HomeMy WebLinkAboutCIP 2026-2030CITY OF COTTAGE GROVE, MN ENGINEERING AND FINANCE DEPARTMENT 12800 Ravine Parkway S, Cottage Grove, MN 55016 | 651-458-2800 | CottageGroveMN.gov Capital Improvement Plan 2026 – 2030 City of Cottage Grove Capital Improvements Plan 2026-2030 Table of Contents Page No. Introduction 1-5 Projects by Program Category 8-9 Funding Summary by Year 11 Facilities and Park Projects Summary 13 Facilities and Park Projects Detail 14-37 Street, Road Improvements & Public Works Projects Summary 39 Street, Road Improvements & Public Works Projects Detail 40-62 Projects by Year (with Maps) 2026 Annual Summary 64-65 2027 Annual Summary 66-67 2028 Annual Summary 68-69 2029 Annual Summary 70-71 2030 Annual Summary 72-73 Projected Financial Position Statements Roadway and Trailway Maintenance Fund 74 Ice Arena Capital Fund 75 Storm Water Utility Fund 76 Water Utility Fund 77 Sanitary Sewer Utility Fund 78 Street Light Utility Fund 79 Park Improvement Fund 80 Park Trust Fund 81 Public Landscape Initiative Fund 82 Municipal Building Fund 83 ED Trust Fund 84 MSA Construction Fund 85 SROP Fund 86 Pavement Management Fund 87 Water Area Fund 88 Sanitary Sewer Area Fund 89 Storm Water Area Fund 90 3M Settlement/MPCA Fund 91 Bonds (Debt Issuance) 92 -This Page Intentionally left Blank - City of Cottage Grove Capital Improvements Plan 2026-2030 Introduction The Capital Improvement Plan (CIP) is a planning device to schedule proposed public capital improvements and purchases over a five-year period. The CIP matches proposed expenditures and revenues by project. A capital improvement is defined as a capital expenditure that is greater than $15,000 with a life expectancy of five years or longer. Capital improvements are projects, which require acquisition, construction, or replacement of various public facilities, public buildings, infrastructure, utilities, and parks in the community. Every effort has been made to draft the document as conservatively and realistically as possible while maintaining the integrity of the funds. The concept of fund integrity includes accounting for certain projects, in particular designated funds that are only used for those purposes for which they are collected. These major funding sources include the operating funds (the General Fund and Enterprise Funds), the development fees and charges (including the Area and Park Trust Funds), as well as identifying larger general projects that are expected to be financed with the issuance of general obligation bonds to be repaid with future property tax levies. A Ten-Year Financial Management Plan (FMP) was completed in 2023. The FMP incorporated the projects included in this CIP that include debt issuance as part of the funding source, future operating budgets including equipment replacement needs, and tax capacity changes (including growth). This FMP has been updated each year, and projects in this CIP were included in the FMP that was utilized during the 2026 budget process. This CIP shows a total capital investment of $72.7 million for 2026 of which $34 million is related to the construction projects funded by the 3M settlement funds, including the Intermediate Zone Water Treatment Plant. $17 million is for the reconstruction of 80th Street from Ideal Avenue to Highway 61 ($5 million of this project will be paid with Federal funds and approximately $5 million will be reimbursed by the State and County for MnDOT intersection improvements). $7.4 million is related to various other street projects including Pavement Management (Thompson Grove Estates 11th Addition, south part Woodridge Park Addition (West of Jamaica)), and 80th Street/Keates Avenue roundabout which is a County led project. Projects summarized by year are included on pages 8-9. This document covers the period from 2026 to 2030 and is organized by the funding sources of the improvement project. Over the next five years $386.9 million in projected improvements have been identified. A significant portion of these projects (76% or $294.3 million) will be funded by other entities and other governmental entities. The remaining dollars come from other identified sources. A funding summary by year is included on page 11. Details of all projects are included on pages 13-62. Maps of projects by year are included on pages 64-73. 1 2026-2030 CIP Introduction Summary of Improvements The identified improvements are included in the financial position statements by fund on pages 74-91. A fund is a related account that is used to maintain control over resources that have been segregated for specific activities or objectives. Eighteen funds are utilized for the accounting of the projects in the CIP. Road and Trailway Maintenance Fund (Page 74) The Road and Trailway Maintenance Fund records activities related to mill & overlaying, trail sealing, and trail replacement activities. Funding for these activities comes from franchise fees charged to property owners on their electric and natural gas utility bills. 2026 includes another mill and overlay project in the amount of $1,019,000. In addition, $673,000 will be spent for trail replacement. Ice Arena Capital Fund (Page 75) The naming rights revenue from NorthPoint is the primary source of revenue for the Ice Arena Capital Fund. 2026 projects include a Zamboni replacement. Enterprise Funds (Pages 76-79) The capital projects included in the Enterprise Fund section are those projects, which will be paid for with funds from the Storm Water, Water, Sanitary Sewer, and Street Light Utility Funds. Each of the Enterprise Funds is supported by user fees charged for the services provided. Storm Water Utility Fund The Storm Water Utility Fund projects include various drainage improvements and maintenance of the storm water utility system. The 2026 projects identified include storm water maintenance related to the 2026 Pavement Management project. Commitments of the Fund for the next five years are for various storm water activities throughout the City. Water Utility Fund The Water Utility Fund includes funding for SCADA upgrades and a meter replacement program beginning in 2026. Other capital projects in the Fund include the water costs for the annual Pavement Management Program, and well maintenance. Debt service for the new Utilities Building is also included in this fund. Sanitary Sewer Utility Fund Sewer costs related to the annual Pavement Management Program, and street reconstruction projects are included in the next five years. Street Light Enterprise Fund The improvements scheduled for the Street Light Utility Fund are traffic signals and system improvements. New traffic signals identified in the next five years are a signal at 80th Street and Jamaica Avenue in 2028, and Keats and Indian Boulevard in 2028. Park Improvement Capital Project Fund (Page 80) In 2013, the City Council directed that revenues derived from leasing space on the City’s Water Towers/Reservoirs for cell phone antennas should be allocated to the purpose of renovation of existing parks and replacement of playground equipment. This revenue source will fund a total of $3.2 million in park and playground renovations over the next five years. Expenditures in 2026 include jump line improvements at the Bike park, sporting lighting improvements at Hamlet, and skate park surface replacement at Hamlet Park. The FMP completed in 2023 identified a need 2 2026-2030 CIP Introduction to fund park improvements beyond the capacity of the cell phone antenna revenues. Therefore, a property tax levy has been included in the Fund beginning in 2026 in the amount of $190,000 per year. Park Trust Fund (Page 81) Improvements scheduled in the Park Trust Fund include the purchase of additional parkland, planning and development of parks and trails, and installing playground equipment in new parks. Revenues coming into the Park Trust Fund have been calculated to reflect the anticipated housing growth and a greater dedication of park land instead of park dedication fees. In 2026, the Jack and Marlys Denzer Park will be constructed, and construction will begin at Roberts Lake. Landscape Initiative Fund (Page 82) Improvements scheduled in the Landscape Initiative Fund include landscape beautification and tree mitigation. Funds from developers fund the projects in this fund. Municipal Building Fund (Page 83) This Fund derives its revenue from accumulated transfers from the General Fund pursuant to the Fund Balance policy, as well as several years of dedicated tax levy dollars. The property tax levy of $350,000 in 2025 will increase to $450,000 in 2026 to be used for municipal building maintenance expenses, and the interfund loan for the building of the Public Safety/City Hall (PSCH) building. In 2025, a facility assessment study was completed for the PSCH building and Central Fire Station. The maintenance items needed in the next five years for both buildings average $250,000 per year. Economic Development Trust Fund (Page 84) The primary source of revenue for this Fund is from an annual donation designated for economic development activities. 2025 and 2026 construction projects include Jamaica and 95th Street intersection improvements and preliminary construction project costs related to the CSAH 19 and TH 61 project. MSA Construction Fund and Street Reconstruction and Overlay Fund (Pages 85-86) The construction of new streets and other street reconstruction projects make up the vast majority of capital improvement projects in the MSA Construction Fund. Funding for these projects includes Municipal State Aid (MSA), other intergovernmental revenue, developer charges and special assessments. Streets included on the “state aid” system are eligible to receive state aid for a portion of the projects. The MSA annual construction allotment for 2025 was $2.47 million. The projects noted below and, in the CIP, will depend on development, the timing of which will vary due to factors including the economy and available land. The 2026 projects identified with their anticipated MSA funding include: Besides MSA revenue, these projects will be funded with other revenue sources including Federal, State, and County funds, assessments, utility funds, and possibly bonded debt. 3 2026-2030 CIP Introduction Other projects that have been included in the MSA Fund that have funding sources other than MSA revenue include: • Jamaica and 95th Improvements (Primary funding sources-ED Trust and development fees) • Ravine Parkway constructions (Primary funding source-development fees) • EPD and Ravine Parkway-Shoppes at Cottage View starting in 2028. (Funding sources- federal funds for $3 million, area funds, and assessments/development fees) • 103rd Street Bridge in 2023. (Funding sources-federal and state funds) A Street Reconstruction and Overlay Plan was approved in 2023 that allows for street reconstruction and overlay bonds to be issued for construction projects identified in the plan. These projects include: • 100th Street 2026-2030. o The CSAH 19 and TH 61 project will be a county-led project that will be primarily funded with Federal and County Funds. The realignment portion of 100th Street of this project will be funded by the City. • Jamaica Avenue from 70th to Military in 2028. (Funding source-bonded debt) • Harkness Avenue in 2030. (Funding sources-area funds, developer fees, and bonded debt) Details of these projects and funding sources are included in the detail of the projects located on pages 42-49. Pavement Management Fund (Page 87) Pavement Management Program projects are reflected in this Fund. The summary sheet identifies other funding sources when available, but for most projects it will be necessary to issue debt to be repaid with a property tax levy to finance the project. The continuation of the Pavement Management Program depends on assessments for a portion of each project