HomeMy WebLinkAbout2015-06-03 PACKET 12.A.
Feasibility Report
Jamaica Avenue
(Indian Boulevard to Military Road)
Street and Utility Improvements
Cottage Grove, Minnesota
May 28, 2015
Project No. 193801999
I hereby certify that this report was prepared by me or under my direct
supervision and that I am a duly licensed Professional Engineer under
the laws of the State of Minnesota.
_________________________________________________________
David R. Sanocki, P.E. Reg. No. 40973
May 28, 2015
CITY OF COTTAGE GROVE
TABLE OF CONTENTS
TABLE OF CONTENTS 1
PROJECT SUMMARY ............................................................................................................. 2
Introduction ..................................................................................................................... 2
PROJECT SCOPE ............................................................................................................... 2
Required Improvements ................................................................................................. 2
REQUIRED EASEMENTS .................................................................................................... 4
Required Permits ........................................................................................................... 4
PROJECT COSTS ............................................................................................................... 4
Estimated Construction Costs ......................................................................................... 4
FINANCING ...................................................................................................................... 5
RECOMMENDATIONS TO COUNCIL .................................................................................... 5
PROJECT SCHEDULE ............................................................................................................ 6
APPENDIX
Preliminary Cost Estimate
FIGURES
Figure 2 Proposed Street Improvements
Figure 3 Proposed Street Improvements Î Roundabout
Figure 4 Dodge Nature Center Î Sanitary Sewer & Water
Figure 5 Assessable Parcels
CITY OF COTTAGE GROVE
PROJECT SUMMARY
INTRODUCTION
This report addresses the proposed improvements for Jamaica Avenue between Indian Boulevard and Military
th
Road (C.S.A.H. 20), and 70 Street South (C.S.A.H. 22) between 1600 feet west and 700 feet east of Jamaica
th
Avenue. Jamaica Avenue, north of 70 Street is showing significant signs of surface deterioration. City Public
Works staff continue to patch and repair this road segment on a regular basis.
th
The proposed improvements include constructing a roundabout at the intersection of Jamaica and 70 Street;
including storm sewer, concrete pavement, concrete medians, trail extensions, lighting, irrigation, and
th
landscaping. Jamaica Avenue, both north and south of 70 Street, are proposed to be reclaimed and a new
th
bituminous section constructed. 70 Street is proposed to be reconstructed to include turn lanes into the
Dodge Nature Center. The general project location is shown below in Figure 1 below. It is anticipated that
this project would be constructed during the 2016 construction season.
PROJECT SCOPE
This project consists of street improvements in the general location shown in Figure 1 below.
Figure 1 Î General Project Location
RI
EQUIRED MPROVEMENTS
th
The project includes improvements to Jamaica Avenue between Indian Boulevard and Military Road; and 70
Street South between 1600 feet west and 700 feet east of Jamaica Avenue (see figure 2 in the appendix of
th
this report). A roundabout at the intersection of Jamaica Avenue and 70 Street, public trail extensions,
street lighting and landscaping are all included in the proposed improvements to be constructed in 2016.
th
The intersection of Jamaica Avenue and 70 Street currently exists as a four way stop controlled intersection.
This intersection is proposed to be reconstructed with a roundabout (see figure 3 in the appendix of this
report). The proposed roundabout will be constructed with concrete curb and gutter, concrete pavement and
concrete medians.
Jamaica Avenue, north of the roundabout, is proposed to be fully reconstructed to the north property line of
the Rose of Sharon Church. Jamaica Avenue, north of the Rose of Sharon Church north property line and
south of the roundabout, is proposed to be reclaimed and a new section of bituminous placed. To minimize
costs related to future adjoining development construction north of the Rose of Sharon Church an interim
pavement section (16 foot bituminous with 8 foot gravel shoulder) will be constructed. A full access to
Jamaica Avenue is proposed for the Rose of Sharon Church.
th
70 Street is proposed to be reconstructed to provide turn lanes into the Dodge Nature Center. The Dodge
Nature Center is proposing to start school programs on site in 2016.
A cost estimate has been included in the appendix of this report. All street improvements will be designed to
meet Municipal State Aid, City of Cottage Grove and Washington County Standards.
th
Eight-foot wide bituminous trails are proposed to be extended on both sides of Jamaica Avenue north of 70
th
Street. The trail on the west side of Jamaica Avenue is proposed to be extended to 67 Street Court South.
