HomeMy WebLinkAbout04-1 HERO Center Project Schedule 3 Quarter 20 rd HERO CENTER PROJECT SCHEDULE As of February 9, 2017, the estimated HERO Center project schedule is as follows: February 9, 2017 Presentation of pre-design to City Councils March-June, 2017 Schematic capital design June 2017 Operational business plan, pro-forma July, 2017 Submit for Governor’s 2018 bond request /Intent to request funds June-September, 2017 Design development/Bonding tour September-October, 2017 Design development completion/Owner review period October-December, 2017 Governor’s budgeting November, 2017-March, 2018 Construction documents March-May, 2018 Owner/quality control review period February-May, 2018 Legislative Session/Legislative bonding request August, 2018 Construction funding awarded June-August, 2018 Construction bidding phase September, 2018-October, 2019 Construction October, 2019 Occupancy