to be used to repay a portion of the debt. The Pavement Management projects included in the next five years total $23.8 million, of which $10.7 million would be assessed to benefiting property owners and $19.5 million would be bonded. Future property taxes levies would repay these bonds and have been included in the FMP. $3,415,000 $1,536,750 $2,420,000 $995,000 3,508,000 1,578,600 2,945,000 563,000 north part Woodridge Park Add (W 3,766,000 1,694,700 2,668,000 1,098,000 6,066,000 2,729,700 4,485,000 1,584,000 7,036,000 3,166,200 7,036,000 1,090,000 4 2026-2030 CIP Introduction Area Funds (Pages 88-90) The Water, Storm Sewer and Sanitary Sewer Area Funds are capital project funds that provide the resources to construct general infrastructure. Projects totaling $10.3 million are expected to be funded from the Area Funds over the next 5 years. The funding sources for these Funds are area charges and connection fees against developing properties and new building construction. The area charges and connection fees are based on rates established by the City Council. Water Area Fund Construction of a water tower in the Industrial Park will be completed in 2026. This project was funded with the Water Utility Fund, Water Area Fund, and bonds. The bonds will be repaid with future revenues (developer area charges) in the Water Area Fund, and the debt service payment is reflected in the fund. Other expenditures in the fund include the water portions for 100th Street, Shoppes at Cottage View, and east ravine development. Sanitary Sewer Area Fund Funding for projects identified in the Sanitary Sewer Area Fund includes activities regarding system-wide construction for 100th Street, Shoppes at Cottage View, and east ravine development. Storm Water Area Fund Funding for projects identified in the Storm Water Area Fund includes activities regarding system-wide construction for 100th Street, Shoppes at Cottage View, and east ravine development. Other Funds (Page 91) 3M Settlement/MPCA Fund 3M settlement implementation funds will be used to construct the Intermediate Zone Water Treatment Plant in 2025 through 2029, and decommissioning of Well #1, Well #2, and the temporary treatment plants. 3M settlement funds will be received to fund the 2026-2029 projects totaling $76 million. Bonds (Page 92) Debt will be issued to fund specific projects identified in the CIP and debt issuance was identified as a financing mechanism in the preparation of the FMP in 2023 for certain CIP projects. The debt (bonds) that have been identified in the CIP are consistent with the debt identified in the FMP. Where there are differences, additional analysis in future years will need to be undertaken to understand the property tax impact. Due to rapid growth in the city, there will likely be little impact. Conclusion City staff has prepared this document in conjunction with those projects and capital items that are known and for which costs can be reasonably estimated. The CIP should be considered a planning tool and the projects included for 2026 and 2027 serve as a work plan for staff. This “work plan” means that these are the projects that staff will bring to Council for authorization before proceeding with a feasibility study, acquisition, or construction. All projects detailed in this document will be included in their respective budgets if the need is established at that time. 5 -This Page Intentionally left Blank - 6 -This Page Intentionally left Blank - 7 PROGRAM CATEGORY 2026 2027 2028 2029 2030 General Public Buildings City Hall/Public Safety-Maintenance 178,950 142,100 250,850 219,900 446,171 Central Fire-Maintenance 33,183 76,580 70,364 2,325 Public Works-Maintenance 12,000 85,000 800,000 60,000 General Public Buildings Total 212,133 230,680 406,214 1,019,900 508,496 75,000 7,000,000 2,000,000 7,000,000 10,000 10,000 10,000 10,000 10,000 80,000 100,000 120,000 100,000 100,000 15,000 15,000 15,000 15,000 15,000 35,000 35,000 35,000 35,000 35,000 100,000 350,000 100,000 5,000,000 10,000 800,000 700,000 500,000 500,000 500,000 315,000 60,000 20,000 100,000 500,000 30,000 150,000 100,000 150,000 500,000 355,000 350,000 35,000 Parks & Recreation Facilities Bike Park Jump Line Improvements Mississippi Dunes Park Matching grant funds Public Landscape initiative Parks - design & planning Parks-Automatic locks on buildings Hamlet Park Skate Park Surface Replacement Hamlet- Park shelter replace & Skate park equip. Hearthside Park: Park Improvements Hemmingway and North Ideal play equipment Highlands Park Tennis Court Replacement Kingston Park Building Replacement Lamar Park Roof-not needed/replaced 2025 Neighborhood Park Development Peter Thompson Park Upgrades Picnic Shelters Pine Coulee-Court Replacement Pine Glen Park Improvements Pine Tree Pond Park Improvements Pine Tree Valley Ice Rink Board Replacement River Oaks Scenic Overlook Woodridge Park Court Resurfacing Woodridge Playground Surface Replacement Sports Lighting Improvements Ice Arena Capital Projects 145,000 1,625,000 145,000 575,000 60,000 Parks & Recreation Facilities 1,615,000 15,315,000 3,775,000 8,515,000 1,680,000 Public Utilities Facilities Annual Sewer Spot Maintenance/Slip Lining 50,000 52,000 53,000 55,000 56,000 Streetlight System Improvements 100,000 103,000 106,000 109,000 112,000 Storm Water Maintenance 205,000 210,000 217,000 224,000 230,000 Trunk Utility Oversizing 20,000 20,000 20,000 20,000 20,000 East Ravine District Infrastructure 50,000 50,000 50,000 50,000 50,000 Annual Well Maintenance 90,000 93,000 96,000 99,000 102,000 SCADA & Well Upgrades 887,900 304,500 Water Tower Painting/Rehab 1,000,000 Traffic Signals, Traffic Improvements 1,480,000 3M Settlement Implementation 34,045,192 30,045,192 12,518,830 4,003,766 Water Softening 100,000,000 Pedestrian Improvements 350,000 Public Utilities Facilities total 35,448,092 31,877,692 14,540,830 4,910,766 100,570,000 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 PROJECTS BY PROGRAM CATEGORY NOTE: This recap includes the total project cost. See the individual project page for funding sources 8 PROGRAM CATEGORY 2026 2027 2028 2029 2030 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 PROJECTS BY PROGRAM CATEGORY NOTE: This recap includes the total project cost. See the individual project page for funding sources Street & Road Improvement Projects Roadway Maintenance 1,979,000 2,078,000 2,183,000 2,292,000 2,407,000 Safe Streets & Roads for All (SS4A)440,000 CSAH 19 and TH 61 680,000 27,742,500 23,077,500 22,900,000 Jamaica Avenue 3,000,000 Ravine Parkway - Shoppes at Cottage View 4,223,000 2,527,000 4,343,000 1,353,000 Ravine Parkway 3,200,000 1,200,000 1,000,000 1,000,000 200,000 80th Street (CSAH19 to TH 61) Reconstruction 17,290,100 80th Street (80th/Keats roundabout cost share)4,000,000 Harkness Ave Reconstruction 3,162,000 103rd Street Railroad Bridge 150,000 150,000 800,000 8,000,000 Subtotal before PM 31,962,100 31,170,500 32,587,500 7,635,000 38,022,000 PM 2026 3,415,000 PM 2027 3,508,000 PM 2028 3,766,000 PM 2029 6,066,000 PM 2030 8,126,000 Road & Street Improvement projects total 3,415,000 3,508,000 3,766,000 6,066,000 8,126,000 9 -This Page Intentionally left Blank - 10 2026 2027 2028 2029 2030 Total '26 to 30 Funding Source Bonds for Pavement Management 2,420,000 3,045,000 2,668,000 4,585,000 7,136,000 19,854,000$ Bonds for CSAH 19 & TH 61 2,621,250 198,750 2,820,000 Bonds for Shoppes at Cottage View 377,000 2,760,000 860,000 3,997,000 Bonds for Harkness Avenue 938,000 938,000 Bonds for Jamaica (Rose of Sharon to Military)3,000,000 3,000,000 Bonds for Kingston Park 5,000,000 5,000,000 Bonds for Ice Arena 1,500,000 1,500,000 Bonds for Dunes Park 2,000,000 1,500,000 7,000,000 10,500,000 Park Improvement Fund 575,000 775,000 495,000 195,000 905,000 2,945,000 Park Trust 815,000 715,000 1,015,000 545,000 515,000 3,605,000 Public Landscape Initiative 80,000 100,000 70,000 100,000 100,000 450,000 Ice Arena Capital Fund 145,000 125,000 145,000 575,000 60,000 1,050,000 Municipal Building Fund 212,133 230,680 406,214 1,019,900 508,496 2,377,423 Franchise Fees 1,976,000 2,064,000 2,173,000 2,281,000 2,392,000 10,886,000 Federal/Grant Funding 8,352,000 19,000,000 19,000,000 - 120,433,000 166,785,000 State of Minnesota 5,436,000 5,150,000 550,000 350,000 11,486,000 Municipal State Aid 5,023,000 1,800,000 5,875,000 12,698,000 Washington County 2,250,000 2,971,250 1,098,750 4,075,000 10,395,000 Developer Assessments/Fees 5,011,600 1,200,000 2,520,000 1,869,000 1,756,000 12,356,600 3M Settlement 34,045,192 30,045,192 12,518,830 4,003,766 80,612,980 Utility Funds 2,381,400 2,339,500 2,320,000 2,079,000 1,605,000 10,724,900 72,652,325$ 82,101,872$ 55,075,544$ 28,146,666$ 148,906,496$ 386,882,903$ City of Cottage Grove Capital Improvement Plan 2026-2030 Funding Summary by Year 11 -This Page Intentionally left Blank - 12 FACILITIES AND PARK PROJECTS Funding Sources 2026 2027 2028 2029 2030 Tax Levy -$ -$ -$ -$ -$ Bonded Debt -$ 8,600,000$ 1,500,000$ 7,100,000$ 100,000$ State/Other Government Units -$ -$ -$ -$ -$ Park Improvement Fund 575,000$ 775,000$ 495,000$ 195,000$ 905,000$ Park Trust Fund 815,000$ 715,000$ 1,015,000$ 545,000$ 515,000$ Landscape Initiative 80,000$ 100,000$ 70,000$ 100,000$ 100,000$ Municipal Building Fund 212,133$ 230,680$ 406,214$ 1,019,900$ 508,496$ Other:145,000$ 5,125,000$ 695,000$ 575,000$ 60,000$ TOTAL 1,827,133 15,545,680 4,181,214 9,534,900 2,188,496 Project Expenses 2026 2027 2028 2029 2030 Land/Easements -$ -$ -$ -$ -$ Engineering/Architect 15,000$ 1,615,000$ 465,000$ 1,415,000$ 15,000$ Admin/Legal -$ -$ -$ -$ -$ Construction 1,510,000$ 13,590,000$ 3,180,000$ 6,990,000$ 1,555,000$ Maintenance 212,133$ 230,680$ 406,214$ 1,019,900$ 508,496$ Other 90,000$ 110,000$ 130,000$ 110,000$ 110,000$ TOTAL 1,827,133 15,545,680 4,181,214 9,534,900 2,188,496 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 13 Project Title Project Description City Hall Public Safety Major Maintenance Department City Hall Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building 178,950 142,100 250,850 219,900 446,171 Other: TOTAL 178,950 142,100 250,850 219,900 446,171 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction Maintenance 178,950 142,100 250,850 219,900 446,171 Other TOTAL 178,950 142,100 250,850 219,900 446,171 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Major maintenance projects for the City Hall-Public Safety building per the Kraus Anderson Facility Condition Assessment. 