Loading...
HomeMy WebLinkAbout4.2 NorthPoint Memo 2022-3-16 TO: Economic Development Authority FROM: Christine Costello, Community Development Director DATE: March 10, 2022 RE: Cottage Grove Logistics Park Phase I – TIF Agreement Background NorthPoint Development (Developer), a Kansas City based development company, received a Master Site Plan approval in December 2021. The Master Site Plan for Cottage Grove Logistics Park consists of approximately 252 acres of land encompassing an assemblage of six separately owned parcels. The Master Site Plan approved nine separate warehouse, manufacturing, distri- bution, and office space buildings. The Developer proposed a phased development, and therefore requires a site plan to be reviewed and approved for each proposed phase of development of the Cottage Grove Logistics Park to ensure the proposed phase aligns with the approved Master Site Plan. At the December 2021 Economic Development Authority (EDA) meeting NorthPoint Development (NorthPoint), received approval for the creation of TIF District No. 1-20 for the Cottage Grove Logistics Park. As part of the TIF District approvals NorthPoint is required to submit to the EDA their proposed phasing plan for each phase of the development. Master Site Plan – Cottage Grove Logistics Park NorthPoint has submitted their first phase of development within the Cottage Grove Logistics Park Master Plan area. Phase I consists of construction of two buildings with approximately 700,000 square feet. In addition, to the construction of the two buildings NorthPoint will also be completing public improvements to 100th Street, Ideal Avenue, and the construction of 105th Street. Economic Development Authority March 10, 2022 Page 2 of 3 Phase I Location per Overall Master Plan Phase I Site Plan Economic Development Authority March 10, 2022 Page 3 of 3 Cottage Grove Logistics Park Building Rendering Planning Commission and City Council The City’s Planning Commission reviewed and held a public hearing for NorthPoint’s request at their February 28, 2022, meeting and recommended approval (7-to-0) of Phase I. The City Council will consider NorthPoint’s Phase I proposal at their April 6, 2022, meeting. Recommendation Consideration of a motion to recommend approval of Phase I of the Cottage Grove Logistics Park.