59$33d ���E��$�! �'p€�Sa�€�€a'en€'f€ s[�a€�f§��(�
O
Z�W/ N �V 91 �� ...�ie....�4: i€f.flta e3iveeeefeeae
a a ' d .is gi i n E k $ � iaiiESga e'' l,6$.71e34� f4 wg,;P6i$€i I p@{{ig$ g 3 R.x@4.3 a di a gk ly�.i€cif pSS°Y#i�f€
Sra4 HOUR
e' ��§E$�a F 86 9gfE a
' a�sa$ aa8 xB�A§€6S�§6$6{��E�aaa'a $ f.. �$i�158 saaaaa'j'P�s 4
a 6 .at r. �.v$s.r 3.4s$43 3�a�evlsa.7i8§ al9aa3e3..easE.ae92f$k$§@$r48.�e6$s�d a$&s€a xT e�a..f...af.?e..l.i_?$:
o do[ a
z —'a8 PH :nhl,IltG. s #�l�i 05
� !
�gE
Ei
4
x tE\ - 3.sgg i Oi 8 `e
Lj
!mno R
t ii t if,
Y* a
aS,a alil
'sr o
i
t
r s a 1 a
I [r z
it I� t` w as xa a F
I : aE. a
1 i 111'i 11 Y 0 1 8§ a Y £pss.
g-
1
1
-iiii5
4y a4 a s ='-
s
✓ ' r�i i �' 3 � - �� �r � I I � as ego ¢g 3 ee b
.�
..� _
t t /ii.
Mi
.. # 3 d E s 3
dP �� s
1 !I1 .r� I e. z�
rlr> r l�6 M � k� ei � 9� a s
of€fig$ sEE
t I Zt o a CC �d€ as �i f
Ya '"r —
c
i
s
V
—,4 d BVI
I
go
IN
II
1
I
Ei
l� xe P
1
rZ
elm
i
s
V
(1- 1� /
;� §