14 Project Title Project description Central Fire Station Major Maintenance Assessment. Department Fire Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building 33,183 76,580 70,364 2,325 Other: TOTAL 33,183 76,580 70,364 0 2,325 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction Maintenance 33,183 76,580 70,364 2,325 Other TOTAL 33,183 76,580 70,364 0 2,325 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Major maintenance projects for the Central Fire Station per the Kraus Anderson Facility Condition 15 Project Title Project description Public Works Major maintenance projects for the public works facility. Major Maintenance 2027 - Water heater 2028 - Garage doors and flooring Department 2029 - Roof replacement Public Works 2030 - Vinyl Tile Replacement Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building 12,000 85,000 800,000 60,000 Other: LOST TOTAL 0 12,000 85,000 800,000 60,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction Maintenance 12,000 85,000 800,000 60,000 Other TOTAL 0 12,000 85,000 800,000 60,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 16 Project Title Project Description Matching Funds Program Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 10,000 10,000 10,000 10,000 10,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 10,000 10,000 10,000 10,000 10,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction Maintenance Other 10,000 10,000 10,000 10,000 10,000 TOTAL 10,000 10,000 10,000 10,000 10,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 17 Project Title Project Description Public Landscape Initiative Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative 80,000 100,000 70,000 100,000 100,000 Municipal Building Other: Grant 50,000 TOTAL 80,000 100,000 120,000 100,000 100,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction Maintenance Other 80,000 100,000 120,000 100,000 100,000 TOTAL 80,000 100,000 120,000 100,000 100,000 Project Balance -$ -$ -$ -$ -$ 2030 - Future ROW Beautification ($50,000), Park Landscape Enhancements/Restoration ($30,000), Diseased Tree Mitigation ($10,000), Arbor Day Tree Planting ($10,000) 2028 - Future ROW Beautification ($50,000), Pine Tree Valley & Pine Tree Pond Park Open Space Restoration Grant Match ($50,000), Diseased Tree Mitigation ($10,000), Arbor Day Tree Planting ($10,000) 2029 - 80th St HWY 61 to Ideal ($50,000), West Draw Park Landscape Enhancements/Restoration ($30,000), Diseased Tree Mitigation ($10,000), Arbor Day Tree Planting ($10,000) CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026 - 80th St HWY 61 to Ideal ($50,000), Oakwood Park Restoration ($10,000), Diseased Tree Mitigation ($10,000), Arbor Day Tree Planting ($10,000) 2027 - Jamaica 100th to Hwy 61 Ramps ($50,000), Woodridge Park Woodland Restoration ($30,000), Diseased Tree Mitigation ($10,000), Arbor Day Tree Planting ($10,000) 18 Project Title Project Description Park Design and Planning Funding for design and planning of parks as development occurs. Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund 15,000 15,000 15,000 15,000 15,000 Landscape Initiative Municipal Building Other: TOTAL 15,000 15,000 15,000 15,000 15,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect 15,000 15,000 15,000 15,000 15,000 Admin/Legal Construction Maintenance Other TOTAL 15,000 15,000 15,000 15,000 15,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 19 Project Title Project description Building Locks Department 2026 - Highlands Parks 2027 - Kingston 2028 - Hamlet 2029 - Peter Thompson 2030 - Woodridge Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 35,000 35,000 35,000 35,000 35,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 35,000 35,000 35,000 35,000 35,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 35,000 35,000 35,000 35,000 35,000 Maintenance Other TOTAL 35,000 35,000 35,000 35,000 35,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 20 Project Title Project Description Picnic Shelters 2030 - Nina's Park ($30,000), Fabric Replacement: Hamlet, Highlands, Granada ($30,000) Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 60,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL - - - - 60,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 60,000 Maintenance Other TOTAL - - - - 60,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 21 Project Title Project Description Replace Playground equipment 2029 - Hemingway and North Ideal - $150,000 2030 - Woodridge Playground Surface Replacement - $500,000 Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 150,000 500,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 0 0 0 150,000 500,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 150,000 500,000 Maintenance Other TOTAL 0 0 0 150,000 500,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 22 Project Title Project Description 2026 - Hamlet Football/Soccer, Courts and Ice Rink 2027 - Lamar Park LED & Poles 2028 - Old CG Park Sports Lighting Replacement Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 355,000 350,000 35,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 355,000 350,000 35,000 - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 355,000 350,000 35,000 Maintenance Other TOTAL 355,000 350,000 35,000 - - Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Sports Lighting 23 Project Title Project description Pavement Management 2027 - River Oaks Scenic Overlook ($100,000) 2029 - Hearthside Park Improvements ($100,000) 2030 - Pine Glen ($100,000) Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 100,000 100,000 100,000 State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building Other: Donations TOTAL 0 100,000 0 100,000 100,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 100,000 100,000 100,000 Maintenance Other TOTAL 0 100,000 0 100,000 100,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 24 Project Title Project description Department 2029 - East Ravine Neighborhood or 100th Street Park Development (development driven) Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund 800,000 700,000 500,000 500,000 500,000 Landscape Initiative Municipal Building Other: TOTAL 800,000 700,000 500,000 500,000 500,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 800,000 700,000 500,000 500,000 500,000 Maintenance Other TOTAL 800,000 700,000 500,000 500,000 500,000 Project Balance -$ -$ -$ -$ -$ 2030 - East Ravine Neighborhood or 100th Street Park Development (development driven) CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Neighborhood Park Development 2028 - East Ravine Neighborhood or 100th Street Park Development (development driven) 25 Project Title Project Description Bike Park 2026 - Jump Line Improvements ($75,000) Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 75,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 75,000 0 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 75,000 Maintenance Other TOTAL 75,000 0 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 26 Project Title Project description Dunes Park 2027 - Infrastructure, Parking Lot, Trails, Boat Ramp Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 2,000,000 1,500,000 7,000,000 State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building Other: Grants 5,000,000 500,000 TOTAL 0 7,000,000 2,000,000 7,000,000 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect 1,400,000 400,000 1,400,000 Admin/Legal Construction 5,600,000 1,600,000 5,600,000 Maintenance Other TOTAL 0 7,000,000 2,000,000 7,000,000 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 27 Project Title Project Description Hamlet Park 2026 - Skate Park Surface Replacement 2027 - Picnic Shelter Replacement ($50,000), Skate Park Equipment ($300,000) Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 100,000 350,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 100,000 350,000 - - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 100,000 350,000 Maintenance Other TOTAL 100,000 350,000 - - - Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 28 Project Title Project Description Highlands Park Tennis Court Replacement Department Facilities Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 100,000 Park Trust Fund Landscape Initiative Municipal Building Other: Project Description TOTAL - - 100,000 - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 100,000 Maintenance Other TOTAL - - 100,000 - - Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 29 Project Title Project Description Kingston Park 2027 - Building Replacement ($5,000,000) - bond in 2027 Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 5,000,000 State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 0 5,000,000 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 5,000,000 Maintenance Other TOTAL 0 5,000,000 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 30 Project Title Lamar Park Project Description 2027 - Roof Replacement Note-Actually replaced in 2025. This can be deleted in future CIP. Department Facilities Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 10,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 0 10,000 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 10,000 Maintenance Other TOTAL 0 10,000 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 31 Project Title Project Description Peter Thompson Park Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement fund 315,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 0 0 315,000 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 315,000 Maintenance Other TOTAL 0 0 315,000 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 32 Project Title Project Description Pine Coulee 2027 - Court Replacement Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 20,000 Park Trust Fund Landscape Initiative Municipal Building Other: Land Sale TOTAL 0 20,000 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 20,000 Maintenance Other TOTAL 0 20,000 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 33 Project Title Project description Pine Tree Pond Park 2029 - Pine Tree Pond Court Replacement Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund Park Trust Fund 500,000 30,000 Landscape Initiative Municipal Building Other: 3M Settlement TOTAL 0 0 500,000 30,000 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect 50,000 Admin/Legal Construction 450,000 30,000 Maintenance Other TOTAL 0 0 500,000 30,000 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 34 Project Title Project Description Pine Tree Valley Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 150,000 Park Trust Fund Landscape Initiative Municipal Building Other: Utility Fund TOTAL 0 0 0 0 150,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 150,000 Maintenance Other TOTAL 0 0 0 0 150,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 35 Project Title Project description Woodridge Department Parks Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State/Other Government Units Park Improvement Fund 150,000 Park Trust Fund Landscape Initiative Municipal Building Other: TOTAL 0 0 0 0 150,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect Admin/Legal Construction 150,000 Maintenance Other TOTAL 0 0 0 0 150,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2030 - Court Resurfacing 36 Project Title Project Description Ice Arena Capital Projects 2026 - Zamboni Replacement ($145,000) Department 2028 - Zamboni Replacement ($145,000) Parks 2029 - Commons Area Rooftop HVAC Unit ($75,000), Steel Roof ($500,000) 2030 - Office/Mezzanine Furnace Replacement ($60,000) Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 1,500,000 State/Other Government Units Park Improvement Fund Park Trust Fund Landscape Initiative Municipal Building 145,000 125,000 145,000 575,000 60,000 TOTAL 145,000 1,625,000 145,000 575,000 60,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements Engineering/Architect 200,000 Admin/Legal Construction 145,000 1,425,000 145,000 575,000 60,000 Maintenance Other TOTAL 145,000 1,625,000 145,000 575,000 60,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2027 - Locker Room 7/8/9 Furnace ($10,000), Floor Scrubber ($15,000), Water Treatment System ($100,000), Office & Interior Remodel ($1,500,000), bond for remodel in 2028 37 -This Page Intentionally left Blank - 38 ALL TRANSPORTATION AND PUBLIC WORKS PROJECTS Funding Sources 2026 2027 2028 2029 2030 Tax Levy -$ -$ -$ -$ -$ Bonded Debt 2,420,000$ 5,566,250$ 6,243,750$ 7,245,000$ 8,834,000$ State of Minnesota/MSA 10,309,000$ -$ 1,800,000$ -$ 5,875,000$ Washington County 2,250,000$ 2,971,250$ 1,098,750$ -$ 4,075,000$ Federal/Grant Funding 8,352,000$ 19,000,000$ 19,000,000$ -$ 120,433,000$ Area Funds 1,293,000$ 3,220,000$ 3,220,000$ 784,000$ 1,748,000$ Utility Funds 2,381,400$ 2,339,500$ 2,320,000$ 2,079,000$ 1,605,000$ Assessments/Developer Fees 5,011,600$ 1,200,000$ 2,520,000$ 1,869,000$ 1,756,000$ Other:38,808,192$ 32,259,192$ 14,691,830$ 6,634,766$ 2,392,000$ TOTAL 70,825,192 66,556,192 50,894,330 18,611,766 146,718,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation 845,000$ 4,845,000$ -$ -$ 250,000$ Engineering/Architect 14,286,059$ 10,000,039$ 7,916,766$ 3,655,754$ 23,921,000$ Admin/Legal -$ -$ -$ -$ 104,000$ Construction 53,436,133$ 49,349,153$ 40,505,564$ 12,369,012$ 119,738,000$ Maintenance 