HomeMy WebLinkAbout07O Final Payment for CP Watermain Improvements
City Council
Action Request Form
Meeting Date
9/7/2016
Department
Community Development
Agenda Category
Consent Agenda
Title
Final Payment for CP Rail Watermain Improvements
Staff Recommendation
Adopt Resolution No. 2016-XXX approving the Final Payment to Minger Construction in the amount of
$38,420.11 for the CP Rail Watermain Improvements.
Budget Implication
Original Contract Amount: $150,737.50 Revised Contract Amount: $164,384.63; Final Construction
Amount: $174,288.63
Attachments
Letter from Stantect
Resolution
RESOLUTION NO. 2016-XXX
RESOLUTION APPROVING FINAL PAY REQUEST IN THE
AMOUNT OF $38,420.11 TO MINGER CONSTRUCTION CO.
FOR THE CP RAIL WATERMAIN IMPROVEMENTS PROJECT
WHEREAS, the City Engineer has certified that work has been satisfactorily
completed; and
WHEREAS, the original total contract amount was $150,737.50. There was
one change order for this project and the Revised Contract amount was
$164,384.63. The actual contract amount completed was $174,288.63, which is
$9,904.00 over the original contract amount. The overrun amount was primarily due
to rock excavation and additional fittings needed to connect to the existing water
main system; and
WHEREAS, the project has been satisfactorily completed in accordance with
the contract plans and specifications.
NOW THEREFORE BE IT RESOLVED, by the City Council of the City of
Cottage Grove, County of Washington, State of Minnesota, that $38,420.11 is paid
to Minger Construction Co. for Final Pay Request for the CP Rail Watermain
Improvements Project.
Passed this 7th day of September 2016.
Myron Bailey, Mayor
Attest:
Joe Fischbach, City Clerk