The trail on the east side of Jamaica Avenue is proposed to be extended to the northern access of the Rose
th
of Sharon Church. Portions of the existing sidewalks on Jamaica Avenue south of 70 Street are proposed to
be realigned to connect into the proposed roundabout.
Street lighting is proposed to be installed within the four legs of the roundabout. The lighting will be very
th
similar to the lighting installed in the roundabout at the intersection of 70 Street South and Keats Avenue.
Ravine style lighting is proposed to be installed on both sides of Jamaica Avenue; north of the roundabout to
the north property line of the Rose of Sharon Church.
The intent of this project is to provide landscaping, irrigation and accent lighting to the roundabout area. The
landscaping will include hardwood trees, shrubs, perennials and ornamental grasses. The landscaping,
th
irrigation and accent lighting will be very similar to that installed in the roundabout at the intersection of 70
Street South and Keats Avenue.
An 8 inch sanitary sewer service and 8 inch water service are proposed to be extended from the south side of
th
70 Street to the Dodge Nature Center property (see figure 4 in the appendix of this report). These utility
extensions will provide future service connections for the Dodge Nature Center.
REQUIRED EASEMENTS
th
At the intersection of 70 Street and Jamaica Avenue, where the roundabout is proposed, additional right-of-
way will be required at the four corners. The additional right-of-way will be needed to construct the proposed
trails and grading slope transitions.
Temporary construction easements will also be required, the extent of which will be determined during the
detailed plan preparation.
RP
EQUIRED ERMITS
This project requires the following permits:
MPCA General Storm water permit (NPDES Permit)
Washington County Right of Way and Access Permit
MPCA Sanitary Sewer extension Permit
MN Department of Heath Water Main Permit
PROJECT COSTS
ECC
STIMATED ONSTRUCTION OSTS
th
A detailed cost estimate for improving Jamaica Avenue between Indian Boulevard and Military Road; and 70
Street South between 1600 feet west and 700 feet east of Jamaica Avenue, have been prepared and is
included in the Appendix. All costs are based on anticipated unit prices for the 2016 construction season.
th
Costs for required right-of-way and temporary easements near the intersection of Jamaica Avenue and 70
Street are not included. An overall summary of the estimated cost is shown below:
th
Jamaica & 70 Roundabout$1,215,770
th
70 Street $372,600
th
70 Street Turn Lane$ 173,930
Jamaica Avenue -South$ 285,160
Jamaica Avenue -North$678,680
ge Nature Center$ 209,950
Dod
TOTAL PROJECT COSTS*$2,936,090
*Right-of-way and temporary easement
costs are not included.
FINANCING
The improvement costs for this project would be financed through the use of a number of dedicated funds
and special assessments. Washington County would provide funding for a portion of the improvements
th
proposed within the 70 Street (C.S.A.H 22) right-of-way
Following is a breakdown on the proposed project financing:
Washington County $ 1,181,530
City of Cottage Grove /
$ 1,754,560
Assessments*
TOTAL PROJECT COSTS $ 2,936,090
*Assessment amounts are based on the City Policy and
further subject to benefit appraisal.
RECOMMENDATIONS TO COUNCIL
The proposed improvements in this report are necessary, feasible and cost-effective related to general
engineering principles. The feasibility of this project as a whole is subject to the financial review. The
improvements are necessary to address continued maintenance issues and to serve future development
properties.
The following recommendations are made:
Adopt this report as the guide for improving the streets described.
The City conducts a legal and fiscal review of the proposed project.
The City installs the improvements as described within this report, with construction being started in
2016.
The below tentative schedule be implemented for the project.
Accept the feasibility report and order the Public Hearing.
PROJECT SCHEDULE
The following is a proposed project schedule:
Council Workshop June 3, 2015
Neighborhood Meeting July 28, 2015
Council Receives Feasibility Report and
Call for Public Hearing August 12, 2015
Council Holds the Public Hearing and Orders
Preparation of the Plans and Specifications September 16, 2015
Approve Plans and Specifications and Set Bid Date January 2016
Project Bid Date February 2016
Contract Award February 2016
Construction Begins April 2016
Construction Completed September 2016
Assessment Hearing October 2016