1,239,000$ 1,292,000$ 1,348,000$ 1,407,000$ 1,466,000$ Other 1,019,000$ 1,070,000$ 1,124,000$ 1,180,000$ 1,239,000$ TOTAL 70,825,192 66,556,192 50,894,330 18,611,766 146,718,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 39 Project Title Project Description Roadway Maintenance Annual maintenance including: 4 miles of mill & overlay Concrete removal & replacement (2% per year) Department 6 miles trail maintenance (crack seal/fog seal) Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 3,000 14,000 10,000 11,000 15,000 Assessments/Developer Fees Other: Maintenance Fund 1,976,000 2,064,000 2,173,000 2,281,000 2,392,000 TOTAL 1,979,000 2,078,000 2,183,000 2,292,000 2,407,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 166,000 174,000 183,000 192,000 202,000 Admin/Legal Sealcoating Contract/Rock Maintenance 794,000 834,000 876,000 920,000 966,000 Other: Mill and Overlay 1,019,000 1,070,000 1,124,000 1,180,000 1,239,000 TOTAL 1,979,000 2,078,000 2,183,000 2,292,000 2,407,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 40 Project Title Project Description Pavement Management (includes ADA improvements) Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 2,420,000 2,945,000 2,668,000 4,485,000 7,036,000 State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 995,000 563,000 1,098,000 1,581,000 1,090,000 Assessments/Developer Fees Other: TOTAL 3,415,000 3,508,000 3,766,000 6,066,000 8,126,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 683,000 702,000 753,000 1,213,000 1,625,000 Admin/Legal Construction 2,732,000 2,806,000 3,013,000 4,853,000 6,501,000 Maintenance Other TOTAL 3,415,000 3,508,000 3,766,000 6,066,000 8,126,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2026 - Thompson Grove Estates 11th Add, south part Woodridge Park Add (W of Jamaica) 2029 - Thompson Grove Estates and Hillside Trail 41 Project Title Project Description 80th Street Reconstruction Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA 8,221,000 Washington County Federal/Grant Funding 5,000,000 Area Funds Utility Funds 50,500 Assessments/Developer Fees 2,211,600 Other: TIF 1-12 1,807,000 TOTAL 17,290,100 0 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 3,458,020 Admin/Legal Construction 13,832,080 Maintenance Other TOTAL 17,290,100 0 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM pavement replacement, spot curb replacement, signal replacement and upgrades, ADA improvements, landscaping, trail replacement and MnDOT interchange improvements. State of Minnesota/MSA incldues $2,934,868 in City MSA and $5,286,026 in MnDOT/County funding for interchange 42 Project Title Project Description Installation of a roundabout at 80th Street and Keats Avenue, County led project Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA 2,000,000 Washington County 2,000,000 Federal/Grant Funding Area Funds Utility Funds Assessments/Developer Fees Other: ED Trust/Park Trust ($130k) TOTAL 4,000,000 - - - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 800,000 Admin/Legal Construction 3,200,000 Maintenance Other TOTAL 4,000,000 - - - - Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 80th Street & Keats Avenue Roundabout 43 Project Title Project Description CSAH 19 and TH 61 $680,000 in engineering costs in 2025, $430,000 City/$250,000 County Department Public Works 2030 - Reconstruction/realignment of bridge/overpass over Highway 61 at County Rd 19 Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 2,621,250 198,750 State of Minnesota/MSA 4,075,000 Washington County 250,000 2,971,250 728,750 4,075,000 Federal/Grant Funding 19,000,000 19,000,000 14,033,000 Area Funds 3,150,000 3,150,000 Utility Funds Assessments/Developer Fees 717,000 Other: ED Trust 430,000 TOTAL 680,000 27,742,500 23,077,500 0 22,900,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation 4,845,000 Engineering/Architect 680,000 2,395,000 2,575,000 Admin/Legal Construction 20,502,500 20,502,500 22,900,000 Maintenance Other TOTAL 680,000 27,742,500 23,077,500 0 22,900,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2026-2028 - County 19A & 100th Street Realignment Project 44 Project Title Project description Reconstruct Harkness Avenue to an urban section with utilities, from Oakwood Park to the north Hardwood Ave intersection. Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 938,000 State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds 1,456,000 Utility Funds Assessments/Developer Fees 768,000 Other: TOTAL 0 0 0 0 3,162,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation 250,000 Engineering/Architect 0 728,000 Admin/Legal 104,000 Construction 2,080,000 Maintenance Other TOTAL 0 0 0 0 3,162,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 45 Project Title Project Description Jamaica Ave Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 3,000,000 State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds Assessments/Developer Fees Other: TOTAL 0 0 3,000,000 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction 3,000,000 Maintenance Other TOTAL 0 0 3,000,000 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2028 - Cost share of reconstruction of Jamaica Ave from Rose of Sharon Church to Military Road to 46 Project Title Project Description Ravine Parkway 2026 - Ravara Trails (Tank/Brier) 2027 - 2029: Tank North, Tank South, Geis, Goebel 2030 - Kemp Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA 200,000 Washington County Federal/Grant Funding Area Funds Utility Funds Assessments/Developer Fees 2,800,000 1,200,000 1,000,000 1,000,000 Other: Interfund Loan 400,000 TOTAL 3,200,000 1,200,000 1,000,000 1,000,000 200,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 1,100,000 400,000 300,000 300,000 30,000 Admin/Legal Construction 2,100,000 800,000 700,000 700,000 170,000 Maintenance Other TOTAL 3,200,000 1,200,000 1,000,000 1,000,000 200,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 47 Project Title Department Public Works *includes 8% inflation adjustment above Feasibility Report costs * Money to be used by August 31, 2030 Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt 377,000 2,760,000 860,000 State of Minnesota/MSA 1,000,000 Washington County Federal/Grant Funding 3,000,000 Area Funds 1,223,000 714,000 222,000 Utility Funds Assessments/Developer Fees 1,150,000 869,000 271,000 Other: TOTAL 4,223,000 - 2,527,000 4,343,000 1,353,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocati 845,000 Engineering/Architect 506,000 1,080,000 336,000 Admin/Legal Construction 3,378,000 2,021,000 3,263,000 1,017,000 Maintenance Other Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Cottage View Project Description 2026 - Phase 1 - EPD to first intersection & hotel access 2028 - Phase 2 - First access to Roundabout 2029 - Phase 3 - Roundabout to CSAH 19 2030 - Phase 4 - North of Roundabout 48 Project Title Project Description 103rd St Railroad Bridge 2026 & 2027 - 103rd St Bridge Feasibility Study 2028 - 103rd St Bridge Preliminary & Final Design 2030 - Reconstruct 103rd Street railroad bridge Department Post 2030 - Grey Cloud Trail Bridge Reconstruction Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA 800,000 1,600,000 Washington County Federal/Grant Funding 6,400,000 Area Funds Utility Funds Assessments/Developer Fees Other: Future Projects 150,000 150,000 TOTAL 150,000 150,000 800,000 0 8,000,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 150,000 150,000 800,000 1,000,000 Admin/Legal Construction 7,000,000 Maintenance Other TOTAL 150,000 150,000 800,000 0 8,000,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 49 Project Title Project Description Traffic Signals 2028 - 80th/Jamaica, Keats/Indian Blvd Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County 370,000 Federal/Grant Funding Area Funds Utility Funds 740,000 Assessments/Developer Fees 370,000 Other: 1-12 TIF District TOTAL 0 0 1,480,000 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 296,000 Admin/Legal Construction 1,184,000 Maintenance Other TOTAL 0 0 1,480,000 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 50 Project Title Project Description East Ravine District Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds 50,000 50,000 50,000 50,000 50,000 Utility Funds Assessments/Developer Fees Other: TOTAL 50,000 50,000 50,000 50,000 50,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction 50,000 50,000 50,000 50,000 50,000 Maintenance Other TOTAL 50,000 50,000 50,000 50,000 50,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM As residential development occurs in the East Ravine, various infrastructure will be constructed to support the new housing. This infrastructure will be paid for by developers either through City financed construction supported by assessments or by Developer constructed of same. 51 Project Title Project Description Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 1,000,000 Assessments/Developer Fees Other: Newport TOTAL - 1,000,000 - - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 170,000 Admin/Legal Construction 830,000 Maintenance Other TOTAL - 1,000,000 - - - Project Balance -$ -$ -$ -$ -$ 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2027 - Pine Hill Water TowerWater Tower Painting/Rehab 52 Project Title Project Description Annual well maintenance Each year a well is 'pulled' for inspection and repair of the pump and other vital parts. Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 90,000 93,000 96,000 99,000 102,000 Assessments/Developer Fees Other: TOTAL 90,000 93,000 96,000 99,000 102,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction Maintenance 90,000 93,000 96,000 99,000 102,000 Other TOTAL 90,000 93,000 96,000 99,000 102,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 53 Project Title Project Description SCADA & Well Upgrades 2026 - IZWTP Watermain Replacement ($476,900) and Wells 3/10 Electrical Upgrades($420,000) 2027 - IZWTP Well SCADA Upgrades Department Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 887,900 304,500 Assessments/Developer Fees Other: Roadway Maintenance TOTAL 887,900 304,500 0 0 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction 887,900 304,500 Maintenance Other TOTAL 887,900 304,500 0 0 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 54 Project Title 3M Settlement Implementation Department Project Description 2025-2029 - Intermediate Zone Water Treatment Plant - $90,135,600 2026 - Intermediate Zone Raw Water Line - $3,000,000 2026 - Well 1 & Well 2 Decommissioning - $1,000,000 2029 - Wells 3, 7, and 8 Interim Treatment Plant Decommissioning- $1,500,000 Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds Assessments/Developer Fees Other: 3M Settlement 34,045,192 30,045,192 12,518,830 4,003,766 TOTAL 34,045,192 30,045,192 12,518,830 4,003,766 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 6,809,039 6,009,039 2,503,766 800,754 Admin/Legal Construction 27,236,153 24,036,153 10,015,064 3,203,012 Maintenance Other TOTAL 34,045,192 30,045,192 12,518,830 4,003,766 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 55 Project Title Project description Water System 2030 - Water Softening ($70,000,000 Intermediate Plant; $30,000,000 Low Plant) Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding 100,000,000 Area Funds Utility Funds Assessments/Developer Fees Other: TOTAL 0 0 0 0 100,000,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 20,000,000 Admin/Legal Construction 80,000,000 Maintenance Other TOTAL 0 0 0 0 100,000,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 56 Project Title Project Description Trunk Utility Oversizing Trunk oversizing of water and sewer facilities as part of development projects Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds 20,000 20,000 20,000 20,000 20,000 Utility Funds Assessments/Developer Fees Other: TOTAL 20,000 20,000 20,000 20,000 20,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction 20,000 20,000 20,000 20,000 20,000 Maintenance Other TOTAL 20,000 20,000 20,000 20,000 20,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 57 Project Title Project Description Stormwater maintenance Annual costs of pond and structure maintenance for City Stormwater system. Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 205,000 210,000 217,000 224,000 230,000 Assessments/Developer Fees Other: TOTAL 205,000 210,000 217,000 224,000 230,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction Maintenance 205,000 210,000 217,000 224,000 230,000 Other TOTAL 205,000 210,000 217,000 224,000 230,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM 58 Project Title Project Description Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 50,000 52,000 53,000 55,000 56,000 Assessments/Developer Fees Other: TOTAL 50,000 52,000 53,000 55,000 56,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction Maintenance 50,000 52,000 53,000 55,000 56,000 Other TOTAL 50,000 52,000 53,000 55,000 56,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 5 YEAR CAPITAL IMPROVEMENT BUDGET 2026-2030 CAPITAL IMPROVEMENT PROGRAM Annual sewer line maintenance/spot sliplining 59 Project Title Project Description Streetlight system improvements Annual cost to refurbish and upgrade the City Streetlight infrastructure. Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds 100,000 103,000 106,000 109,000 112,000 Assessments/Developer Fees Other: TOTAL 100,000 103,000 106,000 109,000 112,000 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect Admin/Legal Construction Maintenance 100,000 103,000 106,000 109,000 112,000 Other TOTAL 100,000 103,000 106,000 109,000 112,000 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 60 Project Title Project description Pedestrian Improvements Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA Washington County Federal/Grant Funding Area Funds Utility Funds Assessments/Developer Fees Other: Grants 350,000 TOTAL 0 0 0 350,000 0 Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 70,000 Admin/Legal Construction 280,000 Maintenance Other TOTAL 0 0 0 350,000 0 Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM 2029 - Install Pedestrian Crossing Infrastructure, including Rectangular Rapid Flashing Beacon and marked crosswalk: 80th Street at Pinetree Valley Park and Pinetree Pond Park ($300,000), and 61 Project Title Project Description Develop a Safe Street and Roads for All plan Department Public Works Funding Sources 2026 2027 2028 2029 2030 Tax Levy Bonded Debt State of Minnesota/MSA 88,000 Washington County Federal/Grant Funding 352,000 Area Funds Utility Funds Assessments/Developer Fees Other: TOTAL 440,000 - - - - Project Expenses 2026 2027 2028 2029 2030 Land/Easements/Utility Relocation Engineering/Architect 440,000 Admin/Legal Construction Maintenance Other TOTAL 440,000 - - - - Project Balance -$ -$ -$ -$ -$ CITY OF COTTAGE GROVE 2026-2030 CAPITAL IMPROVEMENT PROGRAM Safe Streets and Roads for All (SS4A) 62 -This Page Intentionally left Blank - 63 Current Year CIP Last Year CIP points Location Description map Maintenance Replace New Total 2026 2026 Parks Funds used to match donations for park projects 10,000 10,000 2026 2026 Public Landscape initiative See Project Sheet Detail 80,000 80,000 2026 2026 Parks Park design & master planning 15,000 15,000 2026 2026 Parks Annual addition of auto. locks on park buildings 35,000 35,000 2026 2026 2026 2025 2026 2027 2026 2026 Hamlet Park Skate park surface replacement PR10 100,000 100,000 2026 Bike Park Jump line improvements PR30 75,000 75,000 2026 2026 Ice Arena See Project Sheet Detail PR9 145,000 145,000 2026 2026 2026 Roadway & trail maintenance Streets, sidewalk/curb replacement, & trails 1,979,000 1,979,000 2026 2025 Thompson Grove Estates 11th Add, south part Woodridge PW31 3,415,000 3,415,000 2026 2026 511 CSAH 19 and TH 61 100th Street Extension PW4 680,000 680,000 2026 2028 Ravine Parkway-Shoppes at CV PW12 4,223,000 4,223,000 2026 2026 2026 2026 2026 2026 Ravine Parkway Ravara Trails (Tank/Brier)PW20 3,200,000 3,200,000 2026 2025 Safe Streets and Roads for all Develop plan 440,000 440,000 2026 2026 3M Settlement Implementation Intermediate zone water treatment plant PW32 34,045,192 34,045,192 2026 2026 East Ravine District City share of development infrastructure 50,000 50,000 2026 2026 2026 Trunk oversizing Utilities 20,000 20,000 2026 2026 Well Maintenance Pull well 90,000 90,000 2026 SCADA & Well upgrades IZWTP watermain replacement & Well 3/10 887,900 887,900 2026 2026 Various sewer Spot replacement/slip lining 50,000 50,000 2026 2026 various stormwater Storm water maintenance 205,000 205,000 2026 2026 various streetlights System improvements 100,000 100,000 3,524,033 22,210,100 46,918,192 72,652,325 64 2026 CIP Project Locations Cottage Grove, MN Date: 10/8/2024 ± IN W O O D A V E 100TH ST LA M A R A V E LE H I G H R D 80TH ST IN N O V A T I O N R D KI M B R O A V E 70TH ST (C.S.A.H. 22) 85TH ST 65TH ST (CR 74) 100TH ST 103RD ST 80TH ST80TH ST HILLSIDE TRAIL HI N T O N A V E JA M A I C A AV E HA D L E Y A V E JA M A I C A A V E ID E A L A V E 77TH ST JA M A I C A A V E 85TH ST HA D L E Y A V E E PT D O U G L A S R D E PT D O U G L A S R D KE A T S A V E N U E S (C . S . A . H . 1 9 ) HA R K N E S S A V E 90TH ST GREY C L O U D T R L JA M A I C A A V E INDIAN BLVD STA T EHWY 6 1 KE A T S A V E (C . S . A . H 19. ) 110TH ST 90TH ST HA R D W O O D AV E STA T EHWY 6 1 STAT E H W Y 6 1 95TH ST 70TH ST (CSAH 20) MA N N I N G AV E ( S T A T E HW Y 9 5 ) PR10 PW24 PW12 PW4PR26 PR30 PW18 PW20 PW19PR9 PW31 PW32 PR27 FA3 FA3 0 1 20.5 Miles CIP Projects Parks and Recreation Public Works Facilities 65 Current Year CIP Last Year CIP points Location Description map Maintenance Replace New Total 2027 2027 Parks 10,000 10,000 2027 2027 Public Landscape initiative 100,000 100,000 2027 2027 Parks 15,000 15,000 2027 2027 Parks 35,000 35,000 2027 2027 Parks PR13 350,000 350,000 2027 2026 Still Ponds PR16 500,000 500,000 2027 2027 2027 River Oaks scenic overlook PR20 100,000 100,000 2027 2027 Hamlet Park PR10 50,000 50,000 2027 2026 Hamlet Park PR10 300,000 300,000 2027 2027 Lamar Park PR13 10,000 10,000 2027 2026 2027 2027 2027 2027 2027 2027 2027 2027 2027 Funds used to match donations for park projects See Project Sheet Detail Park design & master planning Annual addition of auto. locks on park buildings Sports lighting improvements - Lamar Park Neighborhood park development Neighborhood park development Scenic overlook Shelter replacement Skate park equipment Roof-Replaced 2025 remove from future CIP Building replacement Court replacement See Project Sheet Detail Office & Interior remodel Major maintenance projects Water heater Infrastrucutre, Parking lot, trails, boat ramp PR17 7,000,000 7,000,000 2027 2027 2027 2027 2027 2026 511 CSAH 19 and TH 61 100th Street Extension 2027 2027 Ravine Parkway Tank North, Tank South, Geis, Goebel PW23 1,200,000 1,200,000 2027 2027 3M Settlement Implementation Intermediate Zone Water Treatment Plant PW32 30,045,192 30,045,192 2027 2027 Pine Hill Water tower painting PW37 1,000,000 1,000,000 2027 2027 East Ravine District City share of development infrastructure 50,000 50,000 2027 2027 2027 Trunk oversizing Utilities 20,000 20,000 2027 2027 Well Maintenance Pull well 93,000 93,000 2027 SCADA & Well upgrades IZWTP Well SCADA Upgrades 304,500 304,500 2027 2027 Various sewer Spot replacement/slip lining 52,000 52,000 2027 2027 Various stormwater Storm water maintenance 210,000 210,000 2027 2027 Various streetlights System improvements 103,000 103,000 66 2027 CIP Project Locations Cottage Grove, MN Date: 10/8/2024 ± IN W O O D A V E 100TH ST LA M A R A V E LE H I G H R D 80TH ST IN N O V A T I O N R D KI M B R O A V E 70TH ST (C.S.A.H. 22) 85TH ST 65TH ST (CR 74) 100TH ST 103RD ST 80TH ST80TH ST HILLSIDE TRAIL HI N T O N A V E JA M A I C A A V E HA D L E Y A V E JA M A I C A A V E ID E A L A V E 77TH ST JA M A I C A A V E 85TH ST HA D L E Y A V E E PT D O U G L A S R D E PT D O U G L A S R D KE A T S A V E N U E S (C . S . A . H . 1 9 ) HA R K N E S S A V E 90TH ST GREY C L O U D T R L JA M A I C A A V E INDIAN BLVD STA T E HWY 6 1 KE A T S A V E (C . S . A . H 1 9 . ) 110TH ST 90TH ST HA R D W O O D AV E STA T EHWY 6 1 STAT E H W Y 6 1 95TH ST 70TH ST (CSAH 20) MA N N I N G AV E ( S T A T E HW Y 9 5 ) PR13 PR10 PW24 PW4 PR19 PR4 PR12 PR9 PR17 PR20 PW32 PW33 PW33 PW23 FA3 FA3 PW37 PR16 FA4 0 1 20.5 Miles CIP Projects Parks and Recreation Public Works Facilities 67 Current Year CIP Last Year CIP points Location Description map Maintenance Replace New Total 2028 2028 Parks Funds used to match donations for park projects 10,000 10,000 2028 2028 Public Landscape initiative See Project Sheet Detail 120,000 120,000 2028 2028 Parks Park design & master planning 15,000 15,000 2028 2028 Parks Annual addition of auto. locks on park buildings 35,000 35,000 2028 2028 Parks Sports lighting replacement 35,000 35,000 2028 2028 2028 2028 2028 2028 Peter Thompson Park Rink boards and sport courts PR24 315,000 315,000 2028 2025 2028 2028 Ice Arena See Project Sheet Detail PR9 145,000 145,000 2028 2028 2028 2028 2028 2028 2028 2028 PW35 3,766,000 3,766,000 2028 2027 511 CSAH 19 and TH 61 100th Street Extension PW4 23,077,500 23,077,500 2028 2028 2028 2028 Ravine Parkway Tank North, Tank South, Geis, Goebel PW23 1,000,000 1,000,000 2028 2028 Ravine Parkway-Shoppes at CV Phase 2-First access to roundabout PW12 2,527,000 2,527,000 2028 2027 3M Settlement Implementation Intermediate Zone Water Treatment Plant PW32 12,518,830 12,518,830 2028 2026 Traffic Signal 80th & Jamaica PW15 740,000 740,000 2028 2026 Traffic Signal CSAH 19 & Indian Blvd.PW16 740,000 740,000 2028 2028 East Ravine District City share of development infrastructure 50,000 50,000 2028 2028 2028 Trunk oversizing Utilities 20,000 20,000 2028 2028 Well Maintenance Pull well 96,000 96,000 2028 2028 Various sewer Spot replacement/slip lining 53,000 53,000 2028 2028 various stormwater Storm water maintenance 217,000 217,000 2028 2028 various streetlights System improvements 106,000 106,000 2,976,214 21,264,830 30,834,500 55,075,544 68 2028 CIP Project Locations Cottage Grove, MN ± Date: 10/16/2025 IN W O O D AV E 100TH ST LA M A R A V E LE H I G H R D 80TH ST IN N O V A T I O N R D KI M B R O A V E 70TH ST (C.S.A.H. 22) 85TH ST 65TH ST (CR 74) 100TH ST 103RD ST 80TH ST80TH ST HILLSIDE TRAIL HI N T O N A V E JA M A I C A A V E HA D L E Y A V E JA M A I C A A V E ID E A L A V E 77TH ST JA M A I C A A V E 85TH ST HA D L E Y A V E E PT D O U G L A S R D E PT D O U G L A S R D KE A T S A V E N U E S (C . S . A . H . 1 9 ) HA R K N E S S A V E 90TH ST GREY C L O U D T R L JA M A I C A A V E INDIAN BLVD STA T EHWY 6 1 KE A T S A V E (C . S . A . H 19. ) 110TH ST 90TH ST HA R D W O O D AV E STA T EHWY 6 1 STAT E H W Y 6 1 95TH ST 70TH ST (CSAH 20) MA N N I N G AV E ( S T A T E HW Y 9 5 ) PW27 PR16 PW24 PR16 PW12 PW4 PR28 PW15 PW16 PR9 PR17 PR22 PR24 PW32 PW35 PW23 FA3 FA3 FA4 0 1 20.5 Miles CIP Projects Parks and Rec Public Works Facilities 69 Current Year CIP Last Year CIP points Location Description map Maintenance Replace New Total 2029 2029 Parks Funds used to match donations for park projects 10,000 10,000 2029 2029 Public Landscape initiative See Project Sheet Detail 100,000 100,000 2029 2029 Parks Park design & master planning 15,000 15,000 2029 2029 Parks Annual addition of auto. locks on park buildings 35,000 35,000 2028 2028 Hearthside Park Park improvements as part of pavement mgmt.PR3 100,000 100,000 2028 2028 Hemingway & North Ideal Replace playground equipment PR29 150,000 150,000 2029 2029 2029 2029 2029 2029 Ice Arena See Project Sheet Detail PR9 575,000 575,000 2029 2028 2029 2029 2029 2029 Roadway & trail maintenance Streets, sidewalk/curb replacement, & trails 2,292,000 2,292,000 2029 2029 2029 2029 Ravine Parkway Tank North, Tank South, Geis, Goebel PW23 1,000,000 1,000,000 2029 2029 2027 2027 3M Settlement Implementation Intermediate Zone Water Treatment Plant PW32 4,003,766 4,003,766 2029 2029 Pedestrian Improvements See Project Sheet Detail 350,000 350,000 2029 2029 East Ravine District City share of development infrastructure 50,000 50,000 2029 2029 Trunk oversizing Utilities 20,000 20,000 2029 2029 Well Maintenance Pull well 99,000 99,000 2029 2029 Various sewer Spot replacement/slip lining 55,000 55,000 2029 2029 various stormwater Storm water maintenance 224,000 224,000 2029 2029 various streetlights System improvements 109,000 109,000 2,998,900 11,724,766 13,423,000 28,146,666 70 2029 CIP Projects Cottage Grove, MN ± Date: 10/16/2025 IN W O O D A V E 100TH ST LA M A R A V E LE H I G H R D 80TH ST IN N O V A T I O N R D KI M B R O A V E 70TH ST (C.S.A.H. 22) 85TH ST 65TH ST (CR 74) 100TH ST 103RD ST 80TH ST80TH ST HILLSIDE TRAI L HI N T O N A V E JA M A I C A A V E HA D L E Y A V E JA M A I C A A V E ID E A L A V E 77TH ST JA M A I C A A V E 85TH ST HA D L E Y A V E E PT D O U G L A S R D E PT D O U G L A S R D KE A T S A V E N U E S (C . S . A . H . 1 9 ) HA R K N E S S A V E 90TH ST GREY C L O U D T R L JA M A I C A A V E INDIAN BLVD STA T EHWY 6 1 KE A T S A V E (C . S . A . H 19. ) 110TH ST 90TH ST HA R D W O O D AV E STA T EHWY 6 1 STAT EHWY 6 1 95TH ST 70TH ST (CSAH 20) MA N N I N G AV E ( S T A T E HW Y 9 5 ) PR16 PR16 PW12 PR28PR3 PR9 PR17 PW32 PW36 PR29 PR29 PW23 FA3 FA4 0 1 20.5 Miles CIP Projects Parks and Rec Public Works Facilities 71 Current Year CIP Last Year CIP points Location Description map Maintenance Replace New Total 2030 Parks Funds used to match donations for park projects 10,000 10,000 2030 Public Landscape initiative See Project Sheet Detail 100,000 100,000 2030 Parks Park design & master planning 15,000 15,000 2030 Parks Annual addition of auto. locks on park buildings 35,000 35,000 2030 Nina, Hamlet, Highlands, Granada Picnic shelter replacement 60,000 60,000 2030 Woodridge Playground surface replacement PR32 500,000 500,000 2030 Woodridge Court resurfacing PR32 150,000 150,000 2030 Pine Glen Park improvements PR34 100,000 100,000 2030 Pine Tree Valley Ice rink board replacement PR33 150,000 150,000 2030 2030 Ice Arena See Project Sheet Detail PR9 60,000 60,000 2029 2029 2030 Roadway & trail maintenance Streets, sidewalk/curb replacement, & trails 2,407,000 2,407,000 2030 2030 511 CSAH 19 and TH 61 Realignment of bridge (see project sheet)PW26 22,900,000 22,900,000 2030 Ravine Parkway Kemp Property PW23 200,000 200,000 2030 2030 2029 2030 2029 2030 East Ravine District City share of development infrastructure 50,000 50,000 2030 Trunk oversizing Utilities 20,000 20,000 2030 Well Maintenance Pull well 102,000 102,000 2030 Various sewer Spot replacement/slip lining 56,000 56,000 2030 various stormwater Storm water maintenance 230,000 230,000 2030 various streetlights System improvements 112,000 112,000 2030 2029 Water softening Federal/Grant Funding 100,000,000 100,000,000 3,355,496 43,208,000 102,343,000 148,906,496 72 ± Date: 10/16/2025 2030 CIP Projects 0 21 Miles IN W O O D A V E 100TH ST LA M A R A V E LE H I G H R D 80TH ST IN N O V A T I O N RD KI M B R O A V E 70TH ST (C.S.A.H. 22) 85TH ST 65TH ST (CR 74) 100TH ST 103RD ST 80TH ST80TH ST HILLSIDE TRAIL HI N T O N A V E JA M A I C A A V E HA D L E Y A V E JA M A I C A A V E ID E A L A V E 77TH ST JA M A I C A A V E 85TH ST HA D L E Y A V E E PT DOU G L A S R D E PT D O U G L A S R D KE A T S A V E N U E S (C . S . A . H . 1 9 ) HA R K N E S S A V E 90TH ST GREYCLOU D TRL JA M A I C A A V E INDIAN BLVD W PT DOU G L A S R D STA T EHWY 6 1 KE A T S A V E (C . S . A . H 19. ) 110TH ST 90TH ST HA R D W O O D AV E STA T EHWY 6 1 STAT EHWY 6 1 95TH ST 70TH ST (CSAH 20) MA N N I N G AV E ( S T A T E HW Y 9 5 ) PR16 PW24 PR16 PW12 PW4 PR33PW22 PW23 PR9 PW26 FA3 FA3 FA4 PR32 PR34 PW39 CIP Projects Parks and Rec Public Works Facilities 73 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Aggregate tax 38,775$ 20,314$ 22,000$ 22,000$ 22,000$ 22,000$ 22,000$ 22,000$ Grant Funds Franchise fees 860,203 2,071,626 1,994,400 2,130,000 2,200,000 2,244,000 2,289,000 2,335,000 Investment Interest 9,928 32,435 10,000 10,000 10,000 20,100 21,800 22,600 Charges for services 54,121 45,300 - - - - - - Developer charges 34,624 1,720 - - - - - - Total Revenue 997,651 2,171,395 2,026,400 2,162,000 2,232,000 2,286,100 2,332,800 2,379,600 EXPENDITURES Commodities Trail fog seal, crack seal and sidewalk/curb repair 193,670 295,442 252,000 287,000 302,000 317,000 333,000 350,000 CR 74 trail 5,979 Mill and Overlay 546,614 1,203,983 970,000 1,019,000 1,070,000 1,124,000 1,180,000 1,239,000 Trail replacement 504,000 507,000 532,000 559,000 587,000 616,000 Engineering for M&O and Trail replacement 158,000 166,000 174,000 183,000 192,000 202,000 Contractual services 4,142 510 Total Expenditures 744,426 1,505,914 1,884,000 1,979,000 2,078,000 2,183,000 2,292,000 2,407,000 Other Financing Sources (uses) Transfer In/(out)- (306,728) - 3,000 14,000 10,000 11,000 15,000 Total transfers - (306,728) - 3,000 14,000 10,000 11,000 15,000 Increase (decrease) in fund balance 253,225 358,753 142,400 186,000 168,000 113,100 51,800 (12,400) FB Balance beginning of year 230,719 483,944 842,697 985,097 1,171,097 1,339,097 1,452,197 1,503,997 FB Balance end of year 483,944 842,697 985,097 1,171,097 1,339,097 1,452,197 1,503,997 1,491,597 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Road and Trailway Maintenance Fund (235) Projected Financial Position 74 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Donation 80,000 80,000 80,000 80,000 80,000 80,000 80,000 80,000 Grant Interest 14,682 21,031 11,900 - - - - - Miscellaneous 4,000 146,000 Total Revenue 94,682 101,031 95,900 226,000 80,000 80,000 80,000 80,000 EXPENDITURES Solar Panels 24,447 440,046 South Rink Rubber Floor 5,719 West Rink Cooling Tower 76,921 Water treatment system 100,000 West Rink-bleacher heat 35,000 Dehumidifier wheel replacement 35,000 Ice Arena Space Needs Study 40,000 Zamboni replacement 145,000 Locker 5/6/7-furnace 10,000 Floor scrubber 15,000 Water treatment system 100,000 Office & Interior Remodel 1,500,000 Zamboni replacement 145,000 Common areas rooftop HVAC unit 75,000 Steel roof 500,000 Office/Mezzanine Furnace 60,000 Miscellaneous 5,840 Total Expenditures 30,287 522,686 210,000 145,000 1,625,000 145,000 575,000 60,000 Other Financing Sources (uses) Bond Proceeds 1,500,000 Transfer in from Ice Operating Total other sources - - - - 1,500,000 - - - Increase (decrease) in fund balance 64,395 (421,655) (114,100) 81,000 (45,000) (65,000) (495,000) 20,000 FB Beginning balance - 64,395 (357,260) (471,360) (390,360) (435,360) (500,360) (995,360) City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Ice Arena Capital Fund (526) Projected Financial Position 75 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Charges for Services*1,132,552$ 1,214,681$ 1,251,100$ 1,283,500$ 1,322,000$ 1,361,700$ 1,402,600$ 1,444,700$ Intergovernmental - County/State 165,084 360,976 Interest 107,709 126,867 10,000 23,500 23,500 23,900 22,900 19,300 Miscellaneous 17,414 14,900 14,900 14,900 14,900 14,900 Total Revenue 1,422,759 1,702,524 1,261,100 1,321,900 1,360,400 1,400,500 1,440,400 1,478,900 EXPENDITURES Operating expenses 712,613 829,809 803,280 858,430 892,760 919,543 947,129 975,543 Pavement Management 123,033 22,125 132,000 244,700 242,000 270,000 453,400 156,700 Roadway & Trail Maintenance 1,000 4,700 3,400 3,700 5,000 Annual maintenance projects 89,842 145,882 200,000 205,000 210,000 217,000 224,000 230,000 East Point Douglas and Jamaica 714,430 EastbBooke 2nd Addition-Basins 163,219 Capital Outlay 354,439 350,000 Total Expenditures 925,488 2,229,904 1,485,280 1,309,130 1,349,460 1,409,943 1,628,229 1,367,243 OTHER FINANCING SOURCES (USES) Transfers in Transfers out (45,096) (46,450) (47,850) (49,300) (50,800) (52,300) (53,900) (55,500) Total other sources (45,096) (46,450) (47,850) (49,300) (50,800) (52,300) (53,900) (55,500) Increase (decrease) in fund balance 452,175 (573,830) (272,030) (36,530) (39,860) (61,743) (241,729) 56,157 FB Beginning balance 2,060,248 2,512,423 1,938,593 1,666,563 1,630,033 1,590,173 1,528,430 1,286,701 FB Ending balance 2,512,423 1,938,593 1,666,563 1,630,033 1,590,173 1,528,430 1,286,701 1,342,858 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Storm Water Utility Fund (230) Projected Financial Position 76 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Charges for Services*3,973,360$ 3,360,540$ 3,874,152$ 4,427,000$ 5,161,900$ 6,018,800$ 7,017,900$ 7,551,300$ Intergovernmental 67,054 124,710 98,000 232,200 243,000 250,300 100,000,000 Interest 440,954 756,885 53,748 93,700 86,300 97,500 117,200 143,700 Miscellaneous 200,700 184,280 225,600 294,000 305,000 322,700 335,800 344,600 Total Revenue 4,682,068 4,426,415 4,251,500 5,046,900 5,796,200 6,689,300 7,470,900 108,039,600 EXPENDITURES Operating expenses 2,853,085 2,924,409 3,337,540 3,717,050 3,858,800 3,974,564 4,093,801 4,216,615 Capital Equipment 65,000 147,000 215,700 224,000 45,000 Well maintenance 70,000 90,000 93,000 96,000 99,000 102,000 Water Tower Painting 1,000,000 Water tower 6,000,000 SCADA upgrades 887,900 304,500 Utilities Building Water Softening 100,000,000 Pavement management 9,202 132,000 244,700 121,000 270,000 453,400 156,700 Roadway & Trail Maintenance 1,000 4,700 3,400 3,700 5,000 80th Street Reconstruction 31,300 EPD & Jamaica 418,078 Debt Payment & Issuance Cost-Water Tower 224,100 424,375 425,750 421,500 421,625 Debt Payment & Issuance Cost-Building 328,006 500,900 592,000 591,000 590,000 591,100 592,100 Total Expenditures 2,853,085 3,679,695 10,040,440 5,853,050 6,544,375 5,575,414 5,886,501 105,539,040 OTHER FINANCING SOURCES (USES) Bond issuance 8,551,882 3,690,000 Changes in assets and liabilities (177,253) (8,163,083) Transfers in 1,000,000 224,100 424,375 425,750 421,500 421,625 Transfers out (953,493) (207,752) (209,850) (216,100) (222,600) (229,300) (236,200) (243,300) Total other sources (1,130,746) 181,047 4,480,150 8,000 201,775 196,450 185,300 178,325 Increase (decrease) in net position 698,237 927,767 (1,308,790) (798,150) (546,400) 1,310,336 1,769,699 2,678,885 Unrestricted Net Position Beginning balance 7,528,192 8,226,429 9,154,196 7,845,406 7,047,256 6,500,856 7,811,192 9,580,891 Unrestricted Net Position Ending balance 8,226,429 9,154,196 7,845,406 7,047,256 6,500,856 7,811,192 9,580,891 12,259,776 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Water Utility Fund (610) Projected Financial Position 77 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Charges for Service 3,600,456$ 3,977,841$ 4,185,870$ 4,620,200$ 5,017,600$ 5,398,900$ 5,809,200$ 6,250,700$ Interest 175,014 185,133 37,000 34,900 34,800 69,600 73,100 77,900 Interfund Interest 19,200 17,000 15,000 12,700 10,000 7,300 Grant-Met Council Miscellaneous (26,140) 12,943 2,500 90,000 89,900 89,900 89,900 89,900 Total Revenue 3,749,330 4,175,917 4,244,570 4,762,100 5,157,300 5,571,100 5,982,200 6,425,800 EXPENDITURES Operating Expenses 3,387,402 3,726,414 4,027,670 4,273,450 4,447,400 4,580,822 4,718,247 4,859,794 Pavement Management 248,941 15,925 132,000 244,700 121,000 270,000 453,400 156,700 Roadway & Trail Maintenance 1,000 4,700 3,400 3,700 5,000 Vac Truck 350,000 Sewer slip lining - spot replacement 550,000 50,000 52,000 53,000 55,000 56,000 EPD & Jamaica 3,330 80th Street Reconstruction 19,200 Debt Payment & Issuance Cost-Building 109,335 166,957 197,231 196,950 196,481 197,044 197,356 Total Expenditures 3,636,343 3,855,004 5,226,627 4,785,581 4,822,050 5,103,703 5,427,391 5,274,850 OTHER FINANCING SOURCES (USES) Bond issuance 2,850,628 Changes in assets and liabilities (2,765,574) Transfers in Transfers out (197,796) (206,303) (209,850) (216,150) (222,600) (229,300) (236,200) (243,300) Total other sources (197,796) (121,249) (209,850) (216,150) (222,600) (229,300) (236,200) (243,300) Increase (decrease) in net position (84,809) 199,664 (1,191,907) (239,631) 112,650 238,097 318,609 907,650 Unrestricted Net Position Beginning balance 5,842,533 5,757,724 5,957,388 4,765,481 4,525,850 4,638,500 4,876,597 5,195,206 Unrestricted Net Position Ending balance 5,757,724 5,957,388 4,765,481 4,525,850 4,638,500 4,876,597 5,195,206 6,102,856 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Sewer Utility Fund (620) Projected Financial Position 78 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Charges for Services 972,404$ 1,083,525$ 1,152,400$ 1,239,200$ 1,338,300$ 1,405,200$ 1,475,500$ 1,549,300$ City Supplied Poles 67,600$ 201,177$ 170,500$ 170,500$ 170,500$ 170,500$ 170,500$ 170,500$ Intergovernmental - County/State 370,000 350,000 Development Charge 370,000 Interest 20,782 26,694 5,000 5,000 5,000 9,400 (500) 2,200 Miscellaneous 18,032 76,019 20,000 35,100 35,100 35,100 35,100 35,100 Total Revenue 1,078,818 1,387,415 1,347,900 1,449,800 1,548,900 2,360,200 2,030,600 1,757,100 EXPENDITURES Operating expenses 929,424 1,193,225 987,630 1,035,920 1,065,500 1,086,810 1,108,546 1,130,717 Street Light Service Truck 230,000 Pavement management 82,527 261,000 79,000 288,000 221,000 623,000 Traffic Signal-Hardwood Ave/Hardwood Ct 700,000 Traffic Signal-80th/Jamaica 740,000 Traffic Improvement-Keats/Indian Blvd 740,000 Jamaica and 95th Intersection 13,000 Annual system improvements 100,000 100,000 103,000 106,000 109,000 112,000 Pedestrian Crossings 100,000 350,000 Total Expenditures 1,011,951 1,193,225 2,130,630 1,396,920 1,247,500 2,960,810 1,788,546 1,865,717 OTHER FINANCING SOURCES (USES) Transfers in 700,000 Transfers out (51,500) (53,000) (56,000) (57,680) (59,400) (61,200) (63,000) (64,900) Total other sources (51,500) (53,000) 644,000 (57,680) (59,400) (61,200) (63,000) (64,900) Increase (decrease) in net position 15,367 141,190 (138,730) (4,800) 242,000 (661,810) 179,054 (173,517) Unrestricted Net Position Beginning balance 374,809 390,176 531,366 392,636 387,836 629,836 (31,974) 147,080 Unrestricted Net Position Ending balance 390,176 531,366 392,636 387,836 629,836 (31,974) 147,080 (26,437) City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Street Light Utility Fund (630) Projected Financial Position 79 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL Actual ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Cell Tower Leases 486,781 607,370 533,800 486,800 496,200 513,400 535,500 554,100 Property Tax Levy 190,000 190,000 190,000 190,000 190,000 Interest 211,300 64,275 50,000 10,900 12,600 11,500 14,800 23,000 other (including donations)10,780 - Total Revenue 708,861 671,645 583,800 687,700 698,800 714,900 740,300 767,100 EXPENDITURES Belden playground equipment 70,000 Bike park-jump line improvements 75,000 Donations - matching funding 10,000 10,000 10,000 10,000 10,000 10,000 Glacial Valley 13,751 86,461 Hamlet skate park surface replacement 100,000 Hamlet-shelter replacement & skate park equip 350,000 Hamlet-Court Reconstruction 110,365 Hardwood playground equipment 70,000 Hearthside Park Improvements as part of PM 100,000 Hemmingway playground equipment 75,000 Hidden Valley as part of PM 150,000 Highland playground equipment 161,570 Highlands-Tennis court replacement 100,000 Ideal playground equipment 89,358 North Ideal playground equipment 75,000 Lamar Park-shade shelter replace. & roof replace.80,000 10,000 Sport Lighting Improvements 89,000 65,000 355,000 350,000 35,000 Picnic shelters (Nina's, Hamlet, Highlands, Granada)60,000 Peter Thompson play equipment 116,542 Peter Thompson-Building door replacement 40,000 Peter Thompson-park upgrades including roof 315,000 Pine Coulee-Court Replacement 20,000 Pine Glen & Pine Tree Park-Picnic shelter 60,000 Pine Glen 100,000 Pine Tree Pond Play equipment 79,000 Pine Tree Valley Hockey & Skate Rink 64,295 Pine Tree Valley-ice rink board replacement 150,000 River Oaks-Scenic Overlook 100,000 Woodridge shelter/hockey boards & pickleball courts 300,000 Woodridge-inclusive playground repair & sealing 60,000 Woodridge-playground surface replacement 500,000 Woodridge-court resurfacing 150,000 West Draw, Granada & Nina Park play equipment 242,928 West Draw Park Shelter 40,532 Automatic locks on park buildings 35,000 35,000 35,000 35,000 35,000 35,000 Miscellaneous 95,519 20,004 Total Expenditures 922,879 631,446 1,140,000 575,000 5,875,000 495,000 295,000 1,005,000 OTHER FINANCING SOURCES (USES) Bond proceeds 5,000,000 Transfer (to) from pavement management 150,000 100,000 100,000 100,000 Transfer (to) from park trust Total other sources - - 150,000 - 5,100,000 - 100,000 100,000 Increase (decrease) in fund balance (214,018) 40,199 (406,200) 112,700 (76,200) 219,900 545,300 (137,900) FB Beginning balance 1,309,704 1,095,686 1,135,885 729,685 842,385 766,185 986,085 1,531,385 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Park Improvement Fund (515) Projected Financial Position 80 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Intergovernmental 1,000,000$ -$ 350,000$ -$ -$ 500,000$ -$ -$ Intergovernmental-3M Settlement 678,000$ Park Dedication Fees 767,094 763,941 1,011,000 750,000 750,000 750,000 750,000 750,000 Interest 122,895 30,139 - - 13,000 13,700 9,900 13,100 Other-Grants 5,000,000 Miscellaneous - Refunds & Reimbursements 2,697 Total Revenue 1,892,686 794,080 2,039,000 750,000 5,763,000 1,263,700 759,900 763,100 EXPENDITURES Miscellaneous 90,670 36,913 East Ravine Neighborhood 500,000 500,000 500,000 Glacial Valley Park 1,048,538 187,476 113,120 Glacial Valley Park Building 4,299,248 157,316 Hamlet Park Expansion 51,169 Mississippi Dunes 1,041,492 42,267 7,000,000 2,000,000 7,000,000 Military Trailhead 200,000 Jack and Marlys Denzer Park 28,251 200,000 300,000 Oakwood Park 8,203 145 Parks - Master Planning 12,534 23,907 15,000 15,000 15,000 15,000 15,000 15,000 Oltman Middle School 8,166 3,000,000 Pine Tree Pond Park Improvements 500,000 Pine Tree Pond Court Replacement 30,000 Roberts Lake Neighborhood development 500,000 Still Ponds park development 500,000 Highway 61 trail planning 11,555 Trails as part of development 50,000 21,000 Total Expenditures 6,601,854 516,996 3,328,120 815,000 7,715,000 3,015,000 7,545,000 515,000 OTHER FINANCING SOURCES (USES) Bond Proceeds 4,816,062 (492,801) 2,300,000 2,000,000 1,500,000 7,000,000 Transfer from Park Improvement Fund - Transfer (to) park improvement & ED Trust (120,000) - - - - - Total other sources 4,816,062 (492,801) (120,000) 2,300,000 2,000,000 1,500,000 7,000,000 - Increase (decrease) in fund balance 106,894 (215,717) (1,409,120) 2,235,000 48,000 (251,300) 214,900 248,100 FB Beginning balance 147,658 254,552 38,835 (1,370,285) 864,715 912,715 661,415 876,315 FB Ending balance 254,552 38,835 (1,370,285) 864,715 912,715 661,415 876,315 1,124,415 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Park Trust Fund (570) Projected Financial Position 81 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Grants 8,382 36,831 88,674 31,502 - 50,000 - - Tree Mitigation-6489 118,281 - 40,000 40,000 40,000 40,000 40,000 40,000 Total Revenue 126,663 36,831 128,674 71,502 40,000 90,000 40,000 40,000 EXPENDITURES Landscape Initiative 125,191 119,141 120,000 80,000 100,000 120,000 100,000 100,000 Ravine Parkway Landscaping EPD and Jamaica Landscaping 71,450 Total Expenditures 125,191 190,591 120,000 80,000 100,000 120,000 100,000 100,000 Other Financing Sources (uses) Transfer In Transfer Out-EPD & Jamaica - - - - - - - - Total other sources - - - - - - - - Increase (decrease) in fund balance 1,472 (153,760) 8,674 (8,498) (60,000) (30,000) (60,000) (60,000) FB Beginning balance 687,108 688,580 534,820 543,494 534,996 474,996 444,996 384,996 FB Ending balance 688,580 534,820 543,494 534,996 474,996 444,996 384,996 324,996 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Landscape Initiative-in Fund 510 Projected Financial Position 82 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Property taxes 250,134 298,365 300,000 450,000 450,000 500,000 500,000 500,000 intergovernmental Tower Rental - PW Tower 90,921 104,053 64,700 66,600 68,600 70,700 72,800 75,000 Investment interest 9,610 8,702 12,000 - - - - - Miscellaneous 32,376 Total Revenue 350,665 443,496 376,700 516,600 518,600 570,700 572,800 575,000 EXPENDITURES Municipal building expenses 6,624 Shop & Wash Bay Modifications 500,000 City Hall Remodel 131,211 City Hall/Public Safety-Maintenance 178,950 142,100 250,850 219,900 446,171 Central Fire- Maintenance 33,183 76,580 70,364 2,325 Public Works-Maintenance 12,000 85,000 800,000 60,000 Total Expenditures 131,211 6,624 500,000 212,133 230,680 406,214 1,019,900 508,496 Other Financing Sources (uses) Interfund loan interest (23,350) (21,250) (19,150) (17,050) (14,950) (12,650) (10,025) (7,272) Interfund loan payment (210,000) (210,000) (210,000) (210,000) (210,000) (250,000) (275,000) (275,000) Funded with the IT & Roadway Maint Funds 97,700 63,110 Transfer from General Fund 5,302 Total other sources (228,048) (231,250) (229,150) (129,350) (224,950) (199,540) (285,025) (282,272) Increase (decrease) in fund balance (8,594) 205,622 (352,450) 175,117 62,970 (35,054) (732,125) (215,768) FB Beginning balance (2,284,769) (2,083,363) (1,667,741) (1,810,191) (1,425,074) (1,152,104) (937,158) (1,394,283) FB Ending balance (2,083,363) (1,667,741) (1,810,191) (1,425,074) (1,152,104) (937,158) (1,394,283) (1,335,051) Cash Balance at year-end 116,125 271,807 (80,643) 94,474 157,444 122,390 (609,735) (825,503) Interfund Payable at year-end 2,230,000 2,020,000 1,810,000 1,600,000 1,390,000 1,140,000 865,000 590,000 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Municipal Building Fund (525) Projected Financial Position 83 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Land sales 617,313 Donation 150,000 150,002 Interest 282,792 203,040 67,800 55,900 72,200 70,900 69,600 68,200 South District Assessments 981,536 244,347 1,343,122 1,121,896 Miscellaneous 105 210 Total Revenue 2,031,746 597,599 1,410,922 1,177,796 72,200 70,900 69,600 68,200 EXPENDITURES Professional Services 686 60,000 60,000 60,000 60,000 60,000 60,000 Jamaica & 95th Intersection Improve.330,000 CSAH 19 and TH 61 666,500 430,000 South District Street & Utility 689,085 3,633,454 Total Expenditures 689,085 3,634,140 1,056,500 490,000 60,000 60,000 60,000 60,000 Other Financing Sources (uses) Interfund loan interest 44,847 Interfund loan payment Transfer in for South District 626,020 Transfer to EDA Fund (312,500) - (1,150,000) 400,000 (100,000) (100,000) (100,000) (100,000) Total other sources (312,500) 670,867 (1,150,000) 400,000 (100,000) (100,000) (100,000) (100,000) Increase (decrease) in fund balance 1,030,161 (2,365,674) (795,578) 1,087,796 (87,800) (89,100) (90,400) (91,800) FB Beginning balance 5,858,244 6,888,405 4,522,731 3,727,153 4,814,949 4,727,149 4,638,049 4,547,649 Goal 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 5,000,000 Cash Balance 4,341,553 2,504,929 3,464,388 4,631,684 4,551,384 4,469,784 4,386,884 4,302,584 Capital Improvement Plan 2026-2030 ED Trust Fund (286) Projected Financial Position 84 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Municipal State Aid Construction funds 5,985,250$ 310,201$ 718,216$ 6,633,702$ 1,000,000$ 5,875,000$ LRIP 1,187,500$ Special assessments 6,103 5,826 5,700 Intergovernmental - Federal funding Shoppes at CV 3,000,000 Intergovernmental - Federal funding 80th Street 5,000,000 Intergovernmental - Federal funding 103rd St RR Bridge 6,400,000 Intergovernmental - Federal funding SS4A 352,000 Intergovernmental - State-MNDOT-80th Street 1,012,184 5,286,000 Intergovernmental-Washington County 2,000,000 Assessment/Development Fees 5,011,600 1,200,000 2,150,000 1,869,000 271,000 Interest 46,560 131,313 11,200 - 12,200 12,400 12,600 12,800 Miscellaneous - Grant-Other 6,223 150,000 150,000 800,000 Total Revenue 7,225,413 1,465,747 735,116 27,433,302 1,362,200 3,962,400 1,881,600 12,558,800 EXPENDITURES Professional services-miscellaneous 15 71,531 Safe Streets and Roads for All 440,000 103rd Street Railroad Bridge 150,000 150,000 800,000 8,000,000 80th Street (Ideal to Hwy 61) 59,401 186,005 665,006 17,290,100 80th Street (80th/Keats roundabout)-SROP Approved 4,000,000 East Point Douglas - Jamaica intersection 7,905,857 3,886,847 500,000 Ravine Pkwy - Shoppes at Cottage View 4,223,000 2,527,000 4,343,000 1,353,000 Jamaica Avenue and 95th Intersection Improvements 443,000 Jamaica Ave - 80th to 90th 1,356,943 Ravine Parkway 223,522 250,000 3,200,000 1,200,000 1,000,000 1,000,000 200,000 River Oaks Hwy 61 RCUT 138,896 1,348,758 Total Expenditures 8,327,691 6,850,084 1,858,006 29,303,100 1,350,000 4,327,000 5,343,000 9,553,000 OTHER FINANCING SOURCES (USES) Bond Proceeds 4,744,996 377,000 2,760,000 860,000 Transfers in 1,595,025 443,000 3,080,500 714,000 222,000 Transfers out - CSAH 19 & TH 61 (4,075,000) Total other sources - 6,340,021 443,000 3,080,500 - 377,000 3,474,000 (2,993,000) Increase (decrease) in fund balance (1,102,278) 955,684 (679,890) 1,210,702 12,200 12,400 12,600 12,800 Beginning balance, FB 431,429 (670,849) 284,835 (395,055) 815,647 827,847 840,247 852,847 MSA Beginning Balance 1,195,043 (3,705,538) (1,862,873) 0 (4,000,000) (1,305,700) 388,600 3,082,900 Allocation 1,968,470 2,137,127 2,581,089 2,633,702 2,694,300 2,694,300 2,694,300 2,694,300 Disbursements (6,869,051) (294,462) (718,216) (6,633,702) - (1,000,000) - (5,875,000) MSA Ending Balance (3,705,538) (1,862,873) 0 (4,000,000) (1,305,700) 388,600 3,082,900 (97,800) City of Cottage Grove, MN Capital Improvement Plan 2026-2030 MSA Construction Fund (520) Projected Financial Position 85 2025 2026 2027 2028 2029 2030 ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Special Asessments-Developer Fees 1,485,000$ Intergovernmental - Federal funding 19 & 61 19,000,000 19,000,000 14,033,000 Intergovernmental - County 19 & 61 250,000 2,971,250 728,750 4,075,000 Interest Miscellaneous Total Revenue - 250,000 21,971,250 19,728,750 - 19,593,000 EXPENDITURES Prof Svcs - assmt fees CSAH 19 and TH 61 680,000 27,742,500 23,077,500 22,900,000 Harkness Avenue reconcstruction 3,162,000 Jamaica Ave - Rose of Sharon to Military 3,000,000 Total Expenditures - 680,000 27,742,500 26,077,500 - 26,062,000 Revenue over Expenditures - (430,000) (5,771,250) (6,348,750) - (6,469,000) Other Financing Sources (uses) Bond proceeds 2,621,250 3,198,750 938,000 Transfers from Area Funds 3,150,000 3,150,000 1,456,000 Transfer from MSA Fund 4,075,000 Transfers from ED Trust 430,000 Total other sources - 430,000 5,771,250 6,348,750 - 6,469,000 Increase (decrease) in fund balance - - - - - - FB Beginning balance - - - - - - City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Street Reconstruction and Overlay Fund Projected Financial Position 86 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED $$$$$$$$ REVENUES Special Assessments 21 42 Interest 158,869 155,970 26,100 34,800 35,400 35,900 36,400 37,000 Miscellaneous Total Revenue 158,890 156,012 26,100 34,800 35,400 35,900 36,400 37,000 EXPENDITURES 1,485,694 PM 2025-Hidden Valley 2,699,000 PM 2026 - Thompson Grove Estates 11th Add, south part Woodridge Park Add (W of Jamaica)3,415,000 PM 2027 - East Point Douglas (Inwood to CDS), Kingsborough Trail 3,508,000 PM 2028 - Thompson Grove Estates 12 Add, north part Woodridge Park Add (W of Jamaica)3,766,000 PM 2029 - Thompson Grove Estates and Hillside Trail 6,066,000 PM 2030 - Pine Glen, Cottage Grove Estates 8,126,000 Total Expenditures 3,547,055 1,485,694 2,699,000 3,415,000 3,508,000 3,766,000 6,066,000 8,126,000 Revenue over Expenditures (3,388,165) (1,329,682) (2,672,900) (3,380,200) (3,472,600) (3,730,100) (6,029,600) (8,089,000) Other Financing Sources (uses) Bond proceeds 2,994,722 1,025,000 2,303,000 2,420,000 2,945,000 2,668,000 4,485,000 7,036,000 Transfers from utility funds 563,729 47,251 396,000 995,000 563,000 1,098,000 1,581,000 1,090,000 Total other sources 3,558,451 1,072,251 2,699,000 3,415,000 3,508,000 3,766,000 6,066,000 8,126,000 Increase (decrease) in fund balance 170,286 (257,431) 26,100 34,800 35,400 35,900 36,400 37,000 FB Beginning balance 2,384,140 2,554,426 2,296,995 2,323,095 2,357,895 2,393,295 2,429,195 2,465,595 FB Ending balance 2,554,426 2,296,995 2,323,095 2,357,895 2,393,295 2,429,195 2,465,595 2,502,595 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Pavement Management Fund (560) Projected Financial Position 87 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Developer fees 677,066$ 500,388$ 761,000$ 761,000$ 761,000$ 761,000$ 761,000$ 761,000$ Special Assessments Intergovernmental - County/State 40,000 Interest 199,567 215,885 200,000 60,000 61,300 48,700 35,900 36,800 Miscellaneous Total Revenue 876,633 756,273 961,000 821,000 822,300 809,700 796,900 797,800 EXPENDITURES East Ravine Infrastructure Development 18,000 17,000 17,000 17,000 17,000 17,000 Miscellaneous 5,911 12,000 Water Comp Plan 36,916 Water Main Oversizing 74,743 55,249 67,500 7,000 7,000 7,000 7,000 7,000 South District Street & Utilities 708,007 Ravine Pkwy - Shoppes at Cottage View 489,200 285,600 88,800 CSAH 19 & TH 61 1,215,000 1,215,000 Ravine Parkway I & II 87,960 Harkness Avenue 485,400 Jamaica Avenue & 95th Intersection 100,000 Industrial Park Water Tower 7,310 100th St watermain 66,799 Total Expenditures 981,735 61,160 197,500 513,200 1,239,000 1,239,000 309,600 598,200 OTHER FINANCING SOURCES (USES) Bond Proceeds Transfers in Transfers out (237,909) (118,540) (1,000,000) (224,100) (424,375) (425,750) (421,500) (421,625) Total other sources (237,909) (118,540) (1,000,000) (224,100) (424,375) (425,750) (421,500) (421,625) Increase (decrease) in fund balance (343,011) 576,573 (236,500) 83,700 (841,075) (855,050) 65,800 (222,025) FB Beginning balance 4,005,715 3,662,704 4,239,277 4,002,777 4,086,477 3,245,402 2,390,352 2,456,152 FB Ending balance 3,662,704 4,239,277 4,002,777 4,086,477 3,245,402 2,390,352 2,456,152 2,234,127 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Water Area Fund (575) Projected Financial Position 88 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Developer fees 552,117$ 523,733$ 774,200$ 700,000$ 700,000$ 700,000$ 700,000$ 700,000$ Special Assessments - - - - - - - - Intergovernmental - County/State/Federal (66,481) - - - - - - - Interest 5,017 - 20,000 20,100 25,600 24,600 23,500 31,100 Miscellaneous - - 209,100 - - - - - Total Revenue 490,653 523,733 1,003,300 720,100 725,600 724,600 723,500 731,100 EXPENDITURES East Ravine Infrastructure Development 74,157 17,000 17,000 17,000 17,000 17,000 17,000 Miscellaneous 13,077 34,209 Comp Plan 40,660 South District Street & Utilities 874,379 Ravine Pkwy - Shoppes at Cottage View 330,210 192,780 59,940 CSAH 19 & TH 61 770,000 770,000 Lift Stations 18,970 Harkness Avenue 485,300 Trunk sewer extension - Met council 1,152 Trunk Oversizing 7,000 7,000 7,000 7,000 7,000 7,000 Total Expenditures 1,022,395 34,209 24,000 354,210 794,000 794,000 216,780 569,240 OTHER FINANCING SOURCES (USES) Debt Service - principal & interest - - - - - - - - Transfers in Transfers out (192,536) Total other sources - (192,536) - - - - - - Increase (decrease) in fund balance (531,742) 296,988 979,300 365,890 (68,400) (69,400) 506,720 161,860 FB Beginning balance 596,180 64,438 361,426 1,340,726 1,706,616 1,638,216 1,568,816 2,075,536 FB Ending balance 64,438 361,426 1,340,726 1,706,616 1,638,216 1,568,816 2,075,536 2,237,396 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Sewer Area Fund (580) Projected Financial Position 89 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES Developer fees 555,074$ 656,326$ 998,600$ 700,000$ 700,000$ 700,000$ 700,000$ 700,000$ Special Assessments 7,754 Intergovernmental - County/State Interest 48,849 13,908 10,000 7,000 11,200 - - - Miscellaneous 7,000 Total Revenue 611,677 670,234 1,015,600 707,000 711,200 700,000 700,000 700,000 EXPENDITURES East Ravine Infrastructure Development 4,335 10,000 17,000 17,000 17,000 17,000 17,000 TG-14 10,060 4,158 91,800 L-P3 Pond Improvements 87,082 24,901 800 East Ravine infrastructure & AUAR 224,728 Kwik Trip-95th & Jamaica 40,733 4,900 100th Street Extension 35,744 Miscellaneous 308 59,450 28,400 Jamaica Avenue-Trunk storm sewer realignment 300,513 21,300 South District Trunk Storm Sewer 65,267 15,662 South District Street & Utilities 867,166 CSAH 19 & TH 61 1,165,000 1,165,000 Ravine Pkwy - Shoppes at Cottage View 403,590 235,620 73,260 Lake Flora Ponds 490,327 Harkness Avenue 485,300 Trunk Oversizing 24,407 70,400 7,000 7,000 7,000 7,000 7,000 West draw modeling 16,422 16,100 Total Expenditures 1,780,682 490,581 243,700 427,590 1,189,000 1,189,000 259,620 582,560 OTHER FINANCING SOURCES (USES) Transfers in - 95th &Jamaica Transfers in (out)(314,944) Total other sources - (314,944) - - - - - - Increase (decrease) in fund balance (1,169,005) (135,291) 771,900 279,410 (477,800) (489,000) 440,380 117,440 FB Beginning balance 999,281 (169,724) (305,015) 466,885 746,295 268,495 (220,505) 219,875 FB Ending balance (169,724) (305,015) 466,885 746,295 268,495 (220,505) 219,875 337,315 City of Cottage Grove, MN Capital Improvement Plan 2026-2030 Storm Water Area Fund (585) Projected Financial Position 90 2023 2024 2025 2026 2027 2028 2029 2030 ACTUAL ACTUAL ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED ESTIMATED REVENUES 3M Settlement funds 16,781,220$ 29,717,773$ 38,312,758$ 34,045,192$ 30,045,192$ 12,518,830$ 4,003,766$ -$ Interest - - - - - - - - Miscellaneous Total Revenue 16,781,220 29,717,773 38,312,758 34,045,192 30,045,192 12,518,830 4,003,766 - EXPENDITURES Prior Year Projects 17,328,462 30,505,296 2,713,500 High Zone Raw Water Main 5,120,500 Low Zone Water Treatment Plant & Well 13 14,000,000 Intermediate Zone Water Treatment Plant 15,022,620 30,045,192 30,045,192 12,518,830 2,503,766 Intermediate Zone Raw Water Line 3,000,000 Well 1 & 2 Decommissioning 1,000,000 Well 3,7,8 Interim Treatment Plant Decommissioning 1,500,000 Total Expenditures 17,328,462 30,505,296 36,856,620 34,045,192 30,045,192 12,518,830 4,003,766 - OTHER FINANCING SOURCES (USES) Bond Proceeds Transfers in Transfers out Total other sources - - - - - - - - Increase (decrease) in fund balance (547,242) (787,523) 1,456,138 - - - - - FB Beginning balance (121,373) (668,615) (1,456,138) - - - - - FB Ending balance (668,615) (1,456,138) - - - - - - City of Cottage Grove, MN Capital Improvement Plan 2026-2030 3M Settlement/MPCA Fund 455 Projected Financial Position 91 Bond Issuance Amounts Identified in 2026-2030 CIP Capital Improvement Plan 2026-2030 Project 2026 2027 2028 2029 2030 Total Pavement Management 2,420,000 3,045,000 2,668,000 4,585,000 7,136,000 19,854,000 CSAH 19 & TH 61 2,621,250 198,750 2,820,000 Shoppes at Cottage View 377,000 2,760,000 860,000 3,997,000 Harkness Avenue 938,000 938,000 Jamaica (Rose of Sharon to Military)3,000,000 3,000,000 Oltman-lacrosse complex&parking lot 2,300,000 2,300,000 Kingston Park 5,000,000 5,000,000 Ice Arena 1,500,000 1,500,000 Dunes Park 2,000,000 1,500,000 7,000,000 10,500,000 Equipment 1,310,000 345,000 1,655,000 Bond Issuance Amounts Identified in FMP Project 2026 2027 2028 2029 2030 Total Pavement Management 2,420,000 3,045,000 2,668,000 3,918,000 6,229,000 18,280,000 CSAH 19 & TH 61 2,621,250 198,750 2,820,000 Shoppes at Cottage View 377,000 2,760,000 860,000 3,997,000 Harkness Avenue 938,000 938,000 Jamaica (Rose of Sharon to Military)3,000,000 3,000,000 Oltman-lacrosse complex&parking lot 2,300,000 2,300,000 Kingston Park 5,000,000 5,000,000 Ice Arena - Dunes Park - Equipment 1,310,000 345,000 1,655,000 92